Bridge on Chamasari Majhada MR
Work Completed
|
Project: |
UDRP-AF(Bridge/Slope) |
UID: |
4064 |
Sanction Cost: |
219.91 lakh |
Span:
|
30.000 M |
District: |
Dehradun |
Block: |
Raipur |
Constituency: |
Mussoorie |
Circle: |
|
DEA: |
DEA Tehri |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
Type: |
Bridge |
|
Procurement: |
Package No.: 615
Package Name: 
UDRP/AF/BR/38
Tender Date: 02-09-2019
Current Status: Agreement signed
Achieved on Date: 22-01-2020 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/BR/38
Contractor Name: M/S.ARKS Universal pvt.ltd
|
Start Date: 01-02-2020
Intended Completion Date: 23-07-2021
Original End Date: 31-01-2021 |
Total Bond Cost: 20027608.88 (200.28 lakh)
Variation Cost: 1046205.57 (10.46 lakh) Hence Total Bond Cost is 21073814.45 (210.74 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 3534942 for 353 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Other Allied Works & Finishing Work | 1.00 Job | 5.18 | 15-07-2020 | 30-04-2021 | 1.00 Job | 1.00 Job | 2.9 | 5.18 | 2. | Foundation RHS | 1.00 Job | 5.23 | 15-02-2020 | 15-09-2020 | 1.00 Job | 1.00 Job | 2.93 | 5.23 | 3. | Foundation LHS | 1.00 Job | 5.23 | 15-02-2020 | 30-09-2020 | 1.00 Job | 1.00 Job | 2.93 | 5.23 | 4. | Steel Railing/crush barrier | 62.40 m | 2.54 | 12-03-2021 | 20-03-2021 | 62.40 m | 62.40 m | 1.42 | 2.54 | 5. | Approach Ramp /path | 100.00 m | 35.24 | 15-10-2020 | 03-04-2021 | 100.00 m | 100.00 m | 19.71 | 35.24 | 6. | Protection Work | 1.00 Job | 21.56 | 15-10-2020 | 03-04-2021 | 1.00 Job | 1.00 Job | 12.06 | 21.56 | 7. | Errection Work | 1.00 Job | 16.24 | 25-11-2020 | 15-02-2021 | 1.00 Job | 1.00 Job | 9.08 | 16.24 | 8. | PCC in Foundation | 12.58 cum | 0.67 | 01-07-2020 | 30-07-2020 | 12.58 cum | 12.58 cum | 0.38 | 0.67 | 9. | Fabrication Work | 1.00 job | 44.48 | 25-07-2020 | 15-11-2020 | 1.00 job | 1.00 job | 24.88 | 44.48 | 10. | Abutment Substructure RHS | 1.00 Job | 17.01 | 15-09-2020 | 15-12-2020 | 1.00 Job | 1.00 Job | 9.51 | 17.01 | 11. | Abutment Substructure LHS | 1.00 Job | 17.01 | 16-11-2020 | 30-12-2020 | 1.00 Job | 1.00 Job | 9.51 | 17.01 | 12. | Fixing Bearing/Slab Casting | 1.00 job | 6.86 | 10-11-2020 | 10-03-2021 | 1.00 job | 1.00 job | 3.84 | 6.86 | 13. | Back Wall/ Approach slab | 1.00 job | 0.55 | 21-03-2021 | 28-03-2021 | 1.00 job | 1.00 job | 0.31 | 0.55 | 14. | Wearing Coat | 9.95 Cum | 0.99 | 28-03-2021 | 30-06-2021 | 9.95 Cum | 9.95 Cum | 0.56 | 0.99 |
Total Amount: |
178.79 |
|
100 |
178.79 |
|
Remarks:
No Remarks
Work Program Made On:
15-10-2020 } ?>
Updation of work program on:
12-08-2021
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 29-October-2020 | 29.02 lakh | 2. | 14-December-2020 | 33.91 lakh | 3. | 18-December-2020 | 25.67 lakh | 4. | 19-February-2021 | 33.18 lakh | 5. | 03-April-2021 | 29.88 lakh | 6. | 31-May-2021 | 17.66 lakh | 7. | 22-October-2021 | 26.34 lakh | 8. | 31-March-2022 | 15.07 lakh |
Total |
210.73 lakh |
% Payment |
99.99 % |
|
Advance Amount: 17.88 lakh
Recovered Amount: 17.88 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 330 No. of Test Done : 330 No. of Test Passed : 330 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 91.00 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 83 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 31-01-2022 | Km 2 | Bridge view from approach road | Ashish bhatt | ` | ` | See Pic |
2. | 31-01-2022 | Km 2 | Completed Chamasari Majhada bridge | Ashish bhatt | ` | ` | See Pic |
3. | 31-01-2022 | Chamasari-Majhara Bridge BR-38 | Chamasari-Majhara Bridge Down to upstream stream | Suresh Prasad | ` | ` | See Pic |
4. | 31-01-2022 | Chamasari-Majhara Bridge BR-38 | Chamasari-Majhara Bridge RHS side | Suresh Prasad | ` | ` | See Pic |
5. | 31-01-2022 | Chamasari-Majhara Bridge | Chamasari-Majhara Bridge completed open for traffic | Suresh Prasad | ` | ` | See Pic |
6. | 31-01-2022 | Chamasari-Majhara Bridge BR-38 | Chamasari-Majhara Bridge | Suresh Prasad | ` | ` | See Pic |
7. | 31-01-2022 | Chamasari-Majhara KM-02 BR-38 | Chamasari-Majhara Bridge Upstream to downstream | Suresh Prasad | ` | ` | See Pic |
8. | 31-01-2022 | Chamasari-Majhara KM-02 BR-38 | Chamasari-Majhara LHS side | SURESH PRASAD | ` | ` | See Pic |
9. | 17-09-2021 | Chamasari Majhada Steel girder Bridge Km 02 | Torque checking of 20 mm dia Bolt | Ashish Singh | ` | ` | See Pic |
10. | 01-09-2021 | Chamasari Majhada bridge Dehradun | Site inspection by CE Sir | Sudhir Kumar | ` | ` | See Pic |
11. | 14-08-2021 | Chamasari-Majhara KM-02 | Parapet A1 Side completed | Suresh Prasad | ` | ` | See Pic |
12. | 12-08-2021 | Chamasari-Majhara KM-02 | Parapet shuttering | Suresh Prasad | ` | ` | See Pic |
13. | 11-08-2021 | Chamasari-Majhara KM-02 | Protection work of approach road completed. | Deepak Rawat | unknown | unknown | See Pic |
14. | 03-08-2021 | Chamasari-Majhara Bridge KM-02 | Protection work in progress | Suresh Prasad | ` | ` | See Pic |
15. | 02-08-2021 | Chamasari-Majhara KM-02 | Protection work in progress | Suresh Prasad | ` | ` | See Pic |
16. | 20-07-2021 | Chamasari-Majhara BR-38 | Chamasari-Majhara Bridge Inspection | Suresh Prasad | ` | ` | See Pic |
17. | 20-07-2021 | Chamasari-Majhara | Bridge inspection | Suresh Prasad | ` | ` | See Pic |
18. | 07-07-2021 | Km 2 | Compacting approach via Roller | Ashiah Bhatt, S.S., UDRP- | unknown | unknown | See Pic |
19. | 05-07-2021 | 2km | Cube testing of crash barrier 28days | Waqil singh | unknown | unknown | See Pic |
20. | 05-07-2021 | Km 2 | B/wall work in progress | Ashiah Bhatt, S.S., UDRP- | unknown | unknown | See Pic |
|
|