Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Bridge at Village Lakhi Chufuliya Guard Work Completed
Project: UDRP-AF(Bridge/Slope) UID: 4075 Sanction Cost: 420.31  lakh Span: 45.000 M
District: Chamoli Block: Ghat Constituency: Tharali Circle:
DEA: DEA Karanprayag DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision Type: Bridge
Procurement:
Package No.: 625        Package Name:  UDRP/AF/BR/60        Tender Date: 26-09-2019        Current Status: Agreement signed        Achieved on Date: 22-01-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/60      Contractor Name: M/S.KGL Infrastructure
Start Date:  01-02-2020      Intended Completion Date:  06-11-2021      Original End Date:  30-04-2021
Total Bond Cost: 42080243.41 (420.8 lakh)        Variation Cost: -3225018.71 (-32.25 lakh)    Hence Total Bond Cost is   38855224.7 (388.55 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 9089280 for 432 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Env. Man & Moni Plan1.00 Job4.2201-02-202006-11-20211.00 Job1.00 Job1.034.22
2.Other Allied Works & Finishing Work 1.00 Job3.4530-10-202025-10-20211.00 Job1.00 Job0.843.45
3.Foundation RHS2.00 Job36.9801-08-202030-10-20202.00 Job2.00 Job8.9936.98
4.Foundation LHS2.00 Job36.9801-02-202030-10-20202.00 Job2.00 Job8.9936.98
5.Abutment Superstructure RHS1.00 Job0.2222-09-202005-08-20211.00 Job1.00 Job0.050.22
6.Abutment Superstructure LHS1.00 Job0.2221-11-202005-08-20211.00 Job1.00 Job0.050.22
7.Fixing of chequered Plate/RCC Deck89.21 sqm2.8901-02-202116-07-202189.21 sqm89.21 sqm0.72.89
8.Steel Railing/crush barrier91.20 m2.4801-06-202110-08-202191.20 m91.20 m0.62.48
9.Approach Ramp /path 120.00 m34.9031-08-202125-10-2021120.00 m120.00 m8.4834.90
10.Protection Work1.00 Job21.5520-02-202125-10-20211.00 Job1.00 Job5.2421.55
11.Errection Work1.00 Job46.1705-01-202115-07-20211.00 Job1.00 Job11.2246.17
12.Gabion work334.00 m34.8020-01-202125-10-2021334.00 m334.00 m8.4634.80
13.Fabrication Work1.00 job62.0815-09-202028-01-20211.00 job1.00 job15.0962.08
14.Abutment Substructure RHS1.00 Job60.3301-11-202030-01-20211.00 Job1.00 Job14.6660.33
15.Abutment Substructure LHS1.00 Job60.3311-11-202016-02-20211.00 Job1.00 Job14.6660.33
16.Fixing Bearing/Slab Casting1.00 job3.8201-08-202105-08-20211.00 job1.00 job0.933.82
Total Amount: 411.42 100   411.42
Remarks: No Remarks       Work Program Made On: 06-07-2020        Updation of work program on: 11-11-2021       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.11-November-202023.20  lakh
2.04-December-20202.78  lakh
3.04-February-2021128.13  lakh
4.27-February-202134.69  lakh
5.26-March-202118.76  lakh
6.31-May-202174.80  lakh
7.23-June-202136.26  lakh
8.31-July-202112.23  lakh
9.21-October-202145.20  lakh
10.31-March-20226.99  lakh
Total 383.04  lakh
% Payment 98.59 %
Advance Amount:  36.82  lakh        Recovered Amount:  36.82  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 1729   No. of Test Done : 1756    No. of Test Passed : 1753   No. of Test Failed : 3   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 90.06
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 100
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.26-04-2022Lakhi-Chufliya Bridge site BR/60World Bank Team visit at site for InspectionEr.Vipin Tomar ,AE ` ` See Pic
2.26-01-2022Lakhi chufliyaA2side approach RoadRohit Kumar dubey ` ` See Pic
3.26-01-2022A1 side Approach RoadLakhi chufliyaRohit Kumar dubey ` ` See Pic
4.26-01-2022BridgeLakhi chafliyaRohit Kumar dubey ` ` See Pic
5.26-01-2022Completed bridgeLakhi chufliyaRohit Kumar dubey ` ` See Pic
6.29-12-2021Lakhi-Chufliya Bridge site BR/60Joint Inspection visit with Civil Division PWD Karnprayag Chamoli.Er. Vipin Tomar ` ` See Pic
7.18-11-2021Br/45 Vijaynagar TailaSite visit with Environment Expert Anju Pnawar from PIU Head-Office DehradunEr. Vipin Tomar AE ` ` See Pic
8.08-11-2021Lakhi chufliyaParapet work in progress.Manendra singh ` ` See Pic
9.07-11-2021Lakhi chufliyaParapet work in progress.Manendra singh ` ` See Pic
10.07-11-2021Lakhi chufliyaParfait work in progressManendra ` ` See Pic
11.30-10-2021Lakhi chufliyaPainting work in progressManendra singh ` ` See Pic
12.26-10-2021Lakhi chufliyaPanting work in progress BR60 bridgeManendra singh ` ` See Pic
13.16-10-2021BR60Curing for approach roadRohit Kumar Dubey ` ` See Pic
14.16-10-2021BR60Approach road work in progressRohit Kumar Dubey ` ` See Pic
15.29-09-2021A2 side RHS sideDe-shuttering work in progressVipin Tomar AE ` ` See Pic
16.23-07-2021Lakhi chuflagaad bridge br 60A1 side pedestal concreting work in progressManendra ` ` See Pic
17.26-06-2021At siteErection work under progressVipin Tomar AE ` ` See Pic
18.26-06-2021A2 side (RHS Side)Erection work under progress.Vipin Tomar AE ` ` See Pic
19.26-06-2021BR60Erection work in progressRohit Kumar Dubey ` ` See Pic
20.25-06-2021A2 side RHS SIDEErection work under progressDhwajvir Singh AAE ` ` See Pic