Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Ghughutiyadhar Betalghat Khairna Suyalwadi Odakhan Pasiyapani Bhateliya Mukteshwar MR Km 35 Agreement signed
Project: UDRP-AF(Bridge/Slope) UID: 4058 Sanction Cost: 549.91  lakh Span: 60.000 M
District: Nainital Block: Betalghat Constituency: Nainital Circle:
DEA: DEA Nanital DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision Type: Bridge
Procurement:
Package No.: 643        Package Name:  UDRP/AF/BR/75        Tender Date: 11-11-2019        Current Status: Agreement signed        Achieved on Date: 15-09-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/75      Contractor Name: M/S.KGL Infrastructure
Start Date:  29-10-2020      Intended Completion Date:  28-06-2022      Original End Date:  29-01-2022
Total Bond Cost: 57926186 (579.26 lakh)        Variation Cost: 7678183.98 (76.78 lakh)    Hence Total Bond Cost is   65604369.98 (656.04 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 11411422 for 394 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.R/Wall, B/ Wall Type Protection works140.00 m20.5715-07-202111-11-2021140.00 m140.00 m4.420.57
2.Env. Man & Moni Plan28.00 Job2.8615-11-202026-06-202228.00 Job28.00 Job0.612.86
3.Other Allied Works & Finishing Work 1.00 Job3.9815-11-202028-06-20221.00 Job1.00 Job0.853.98
4.Foundation RHS1.00 Job13.9326-01-202116-02-20211.00 Job1.00 Job2.9813.93
5.Foundation LHS1.00 Job13.9317-02-202115-04-20211.00 Job1.00 Job2.9813.93
6.Deck Cable laying, stretching and Fixing Transoms/Deck Slab 1.00 no28.1701-12-202108-01-20221.00 no1.00 no6.0328.17
7.Steel Railing/crush barrier120.00 m8.0409-01-202220-01-2022120.00 m120.00 m1.728.04
8.Approach Ramp /path 100.00 m22.0015-07-202124-06-2022100.00 m100.00 m4.7122.00
9.Errection Work190.86 Job113.8901-09-202120-03-2022190.86 Job190.86 Job24.38113.89
10.Gabion work186.00 m14.4201-03-202127-06-2022186.00 m186.00 m3.0914.42
11.PCC in Foundation29.90 cum2.3601-01-202120-06-202229.90 cum29.90 cum0.512.36
12.Excavation in soil6688.32 cum5.2216-12-202031-12-20206688.32 cum6688.32 cum1.125.22
13.Fabrication Work184.80 job177.8201-02-202115-08-2021184.80 job184.80 job38.07177.82
14.Abutment Substructure RHS1.00 Job16.3217-02-202115-05-20211.00 Job1.00 Job3.4916.32
15.Abutment Substructure LHS1.00 Job16.3216-04-202111-07-20211.00 Job1.00 Job3.4916.32
16.Fixing Bearing/Slab Casting6.00 job2.9201-08-202131-05-20226.00 job6.00 job0.632.92
17.Back Wall/ Approach slab2.00 job1.3310-01-202221-06-20222.00 job2.00 job0.281.33
18.Wearing Coat23.40 Cum3.0420-01-202211-06-202223.40 Cum23.40 Cum0.653.04
Total Amount: 467.12 100   467.12
Remarks: No Remarks       Work Program Made On: 26-01-2021        Updation of work program on: 20-12-2022       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.16-March-202168.26  lakh
2.09-April-202127.59  lakh
3.22-July-202160.40  lakh
4.24-September-202153.04  lakh
5.02-November-2021156.78  lakh
6.30-December-202147.10  lakh
7.10-March-202258.56  lakh
8.31-March-202295.11  lakh
9.31-May-202230.80  lakh
10.31-August-202234.74  lakh
11.25-November-202223.64  lakh
Total 656.02  lakh
% Payment 99.92 %
Advance Amount:  57.73  lakh        Recovered Amount:  57.73  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level): No Pending Issue
Environment & Social Compliances(Sub Project level): Land Owner Consent
Detailed report of this subproject
Quality
No. of Test Required : 474   No. of Test Done : 519    No. of Test Passed : 485   No. of Test Failed : 34   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 94.23
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 301
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.23-06-2022Ghiroli Betalghat NainitalDirt wall Reinforcement fixing work is in progress at BR-75Surendra Singh ` ` See Pic
2.23-06-2022Ghiroli Betalghat NainitalLatest photos at siteSurendra Singh ` ` See Pic
3.23-06-2022Ghiroli Betalghat NainitalLatest photos at siteSurendra Singh ` ` See Pic
4.22-06-2022Ghiroli betalghatApproach slab pcc laying is in progressShivam ` ` See Pic
5.22-06-2022Ghiroli betalghatPCC laying for approach slab At A-1 sideShivam ` ` See Pic
6.22-06-2022BR 75Crush berrier work in progressSantosh Shukla ` ` See Pic
7.20-06-2022Ghiroli BetalghatWearing coat laying is in progress BR-75Shivam ` ` See Pic
8.13-06-2022Ghiroli BetalghatCrash Barrier Curing work is in progress BR-75Shivam ` ` See Pic
9.13-06-2022Ghiroli BetalghatDirt wall concreting is in progress BR-75 A-1 sideShivam ` ` See Pic
10.09-06-2022Ghiroli Betalghat NainitalCrash Barrier Curing work is in progressSurendra Singh Bisht ` ` See Pic
11.09-06-2022Ghiroli Betalghat NainitalCrash Barrier concreting work is in progressSurendra Singh Bisht ` ` See Pic
12.09-06-2022Ghiroli Betalghat NainitalDeck slab Curing work is in progressSurendra Singh Bisht ` ` See Pic
13.05-06-2022Ghiroli Betalghat NainitalDeck slab Curing work is in progressSurendra Singh Bisht ` ` See Pic
14.04-06-2022Ghiroli Betalghat NainitalDeck slab Curing work is in progressSurendra Singh Bisht ` ` See Pic
15.03-06-2022Ghiroli Betalghat NainitalDeck slab Curing work is in progressSurendra Singh Bisht ` ` See Pic
16.03-06-2022Ghiroli BetalghatDeck slab Curing work is in progressShivam ` ` See Pic
17.01-06-2022BR 75Deck Slab M 35 Concrete workSantosh Shukla ` ` See Pic
18.01-06-2022BR 75Gradation fine. AggregateSantosh Shukla ` ` See Pic
19.01-06-2022BR 75Gradation curse Aggregate 20MMSantosh Shukla ` ` See Pic
20.01-06-2022BR 75Deck Slab Concrete workSantosh Shukla ` ` See Pic