Bridge at KM-1 of Dhauntari Kamad MR
Work Completed
|
Project: |
UDRP-AF(Bridge/Slope) |
UID: |
4070 |
Sanction Cost: |
228.19 lakh |
Span:
|
24.000 M |
District: |
Uttarkashi |
Block: |
Dunda |
Constituency: |
Gangotri |
Circle: |
|
DEA: |
DEA Uttarkashi |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
Type: |
Bridge |
|
Procurement: |
Package No.: 618
Package Name: 
UDRP/AF/BR/41
Tender Date: 02-09-2019
Current Status: Agreement signed
Achieved on Date: 11-06-2020 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/BR/41
Contractor Name: Anil Mehta
|
Start Date: 01-07-2020
Intended Completion Date: 03-02-2022
Original End Date: 30-09-2021 |
Total Bond Cost: 19940526.2 (199.41 lakh)
Variation Cost: 934564.65 (9.35 lakh) Hence Total Bond Cost is 20875090.85 (208.75 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 219340 for 22 days
LD Analysis for Milestone2: calculated LD is Rs 697900 for 70 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Other Allied Works & Finishing Work | 1.00 Job | 6.33 | 12-09-2021 | 22-09-2021 | 1.00 Job | 1.00 Job | 3.56 | 6.33 | 2. | Foundation RHS | 1.00 Job | 7.05 | 30-10-2020 | 08-11-2020 | 1.00 Job | 1.00 Job | 3.96 | 7.05 | 3. | Foundation LHS | 1.00 Job | 7.05 | 06-11-2020 | 30-12-2020 | 1.00 Job | 1.00 Job | 3.96 | 7.05 | 4. | Abutment Superstructure RHS | 1.00 Job | 10.05 | 29-12-2020 | 28-02-2021 | 1.00 Job | 1.00 Job | 5.64 | 10.05 | 5. | Abutment Superstructure LHS | 1.00 Job | 10.05 | 01-01-2021 | 28-02-2021 | 1.00 Job | 1.00 Job | 5.64 | 10.05 | 6. | Fixing of chequered Plate/RCC Deck | 1.00 sqm | 10.97 | 10-07-2021 | 10-08-2021 | 1.00 sqm | 1.00 sqm | 6.16 | 10.97 | 7. | Steel Railing/crush barrier | 96.00 m | 3.71 | 25-08-2021 | 10-09-2021 | 96.00 m | 96.00 m | 2.08 | 3.71 | 8. | Approach Ramp /path | 1.00 m | 46.80 | 15-07-2021 | 30-08-2021 | 1.00 m | 1.00 m | 26.29 | 46.80 | 9. | Protection Work | 1.00 Job | 28.43 | 01-02-2021 | 30-08-2021 | 1.00 Job | 1.00 Job | 15.97 | 28.43 | 10. | Errection Work | 1.00 Job | 17.51 | 10-05-2021 | 05-07-2021 | 1.00 Job | 1.00 Job | 9.83 | 17.51 | 11. | Fabrication Work | 1.00 job | 28.26 | 15-07-2020 | 15-08-2020 | 1.00 job | 1.00 job | 15.87 | 28.26 | 12. | Fixing Bearing/Slab Casting | 4.00 job | 1.85 | 17-04-2021 | 25-07-2021 | 4.00 job | 4.00 job | 1.04 | 1.85 |
Total Amount: |
178.06 |
|
100 |
178.06 |
|
Remarks:
No Remarks
Work Program Made On:
04-02-2021 } ?>
Updation of work program on:
03-08-2021
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 23-January-2021 | 47.31 lakh | 2. | 30-March-2021 | 9.16 lakh | 3. | 23-June-2021 | 34.04 lakh | 4. | 03-August-2021 | 22.68 lakh | 5. | 07-September-2021 | 14.45 lakh | 6. | 20-January-2022 | 23.55 lakh | 7. | 24-February-2022 | 11.48 lakh | 8. | 31-May-2022 | 45.72 lakh |
Total |
208.39 lakh |
% Payment |
99.82 % |
|
Advance Amount: 12.03 lakh
Recovered Amount: 12.03 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 532 No. of Test Done : 674 No. of Test Passed : 667 No. of Test Failed : 7 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 90.00 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 169 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 14-05-2022 | Dhauntri Kamad | Complete | Ajay Singh Rana | ` | ` | See Pic |
2. | 13-05-2022 | 24m span Motor bridge Dhauntri Kamad | Painting complete | Ajay Singh Rana | ` | ` | See Pic |
3. | 12-05-2022 | Dhauntri-Kamad | Completed | Ajay Singh Rana | ` | ` | See Pic |
4. | 11-05-2022 | Bagigaon Gajna bridle bridge | Complete painting work | Ajay Singh Rana | ` | ` | See Pic |
5. | 06-05-2022 | Dhauntri kamad 24m span motor bridge | Painting work completed | Ajay Singh Rana | ` | ` | See Pic |
6. | 22-01-2022 | Dhauntri kamad km1 | Curing For Dack slab At dhauntri kamad motor bridge BR 41 | Deepak | ` | ` | See Pic |
7. | 31-12-2021 | BR/41 | Deck slab curring work in progress. | Niraj pathak | ` | ` | See Pic |
8. | 23-12-2021 | Br 41 dhauntri kamad bridge deck casting | Deck slab casting in progress | Arun kumar RE | ` | ` | See Pic |
9. | 20-12-2021 | BR/41 | Deck slab concrete sampling done.concrete grade,M35. | Niraj pathak | ` | ` | See Pic |
10. | 20-12-2021 | BR/41 | Deck slab concrete sampling work in progress. Concrete grade M35. | Niraj pathak | ` | ` | See Pic |
11. | 20-12-2021 | BR/41 | Deck slab concrete.slump test on progress, concrete grade M35. | Niraj pathak | ` | ` | See Pic |
12. | 20-12-2021 | BR/41 | Slump test on progress. Concrete grade M35.deck slab | Niraj pathak | ` | ` | See Pic |
13. | 20-12-2021 | BR/41 | Course aggregate gradation test on progress. | Niraj pathak | ` | ` | See Pic |
14. | 20-12-2021 | Dhautri kamad bridge | Deck slab work is on progress of M-35 grade | AE Pawan Kumar | unknown | unknown | See Pic |
15. | 20-12-2021 | Dhautri-kamad bridge | Slump test of deck slab M-35 Grade | AE Pawan Kumar | unknown | unknown | See Pic |
16. | 09-12-2021 | Dhauntri kamada km1 | Dirtwall casting A1 side at dhauntri kamad motor bridge BR/41 | Deepak | ` | ` | See Pic |
17. | 09-12-2021 | Dhauntri kamad km1 | Cube casting for Dirtwall A1 side At dhauntri kamad motor bridge BR/41 | Deepak | ` | ` | See Pic |
18. | 01-12-2021 | Dhauntri kamad km1 | Dirt wall concrete A1 side at dhauntri kamad motor bridge BR/41 | Deepak | ` | ` | See Pic |
19. | 25-11-2021 | Dhauntri kamad motor bridge | Deck slab shuttering work on progress | Ajay Singh Rana | ` | ` | See Pic |
20. | 24-11-2021 | BR/41 | A1,A2, pedestal concrete sampling work in progress.concrete grade M40. | Niraj pathak | ` | ` | See Pic |
|
|