Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Bridge on KM-7 of Agrakhal Kusraila MR Work Completed
Project: UDRP-AF(Bridge/Slope) UID: 4061 Sanction Cost: 218.42  lakh Span: 30.000 M
District: Tehri Block: Narendra Nagar Constituency: Narendra Nagar Circle:
DEA: DEA Tehri DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision Type: Bridge
Procurement:
Package No.: 632        Package Name:  UDRP/AF/BR/63        Tender Date: 11-10-2019        Current Status: Agreement signed        Achieved on Date: 12-02-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/63      Contractor Name: M/S Beer Chandra Ramola
Start Date:  20-02-2020      Intended Completion Date:  27-10-2021      Original End Date:  19-02-2021
Total Bond Cost: 20571232.64 (205.71 lakh)        Variation Cost: -2393377.63 (-23.93 lakh)    Hence Total Bond Cost is   18177855.01 (181.78 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 4278976 for 416 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Other Allied Works & Finishing Work 1.00 Job7.7801-12-202020-10-20211.00 Job1.00 Job3.787.78
2.Foundation RHS1.00 Job6.3201-03-202015-01-20211.00 Job1.00 Job3.076.32
3.Foundation LHS1.00 Job6.3220-02-202030-12-20201.00 Job1.00 Job3.076.32
4.Steel Railing/crush barrier110.00 m3.3301-07-202105-10-2021110.00 m110.00 m1.623.33
5.Approach Ramp /path 95.00 m45.3101-06-202115-10-202195.00 m95.00 m22.0345.31
6.Protection Work1.00 Job20.6510-01-202131-05-20211.00 Job1.00 Job10.0420.65
7.Errection Work1.00 Job20.9110-04-202120-05-20211.00 Job1.00 Job10.1620.91
8.Fabrication Work1.00 job49.8216-01-202131-03-20211.00 job1.00 job24.2249.82
9.Abutment Substructure RHS1.00 Job15.9805-01-202131-01-20211.00 Job1.00 Job7.7715.98
10.Abutment Substructure LHS1.00 Job15.9816-01-202131-01-20211.00 Job1.00 Job7.7715.98
11.Fixing Bearing/Slab Casting1.00 job11.8025-05-202130-06-20211.00 job1.00 job5.7411.80
12.Wearing Coat12.31 Cum1.5215-06-202105-07-202112.31 Cum12.31 Cum0.741.52
Total Amount: 205.72 100   205.72
Remarks: No Remarks       Work Program Made On: 19-02-2021        Updation of work program on: 21-09-2021       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.26-March-202199.77  lakh
2.28-June-202136.44  lakh
3.21-September-202115.77  lakh
4.21-March-202229.79  lakh
Total 181.77  lakh
% Payment 100.01 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 219   No. of Test Done : 219    No. of Test Passed : 219   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 90.10
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 75
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.06-04-2022Agrakhal Kushrela km 7Bridge work CompletedSudhir Kumar ` ` See Pic
2.21-03-2022Agrakhal-Kusraila KM-07Approach road LHS to RHSSuresh Prasad ` ` See Pic
3.21-03-2022Agrakhal-Kusraila KM-07Agrakhal-Kusraila KM-07 bridge LHS SIDESuresh Prasad ` ` See Pic
4.21-03-2022Agrakhal-Kusraila KM-07Up stream side of bridgeSuresh Prasad ` ` See Pic
5.21-03-2022Agrakhal-Kusraila KM-07Down stream side of bridgeSuresh Prasad ` ` See Pic
6.21-03-2022Agrakhal-Kusraila KM-07Agrakhal-Kusraila KM-07 RHS SIDESuresh Prasad ` ` See Pic
7.24-07-2021Agrakhal kusherela km 7Crush Barrier M -40 Casting work on progressVikash Baboounknownunknown See Pic
8.10-07-2021Agrakhal Kushrela km 7Slab CastingSudhir Kumar ` ` See Pic
9.07-07-2021Agrakhal Km-07Deck Slab castingVikas Vermaunknownunknown See Pic
10.06-07-2021Agrakhal-Kusraila KM-07Agrakhal-Kusraila KM-07 Deck Slab RCC M-35 Casting DoneSuresh Prasad ` ` See Pic
11.06-07-2021Agrakhal kusherela km 7Agrakhal kusherela km 7 Deck Slab Casting completed M-35Vikash Baboounknownunknown See Pic
12.03-07-2021Agrakhal kusrila Km-7Deck Slab steel bar binding workVikas Vermaunknownunknown See Pic
13.17-06-2021Agrakhal kusherela km 7AB1 Side Shaft & Retaining wall1st Lift CastingVikash Baboounknownunknown See Pic
14.16-06-2021KM-7 Agrakhal KushrailaBar Binding work in progress Deck SlabVikas Vermaunknownunknown See Pic
15.12-06-2021Agrakhal Kushrela km 7Bearing TestingSudhir Kumar ` ` See Pic
16.25-05-2021Chamasari Majhada km 2Concrete work in progress Return WallSudhir Kumar ` ` See Pic
17.25-05-2021Agrakhal Kushrela km 7Errection work in progressSudhir Kumar ` ` See Pic
18.15-05-2021Agrakhal Kushrela km 7Errection work in progressSudhir Kumar ` ` See Pic
19.06-05-2021Agrakhal Kushrela km 7Errection work in progressSudhir Kumar ` ` See Pic
20.06-05-2021Agrakhal Kushrela km 7Errection work in progressSudhir Kumar ` ` See Pic