Over Bhagirathi River at Harsil
Agreement signed
|
Project: |
UDRP-AF(Bridge/Slope) |
UID: |
4071 |
Sanction Cost: |
530.95 lakh |
Span:
|
42.000 M |
District: |
Uttarkashi |
Block: |
Bhatwari |
Constituency: |
Gangotri |
Circle: |
|
DEA: |
DEA Uttarkashi |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
Type: |
Bridge |
|
Procurement: |
Package No.: 630
Package Name: 
UDRP/AF/BR/69
Tender Date: 22-01-2020
Current Status: Agreement signed
Achieved on Date: 18-01-2021 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/BR/69
Contractor Name: M/s. Valley Construction Company Pvt.Ltd.
|
Start Date: 06-02-2021
Intended Completion Date: 30-07-2023
Original End Date: 31-03-2022 |
Total Bond Cost: 54397225.21 (543.97 lakh)
Variation Cost: 2904028.71 (29.04 lakh) Hence Total Bond Cost is 57301253.92 (573.01 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 22139986 for 814 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Other Allied Works & Finishing Work | 1.00 Job | 57.41 | 01-11-2022 | 30-11-2022 | 1.00 Job | 0.00 Job | 0 | 0.00 | 2. | Foundation RHS | 1.00 Job | 31.31 | 10-03-2021 | 30-07-2021 | 1.00 Job | 1.00 Job | 6.17 | 31.31 | 3. | Foundation LHS | 1.00 Job | 31.31 | 25-02-2021 | 25-07-2021 | 1.00 Job | 1.00 Job | 6.17 | 31.31 | 4. | Abutment Superstructure RHS | 1.00 Job | 19.41 | 11-04-2021 | 30-10-2021 | 1.00 Job | 1.00 Job | 3.83 | 19.41 | 5. | Abutment Superstructure LHS | 1.00 Job | 19.41 | 25-03-2021 | 30-10-2021 | 1.00 Job | 1.00 Job | 3.83 | 19.41 | 6. | Steel Railing/crush barrier | 1.00 m | 23.93 | 27-08-2022 | 30-09-2022 | 1.00 m | 0.00 m | 0 | 0.00 | 7. | Approach Ramp /path | 1.00 m | 19.62 | 21-08-2022 | 15-09-2022 | 1.00 m | 0.00 m | 0 | 0.00 | 8. | Protection Work | 1.00 Job | 21.98 | 15-04-2021 | 05-10-2022 | 1.00 Job | 0.20 Job | 0.87 | 4.40 | 9. | Errection Work | 1.00 Job | 73.57 | 16-07-2022 | 20-08-2022 | 1.00 Job | 0.00 Job | 0 | 0.00 | 10. | Fabrication Work | 1.00 job | 184.25 | 28-09-2021 | 15-07-2022 | 1.00 job | 0.40 job | 14.53 | 73.70 | 11. | Fixing Bearing/Slab Casting | 4.00 job | 25.01 | 21-08-2022 | 25-08-2022 | 4.00 job | 0.00 job | 0 | 0.00 |
Total Amount: |
507.21 |
|
35.4 |
179.54 |
|
Remarks:
No Remarks
Work Program Made On:
16-03-2021 } ?>
Updation of work program on:
25-05-2022
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 22-September-2021 | 44.52 lakh | 2. | 11-March-2022 | 41.58 lakh | 3. | 15-June-2022 | 8.43 lakh | 4. | 28-July-2022 | 9.25 lakh | 5. | 24-November-2022 | 13.55 lakh | 6. | 28-January-2023 | 33.61 lakh | 7. | 25-March-2023 | 67.24 lakh | 8. | 11-April-2023 | 48.37 lakh | 9. | 25-April-2023 | 70.25 lakh | 10. | 26-May-2023 | 44.87 lakh | 11. | 15-July-2023 | 41.84 lakh | 12. | 26-July-2023 | 13.78 lakh | 13. | 10-August-2023 | 6.36 lakh | 14. | 15-September-2023 | 33.81 lakh | 15. | 05-October-2023 | 51.41 lakh | 16. | 19-October-2023 | 33.55 lakh | 17. | 06-November-2023 | 59.58 lakh | 18. | 30-December-2023 | 28.52 lakh |
Total |
650.52 lakh |
% Payment |
113.52 % |
|
Advance Amount: 30.07 lakh
Recovered Amount: 27.26 lakh
Balance to be Recovered 2.81 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 159 No. of Test Done : 188 No. of Test Passed : 185 No. of Test Failed : 3 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 90.00 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 84 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 22-04-2022 | Harsil motor bridge | Shuttering of abutment A1 first lift is in progress. | Abhishek tiwari | ` | ` | See Pic |
2. | 22-04-2022 | Harsil motor bridge | Shuttering of abutment A2 2nd lift is in progress. | Abhishek tiwari | ` | ` | See Pic |
3. | 21-04-2022 | Harsil | A1,wall 1st lift concrete sampling done.concrete grade M35. | Niraj pathak | ` | ` | See Pic |
4. | 21-04-2022 | Harsil | A1, wall 1st lift concrete sampling done, concrete grade M35. | Niraj pathak | ` | ` | See Pic |
5. | 21-04-2022 | Harsil | A2,wall 2nd lift shuttering work in progress. | Niraj pathak | ` | ` | See Pic |
6. | 21-04-2022 | Harsil | A2,wall 2nd lift shuttering work in progress. | Niraj pathak | ` | ` | See Pic |
7. | 23-12-2021 | Harsil bridge A1 site | Excavation Abutment A1 | Arun kumar | ` | ` | See Pic |
8. | 23-12-2021 | Harsil bridge no-69 | Survey Abutment bagori side | Arun kumar | ` | ` | See Pic |
9. | 23-12-2021 | Harsil bridge no-69 | TS survey Abutment A2 | Arun kumar | ` | ` | See Pic |
10. | 23-12-2021 | Harsil bridge no-69 | TS servey | Arun kumar R.E | ` | ` | See Pic |
11. | 16-11-2021 | BR/69 | A2, footing concrete sampling work in progress, concrete grade M35. | Niraj pathak | unknown | unknown | See Pic |
12. | 16-11-2021 | BR/69 | Slump test is progress, concrete grade M35,A2 footing concrete. | Niraj pathak | unknown | unknown | See Pic |
13. | 11-10-2021 | Harsil Bridge Abutment Bagori A2 | Bridge no 69 | Arun kumar | ` | ` | See Pic |
14. | 29-09-2021 | Harshil Bridge | H.p Stone Filling Work in progress for Abutment R.H S Side ISt lift at 42m span steel Truss Bridge at Harshil District Uttarkashi | Yogesh Dobhal | ` | ` | See Pic |
15. | 11-09-2021 | Abutment A2 raft | Concreting of abutment A2 raft is in progress at harsil bridge in district Uttarkashi | Abhishek tiwari | ` | ` | See Pic |
16. | 11-09-2021 | Abutment A2 raft | Concreting of abutment A2 raft foundation is in progress at harsil bridge in district Uttarkashi | Abhishek tiwari | ` | ` | See Pic |
17. | 11-09-2021 | Abutment A2 raft | Concreting of abutment A2 raft foundation is in progress at harsil bridge in district Uttarkashi | Abhishek tiwari | ` | ` | See Pic |
18. | 11-09-2021 | Abutment A1 | PCC work of abutment A1 done. | Abhishek tiwari | ` | ` | See Pic |
19. | 11-09-2021 | Abutment A2 raft | Concreting of abutment A2 raft foundation is in progress at harsil bridge in district Uttarkashi | Abhishek tiwari | ` | ` | See Pic |
20. | 11-09-2021 | Abutment A2 | Concreting of abutment A2 raft foundation is in progress at harsil bridge in district Uttarkashi. | Abhishek tiwari | ` | ` | See Pic |
|
|