Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Bridge in KM-3 of Sisaldi Satpuli MR Work Completed
Project: UDRP-AF(Bridge/Slope) UID: 4066 Sanction Cost: 456.41  lakh Span: 45.000 M
District: Pauri Block: Zahrikhal Constituency: Lansdowne Circle:
DEA: DEA Pauri DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision Type: Bridge
Procurement:
Package No.: 614        Package Name:  UDRP/AF/BR/37        Tender Date: 02-09-2019        Current Status: Agreement signed        Achieved on Date: 22-01-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/37      Contractor Name: M/S.ARKS Universal pvt.ltd
Start Date:  01-02-2020      Intended Completion Date:  18-03-2022      Original End Date:  30-04-2021
Total Bond Cost: 46758700.08 (467.59 lakh)        Variation Cost: -367948.17 (-3.68 lakh)    Hence Total Bond Cost is   46390751.91 (463.91 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 12998724 for 556 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence0.11 KM7.8320-07-202028-02-20220.11 KM0.11 KM1.667.83
2.R/Wall, B/ Wall Type Protection works70.00 m16.9115-12-202028-02-202270.00 m70.00 m3.5916.91
3.PC/CC i/c Prime Coat, Tack Coat0.15 KM1.2901-02-202228-02-20220.15 KM0.15 KM0.271.29
4.longitudinal Drain105.00 m1.2310-02-202228-02-2022105.00 m105.00 m0.261.23
5.Crash Barrier94.00 m5.5504-02-202228-02-202294.00 m94.00 m1.185.55
6.Road Furniture4.00 No0.4015-05-202022-12-20204.00 No4.00 No0.090.40
7.Env. Man & Moni Plan1.00 Job2.8601-02-202020-02-20221.00 Job1.00 Job0.612.86
8.Other Allied Works & Finishing Work 10.00 Job8.0301-02-202028-02-202210.00 Job10.00 Job1.78.03
9.Foundation RHS1.00 Job0.9202-03-202007-09-20201.00 Job1.00 Job0.20.92
10.Foundation LHS1.00 Job0.9201-02-202030-07-20201.00 Job1.00 Job0.20.92
11.Abutment Superstructure RHS1.00 Job19.8330-10-202015-04-20211.00 Job1.00 Job4.219.83
12.Abutment Superstructure LHS1.00 Job8.7510-09-202031-03-20211.00 Job1.00 Job1.868.75
13.Deck Cable laying, stretching and Fixing Transoms/Deck Slab 1.00 no23.6912-01-202225-02-20221.00 no1.00 no5.0223.69
14.Steel Railing/crush barrier0.00 m0.0015-06-202128-02-20220.00 m0.00 m00.00
15.Approach Ramp /path 105.00 m2.8305-01-202228-02-2022105.00 m105.00 m0.62.83
16.Protection Work1.00 Job5.7805-06-202128-02-20221.00 Job1.00 Job1.225.78
17.Errection Work1.00 Job132.0601-08-202120-02-20221.00 Job1.00 Job27.99132.06
18.Gabion work150.00 m4.8415-12-202001-11-2021150.00 m150.00 m1.034.84
19.PCC in Foundation13.62 cum0.9805-09-202009-02-202213.62 cum13.62 cum0.210.98
20.Fabrication Work1.00 job219.5308-04-202105-06-20211.00 job1.00 job46.53219.53
21.Fixing Bearing/Slab Casting6.00 job4.5705-01-202225-02-20226.00 job6.00 job0.974.57
22.Wearing Coat9.88 Cum3.0305-02-202228-02-20229.88 Cum9.88 Cum0.643.03
Total Amount: 471.83 100   471.83
Remarks: ERECTION ,BEARING FIXING,APPROACH ROAD AND DECK SLAB WORK IS IN PROGRESS       Work Program Made On: 05-12-2020        Updation of work program on: 02-05-2022       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.31-March-202126.85  lakh
2.29-July-2021204.41  lakh
3.31-August-202136.62  lakh
4.02-November-20219.10  lakh
5.28-December-202167.37  lakh
6.21-February-202267.23  lakh
7.31-May-202238.23  lakh
8.15-June-202214.10  lakh
Total 463.91  lakh
% Payment 99.99 %
Advance Amount:  41.75  lakh        Recovered Amount:  41.75  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 345   No. of Test Done : 350    No. of Test Passed : 348   No. of Test Failed : 2   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 98.98
Number of Notice(s) issued: 2

Mobile Pic Upload

Number of Pics Available on Web Repository: 714
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.25-04-2022Br37Bridge work completedKrishnan gopalunknownunknown See Pic
2.06-04-2022Br37Bridge work completedKrishnan gopalunknownunknown See Pic
3.06-04-2022Br37Bridge work completedKrishnan gopalunknownunknown See Pic
4.04-04-2022BR-37Bottom shuttring checking by R.E.sir for deck slabDeepak Rawat ` ` See Pic
5.30-03-2022Br37RCC crash barrier completedKrishnan gopalunknownunknown See Pic
6.30-03-2022Br37Downstream side crash barrier concrete work is in progressKrishnan gopalunknownunknown See Pic
7.30-03-2022Br37Deck slab concrete work is in progressKrishnan gopalunknownunknown See Pic
8.30-03-2022Br37Deck slab concrete work is in progress,slump checked and found satisfactoryKrishnan gopalunknownunknown See Pic
9.30-03-2022Br37Painting work is in progressKrishnan gopalunknownunknown See Pic
10.30-03-2022Br37Deck slab work is in progressKrishnan gopalunknownunknown See Pic
11.30-03-2022Br37Deck slab work is in progressKrishnan gopalunknownunknown See Pic
12.30-03-2022Br37Expansion joint fixing work is in progressKrishnan gopalunknownunknown See Pic
13.30-03-2022Br37Painting work is in progressKrishnan gopalunknownunknown See Pic
14.30-03-2022Br37Gradation workKrishnan gopalunknownunknown See Pic
15.30-03-2022Br37Deck slab crash barrier reinforcement work is in progressKrishnan gopalunknownunknown See Pic
16.27-02-2022BR-37Deck Slab reinforcement Checking is in progressBharat Bhoosan Sharmaunknownunknown See Pic
17.25-02-2022BR-37Curing at bearing pedestalDeepak Rawat ` ` See Pic
18.24-02-2022BR-37Paint work is in progressDeepak Rawat ` ` See Pic
19.24-02-2022BR-37Paint work is in progressDeepak Rawat ` ` See Pic
20.24-02-2022BR-37Steel binding work is in progressDeepak Rawat ` ` See Pic