Bridge in KM-3 of Sisaldi Satpuli MR
Work Completed
|
Project: |
UDRP-AF(Bridge/Slope) |
UID: |
4066 |
Sanction Cost: |
456.41 lakh |
Span:
|
45.000 M |
District: |
Pauri |
Block: |
Zahrikhal |
Constituency: |
Lansdowne |
Circle: |
|
DEA: |
DEA Pauri |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
Type: |
Bridge |
|
Procurement: |
Package No.: 614
Package Name: 
UDRP/AF/BR/37
Tender Date: 02-09-2019
Current Status: Agreement signed
Achieved on Date: 22-01-2020 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/BR/37
Contractor Name: M/S.ARKS Universal pvt.ltd
|
Start Date: 01-02-2020
Intended Completion Date: 18-03-2022
Original End Date: 30-04-2021 |
Total Bond Cost: 46758700.08 (467.59 lakh)
Variation Cost: -367948.17 (-3.68 lakh) Hence Total Bond Cost is 46390751.91 (463.91 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 12998724 for 556 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 0.11 KM | 7.83 | 20-07-2020 | 28-02-2022 | 0.11 KM | 0.11 KM | 1.66 | 7.83 | 2. | R/Wall, B/ Wall Type Protection works | 70.00 m | 16.91 | 15-12-2020 | 28-02-2022 | 70.00 m | 70.00 m | 3.59 | 16.91 | 3. | PC/CC i/c Prime Coat, Tack Coat | 0.15 KM | 1.29 | 01-02-2022 | 28-02-2022 | 0.15 KM | 0.15 KM | 0.27 | 1.29 | 4. | longitudinal Drain | 105.00 m | 1.23 | 10-02-2022 | 28-02-2022 | 105.00 m | 105.00 m | 0.26 | 1.23 | 5. | Crash Barrier | 94.00 m | 5.55 | 04-02-2022 | 28-02-2022 | 94.00 m | 94.00 m | 1.18 | 5.55 | 6. | Road Furniture | 4.00 No | 0.40 | 15-05-2020 | 22-12-2020 | 4.00 No | 4.00 No | 0.09 | 0.40 | 7. | Env. Man & Moni Plan | 1.00 Job | 2.86 | 01-02-2020 | 20-02-2022 | 1.00 Job | 1.00 Job | 0.61 | 2.86 | 8. | Other Allied Works & Finishing Work | 10.00 Job | 8.03 | 01-02-2020 | 28-02-2022 | 10.00 Job | 10.00 Job | 1.7 | 8.03 | 9. | Foundation RHS | 1.00 Job | 0.92 | 02-03-2020 | 07-09-2020 | 1.00 Job | 1.00 Job | 0.2 | 0.92 | 10. | Foundation LHS | 1.00 Job | 0.92 | 01-02-2020 | 30-07-2020 | 1.00 Job | 1.00 Job | 0.2 | 0.92 | 11. | Abutment Superstructure RHS | 1.00 Job | 19.83 | 30-10-2020 | 15-04-2021 | 1.00 Job | 1.00 Job | 4.2 | 19.83 | 12. | Abutment Superstructure LHS | 1.00 Job | 8.75 | 10-09-2020 | 31-03-2021 | 1.00 Job | 1.00 Job | 1.86 | 8.75 | 13. | Deck Cable laying, stretching and Fixing Transoms/Deck Slab | 1.00 no | 23.69 | 12-01-2022 | 25-02-2022 | 1.00 no | 1.00 no | 5.02 | 23.69 | 14. | Steel Railing/crush barrier | 0.00 m | 0.00 | 15-06-2021 | 28-02-2022 | 0.00 m | 0.00 m | 0 | 0.00 | 15. | Approach Ramp /path | 105.00 m | 2.83 | 05-01-2022 | 28-02-2022 | 105.00 m | 105.00 m | 0.6 | 2.83 | 16. | Protection Work | 1.00 Job | 5.78 | 05-06-2021 | 28-02-2022 | 1.00 Job | 1.00 Job | 1.22 | 5.78 | 17. | Errection Work | 1.00 Job | 132.06 | 01-08-2021 | 20-02-2022 | 1.00 Job | 1.00 Job | 27.99 | 132.06 | 18. | Gabion work | 150.00 m | 4.84 | 15-12-2020 | 01-11-2021 | 150.00 m | 150.00 m | 1.03 | 4.84 | 19. | PCC in Foundation | 13.62 cum | 0.98 | 05-09-2020 | 09-02-2022 | 13.62 cum | 13.62 cum | 0.21 | 0.98 | 20. | Fabrication Work | 1.00 job | 219.53 | 08-04-2021 | 05-06-2021 | 1.00 job | 1.00 job | 46.53 | 219.53 | 21. | Fixing Bearing/Slab Casting | 6.00 job | 4.57 | 05-01-2022 | 25-02-2022 | 6.00 job | 6.00 job | 0.97 | 4.57 | 22. | Wearing Coat | 9.88 Cum | 3.03 | 05-02-2022 | 28-02-2022 | 9.88 Cum | 9.88 Cum | 0.64 | 3.03 |
Total Amount: |
471.83 |
|
100 |
471.83 |
|
Remarks:
ERECTION ,BEARING FIXING,APPROACH ROAD AND DECK SLAB WORK IS IN PROGRESS
Work Program Made On:
05-12-2020 } ?>
Updation of work program on:
02-05-2022
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 31-March-2021 | 26.85 lakh | 2. | 29-July-2021 | 204.41 lakh | 3. | 31-August-2021 | 36.62 lakh | 4. | 02-November-2021 | 9.10 lakh | 5. | 28-December-2021 | 67.37 lakh | 6. | 21-February-2022 | 67.23 lakh | 7. | 31-May-2022 | 38.23 lakh | 8. | 15-June-2022 | 14.10 lakh |
Total |
463.91 lakh |
% Payment |
99.99 % |
|
Advance Amount: 41.75 lakh
Recovered Amount: 41.75 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 345 No. of Test Done : 350 No. of Test Passed : 348 No. of Test Failed : 2 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 98.98 |
Number of Notice(s) issued: 2 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 714 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 25-04-2022 | Br37 | Bridge work completed | Krishnan gopal | unknown | unknown | See Pic |
2. | 06-04-2022 | Br37 | Bridge work completed | Krishnan gopal | unknown | unknown | See Pic |
3. | 06-04-2022 | Br37 | Bridge work completed | Krishnan gopal | unknown | unknown | See Pic |
4. | 04-04-2022 | BR-37 | Bottom shuttring checking by R.E.sir for deck slab | Deepak Rawat | ` | ` | See Pic |
5. | 30-03-2022 | Br37 | RCC crash barrier completed | Krishnan gopal | unknown | unknown | See Pic |
6. | 30-03-2022 | Br37 | Downstream side crash barrier concrete work is in progress | Krishnan gopal | unknown | unknown | See Pic |
7. | 30-03-2022 | Br37 | Deck slab concrete work is in progress | Krishnan gopal | unknown | unknown | See Pic |
8. | 30-03-2022 | Br37 | Deck slab concrete work is in progress,slump checked and found satisfactory | Krishnan gopal | unknown | unknown | See Pic |
9. | 30-03-2022 | Br37 | Painting work is in progress | Krishnan gopal | unknown | unknown | See Pic |
10. | 30-03-2022 | Br37 | Deck slab work is in progress | Krishnan gopal | unknown | unknown | See Pic |
11. | 30-03-2022 | Br37 | Deck slab work is in progress | Krishnan gopal | unknown | unknown | See Pic |
12. | 30-03-2022 | Br37 | Expansion joint fixing work is in progress | Krishnan gopal | unknown | unknown | See Pic |
13. | 30-03-2022 | Br37 | Painting work is in progress | Krishnan gopal | unknown | unknown | See Pic |
14. | 30-03-2022 | Br37 | Gradation work | Krishnan gopal | unknown | unknown | See Pic |
15. | 30-03-2022 | Br37 | Deck slab crash barrier reinforcement work is in progress | Krishnan gopal | unknown | unknown | See Pic |
16. | 27-02-2022 | BR-37 | Deck Slab reinforcement Checking is in progress | Bharat Bhoosan Sharma | unknown | unknown | See Pic |
17. | 25-02-2022 | BR-37 | Curing at bearing pedestal | Deepak Rawat | ` | ` | See Pic |
18. | 24-02-2022 | BR-37 | Paint work is in progress | Deepak Rawat | ` | ` | See Pic |
19. | 24-02-2022 | BR-37 | Paint work is in progress | Deepak Rawat | ` | ` | See Pic |
20. | 24-02-2022 | BR-37 | Steel binding work is in progress | Deepak Rawat | ` | ` | See Pic |
|
|