Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Over Bhagirathi River at Harsil Agreement signed
Project: UDRP-AF(Bridge/Slope) UID: 4071 Sanction Cost: 530.95  lakh Span: 42.000 M
District: Uttarkashi Block: Bhatwari Constituency: Gangotri Circle:
DEA: DEA Uttarkashi DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision Type: Bridge
Procurement:
Package No.: 630        Package Name:  UDRP/AF/BR/69        Tender Date: 22-01-2020        Current Status: Agreement signed        Achieved on Date: 18-01-2021

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/69      Contractor Name: M/s. Valley Construction Company Pvt.Ltd.
Start Date:  06-02-2021      Intended Completion Date:  30-07-2023      Original End Date:  31-03-2022
Total Bond Cost: 54397225.21 (543.97 lakh)        Variation Cost: 2904028.71 (29.04 lakh)    Hence Total Bond Cost is   57301253.92 (573.01 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 22139986 for 814 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Other Allied Works & Finishing Work 1.00 Job57.4101-11-202230-11-20221.00 Job0.00 Job00.00
2.Foundation RHS1.00 Job31.3110-03-202130-07-20211.00 Job1.00 Job6.1731.31
3.Foundation LHS1.00 Job31.3125-02-202125-07-20211.00 Job1.00 Job6.1731.31
4.Abutment Superstructure RHS1.00 Job19.4111-04-202130-10-20211.00 Job1.00 Job3.8319.41
5.Abutment Superstructure LHS1.00 Job19.4125-03-202130-10-20211.00 Job1.00 Job3.8319.41
6.Steel Railing/crush barrier1.00 m23.9327-08-202230-09-20221.00 m0.00 m00.00
7.Approach Ramp /path 1.00 m19.6221-08-202215-09-20221.00 m0.00 m00.00
8.Protection Work1.00 Job21.9815-04-202105-10-20221.00 Job0.20 Job0.874.40
9.Errection Work1.00 Job73.5716-07-202220-08-20221.00 Job0.00 Job00.00
10.Fabrication Work1.00 job184.2528-09-202115-07-20221.00 job0.40 job14.5373.70
11.Fixing Bearing/Slab Casting4.00 job25.0121-08-202225-08-20224.00 job0.00 job00.00
Total Amount: 507.21 35.4   179.54
Remarks: No Remarks       Work Program Made On: 16-03-2021        Updation of work program on: 25-05-2022       
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.22-September-202144.52  lakh
2.11-March-202241.58  lakh
3.15-June-20228.43  lakh
4.28-July-20229.25  lakh
5.24-November-202213.55  lakh
6.28-January-202333.61  lakh
7.25-March-202367.24  lakh
8.11-April-202348.37  lakh
9.25-April-202370.25  lakh
10.26-May-202344.87  lakh
11.15-July-202341.84  lakh
12.26-July-202313.78  lakh
13.10-August-20236.36  lakh
14.15-September-202333.81  lakh
15.05-October-202351.41  lakh
16.19-October-202333.55  lakh
17.06-November-202359.58  lakh
18.30-December-202328.52  lakh
Total 650.52  lakh
% Payment 113.52 %
Advance Amount:  30.07  lakh        Recovered Amount:  27.26  lakh        Balance to be Recovered  2.81  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level): No Pending Issue
Environment & Social Compliances(Sub Project level): EMP
Detailed report of this subproject
Quality
No. of Test Required : 159   No. of Test Done : 188    No. of Test Passed : 185   No. of Test Failed : 3   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 90.00
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 84
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.22-04-2022Harsil motor bridgeShuttering of abutment A1 first lift is in progress.Abhishek tiwari ` ` See Pic
2.22-04-2022Harsil motor bridgeShuttering of abutment A2 2nd lift is in progress.Abhishek tiwari ` ` See Pic
3.21-04-2022HarsilA1,wall 1st lift concrete sampling done.concrete grade M35.Niraj pathak ` ` See Pic
4.21-04-2022HarsilA1, wall 1st lift concrete sampling done, concrete grade M35.Niraj pathak ` ` See Pic
5.21-04-2022HarsilA2,wall 2nd lift shuttering work in progress.Niraj pathak ` ` See Pic
6.21-04-2022HarsilA2,wall 2nd lift shuttering work in progress.Niraj pathak ` ` See Pic
7.23-12-2021Harsil bridge A1 siteExcavation Abutment A1Arun kumar ` ` See Pic
8.23-12-2021Harsil bridge no-69Survey Abutment bagori sideArun kumar ` ` See Pic
9.23-12-2021Harsil bridge no-69TS survey Abutment A2Arun kumar ` ` See Pic
10.23-12-2021Harsil bridge no-69TS serveyArun kumar R.E ` ` See Pic
11.16-11-2021BR/69A2, footing concrete sampling work in progress, concrete grade M35.Niraj pathakunknownunknown See Pic
12.16-11-2021BR/69Slump test is progress, concrete grade M35,A2 footing concrete.Niraj pathakunknownunknown See Pic
13.11-10-2021Harsil Bridge Abutment Bagori A2Bridge no 69Arun kumar ` ` See Pic
14.29-09-2021Harshil BridgeH.p Stone Filling Work in progress for Abutment R.H S Side ISt lift at 42m span steel Truss Bridge at Harshil District UttarkashiYogesh Dobhal ` ` See Pic
15.11-09-2021Abutment A2 raftConcreting of abutment A2 raft is in progress at harsil bridge in district UttarkashiAbhishek tiwari ` ` See Pic
16.11-09-2021Abutment A2 raftConcreting of abutment A2 raft foundation is in progress at harsil bridge in district UttarkashiAbhishek tiwari ` ` See Pic
17.11-09-2021Abutment A2 raftConcreting of abutment A2 raft foundation is in progress at harsil bridge in district UttarkashiAbhishek tiwari ` ` See Pic
18.11-09-2021Abutment A1PCC work of abutment A1 done.Abhishek tiwari ` ` See Pic
19.11-09-2021Abutment A2 raftConcreting of abutment A2 raft foundation is in progress at harsil bridge in district UttarkashiAbhishek tiwari ` ` See Pic
20.11-09-2021Abutment A2Concreting of abutment A2 raft foundation is in progress at harsil bridge in district Uttarkashi.Abhishek tiwari ` ` See Pic