Km 11 of Arakot Chinwa Balcha MR
Work Completed
|
Project: |
UDRP-AF(Bridge/Slope) |
UID: |
4072 |
Sanction Cost: |
403.85 lakh |
Span:
|
42.000 M |
District: |
Uttarkashi |
Block: |
Mori |
Constituency: |
Purola |
Circle: |
|
DEA: |
DEA Uttarkashi |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
Type: |
Bridge |
|
Procurement: |
Package No.: 624
Package Name: 
UDRP/AF/BR/59
Tender Date: 26-09-2019
Current Status: Agreement signed
Achieved on Date: 22-01-2020 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/BR/59
Contractor Name: Tons Builderes
|
Start Date: 01-02-2020
Intended Completion Date: 04-11-2021
Original End Date: 30-04-2021 |
Total Bond Cost: 37571580.54 (375.72 lakh)
Variation Cost: 9661622.05 (96.62 lakh) Hence Total Bond Cost is 47233202.59 (472.33 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 5880018 for 313 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Other Allied Works & Finishing Work | 1.00 Job | 9.04 | 11-06-2021 | 03-11-2021 | 1.00 Job | 1.00 Job | 2.69 | 9.04 | 2. | Foundation RHS | 1.00 Job | 10.32 | 10-02-2020 | 25-08-2020 | 1.00 Job | 1.00 Job | 3.08 | 10.32 | 3. | Foundation LHS | 1.00 Job | 10.32 | 12-03-2020 | 25-09-2020 | 1.00 Job | 1.00 Job | 3.08 | 10.32 | 4. | Abutment Superstructure RHS | 1.00 Job | 14.56 | 15-04-2020 | 28-11-2020 | 1.00 Job | 1.00 Job | 4.34 | 14.56 | 5. | Abutment Superstructure LHS | 1.00 Job | 14.56 | 02-05-2020 | 01-12-2020 | 1.00 Job | 1.00 Job | 4.34 | 14.56 | 6. | Fixing of chequered Plate/RCC Deck | 1.00 sqm | 3.60 | 25-07-2021 | 05-09-2021 | 1.00 sqm | 1.00 sqm | 1.07 | 3.60 | 7. | Steel Railing/crush barrier | 1.00 m | 2.67 | 07-09-2021 | 30-09-2021 | 1.00 m | 1.00 m | 0.8 | 2.67 | 8. | Approach Ramp /path | 1.00 m | 20.47 | 27-01-2021 | 10-10-2021 | 1.00 m | 1.00 m | 6.1 | 20.47 | 9. | Protection Work | 1.00 Job | 19.70 | 27-01-2021 | 11-06-2021 | 1.00 Job | 1.00 Job | 5.87 | 19.70 | 10. | Errection Work | 1.00 Job | 59.76 | 25-10-2020 | 20-07-2021 | 1.00 Job | 1.00 Job | 17.82 | 59.76 | 11. | Fabrication Work | 1.00 job | 167.73 | 02-05-2020 | 12-11-2020 | 1.00 job | 1.00 job | 50 | 167.73 | 12. | Fixing Bearing/Slab Casting | 6.00 job | 2.72 | 25-04-2020 | 15-07-2020 | 6.00 job | 6.00 job | 0.81 | 2.72 |
Total Amount: |
335.45 |
|
100 |
335.45 |
|
Remarks:
No Remarks
Work Program Made On:
06-03-2020 } ?>
Updation of work program on:
30-05-2022
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 01-December-2020 | 188.33 lakh | 2. | 07-January-2021 | 19.11 lakh | 3. | 15-February-2021 | 20.69 lakh | 4. | 30-March-2021 | 81.11 lakh | 5. | 10-June-2021 | 72.94 lakh | 6. | 30-September-2021 | 39.30 lakh | 7. | 06-November-2021 | 35.77 lakh | 8. | 24-February-2022 | 15.08 lakh |
Total |
472.33 lakh |
% Payment |
99.99 % |
|
Advance Amount: 76.13 lakh
Recovered Amount: 76.13 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 470 No. of Test Done : 495 No. of Test Passed : 491 No. of Test Failed : 4 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 98.01 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 47 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 21-01-2022 | Construction of 42m span steel truss motor bridge at Aarakot chinwa motor road km 11 BR59 | Complete bridge | Mukesh Tyagi | ` | ` | See Pic |
2. | 16-11-2021 | Arakot chinwa motor bridge | Work completed at Arakot-chinwa motor bridge. | Abhishek tiwari | ` | ` | See Pic |
3. | 16-11-2021 | Arakot-chinwa motor bridge | Work completed at arakot-chinwa motor bridge. | Abhishek tiwari | ` | ` | See Pic |
4. | 16-11-2021 | Arakot-chinwa motor bridge | Arakot-chinwa motor bridge work completed. | Abhishek tiwari | ` | ` | See Pic |
5. | 16-11-2021 | Arakot-chinwa motor bridge | Arakot chinwa motor bridge completed. | Abhishek tiwari | ` | ` | See Pic |
6. | 29-10-2021 | BR59 arakot chinwa motor bridge | Bridge work has been completed | Manoj sain Qc | ` | ` | See Pic |
7. | 29-10-2021 | BR59 arakot chinwa motor bridge | Bridge work complted , curing work is in progress | Manoj sain Qc | ` | ` | See Pic |
8. | 29-10-2021 | BR59 arakot chinwa motor bridge | Bridge work completed , curing work is in progress | Manoj sain Qc | ` | ` | See Pic |
9. | 29-10-2021 | BR59 arakot chinwa motor bridge | Bridge work has been completed | Manoj sain Qc | ` | ` | See Pic |
10. | 19-10-2021 | Arakot chinwa BR59 | Slump test for deck slab concrete | Manoj sain | ` | ` | See Pic |
11. | 01-10-2021 | Arakot motor bridge | Reinforcement of deck slab is in progress at arakot chinwa motor bridge. | Abhishek tiwari | ` | ` | See Pic |
12. | 01-10-2021 | Arakot chinwa motor bridge | Fixation of expansion joint is in progress at arakot-chinwa motor bridge in district Uttarkashi. | Abhishek tiwari | ` | ` | See Pic |
13. | 17-08-2021 | Arakot bridge | Work in progress | AAE CL Bharti | ` | ` | See Pic |
14. | 16-08-2021 | BR59 | At location arakot chinwa slop checking of Abutement A1 side approach road . | Manoj sain | ` | ` | See Pic |
15. | 08-07-2021 | A2 pedestal | Curing of A2 pedestal | AAE C.L.Bharti | ` | ` | See Pic |
16. | 07-07-2021 | Arakot Chinwa motor Bridge BR 59 | Pedestals casting after fixing and leveling of Bearing. | Manoj sain | ` | ` | See Pic |
17. | 05-07-2021 | Construction of 42m span steel truss motor bridge at km. 11 of Aarkot chinwa motor road in distt uttarkashi | Checking of levels for bearings | Sandeep kumar | unknown | unknown | See Pic |
18. | 27-06-2021 | Arakot motor bridge | Panting work in progress | AAE C.L.Bharti | ` | ` | See Pic |
19. | 27-06-2021 | Arakot Bridge | Bearing reached at Site. | AAE C.L.Bharti | ` | ` | See Pic |
20. | 17-03-2021 | Arakot bridge | Medical Health checkup camp | C.L.Bharti | ` | ` | See Pic |
|
|