Bridge on Basutiya Dogda Motor Road (Km-1)
Work Completed
|
Project: |
UDRP-AF(Bridge/Slope) |
UID: |
4057 |
Sanction Cost: |
194.62 lakh |
Span:
|
32.000 M |
District: |
Nainital |
Block: |
Bhimtal |
Constituency: |
Kaladhungi |
Circle: |
|
DEA: |
DEA Nanital |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
Type: |
Bridge |
|
Procurement: |
Package No.: 645
Package Name: 
UDRP/AF/BR/65
Tender Date: 22-10-2019
Current Status: Agreement signed
Achieved on Date: 24-06-2020 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/BR/65
Contractor Name: Gaurav Builder
|
Start Date: 10-09-2020
Intended Completion Date: 14-02-2022
Original End Date: 09-09-2021 |
Total Bond Cost: 20663226.08 (206.63 lakh)
Variation Cost: -469579.27 (-4.7 lakh) Hence Total Bond Cost is 20193646.81 (201.94 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 3151260 for 305 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Env. Man & Moni Plan | 25.00 Job | 4.33 | 10-09-2020 | 15-02-2022 | 25.00 Job | 25.00 Job | 2.1 | 4.33 | 2. | Other Allied Works & Finishing Work | 1.00 Job | 5.10 | 01-02-2021 | 15-02-2022 | 1.00 Job | 1.00 Job | 2.47 | 5.10 | 3. | Foundation RHS | 1.00 Job | 9.72 | 10-10-2020 | 05-02-2021 | 1.00 Job | 1.00 Job | 4.7 | 9.72 | 4. | Foundation LHS | 1.00 Job | 13.45 | 09-11-2020 | 28-01-2021 | 1.00 Job | 1.00 Job | 6.51 | 13.45 | 5. | Deck Cable laying, stretching and Fixing Transoms/Deck Slab | 1.00 no | 17.76 | 01-06-2021 | 30-06-2021 | 1.00 no | 1.00 no | 8.59 | 17.76 | 6. | Steel Railing/crush barrier | 78.00 m | 4.89 | 02-06-2021 | 10-06-2021 | 78.00 m | 78.00 m | 2.37 | 4.89 | 7. | Approach Ramp /path | 100.00 m | 37.38 | 30-04-2021 | 12-02-2022 | 120.00 m | 120.00 m | 18.09 | 37.38 | 8. | Protection Work | 1.00 Job | 15.35 | 30-04-2021 | 30-08-2021 | 1.00 Job | 1.00 Job | 7.43 | 15.35 | 9. | Errection Work | 1.00 Job | 31.46 | 16-04-2021 | 31-05-2021 | 1.00 Job | 1.00 Job | 15.22 | 31.46 | 10. | Fabrication Work | 1.00 job | 40.49 | 30-10-2020 | 15-04-2021 | 1.00 job | 1.00 job | 19.6 | 40.49 | 11. | Abutment Substructure RHS | 1.00 Job | 9.06 | 09-11-2020 | 01-03-2021 | 1.00 Job | 1.00 Job | 4.39 | 9.06 | 12. | Abutment Substructure LHS | 1.00 Job | 17.65 | 09-12-2020 | 25-02-2021 | 1.00 Job | 1.00 Job | 8.54 | 17.65 |
Total Amount: |
206.64 |
|
100 |
206.64 |
|
Remarks:
No Remarks
Work Program Made On:
28-01-2021 } ?>
Updation of work program on:
29-01-2022
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 14-January-2021 | 28.83 lakh | 2. | 30-March-2021 | 59.23 lakh | 3. | 31-May-2021 | 36.90 lakh | 4. | 19-August-2021 | 19.46 lakh | 5. | 06-November-2021 | 14.03 lakh | 6. | 19-February-2022 | 15.02 lakh | 7. | 05-May-2022 | 28.42 lakh |
Total |
201.89 lakh |
% Payment |
99.98 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 410 No. of Test Done : 435 No. of Test Passed : 415 No. of Test Failed : 20 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 91.71 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 118 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 10-06-2022 | BR 65 | 32 Metter Span Steel bridge Completed | Santosh Shukla | ` | ` | See Pic |
2. | 22-02-2022 | 00 + 160 | OGPC And seal coat | Santosh Shukla | ` | ` | See Pic |
3. | 22-02-2022 | 00TO 160 | OGPC And Seal coat in progress | Santosh Shukla | ` | ` | See Pic |
4. | 20-02-2022 | 130 TO 160 | OGPC ONE Site Completed | Santosh Shukla | ` | ` | See Pic |
5. | 20-02-2022 | 130 +160 A2 Site | OrOpen graded PC Work | Santosh Shukla | ` | ` | See Pic |
6. | 20-02-2022 | Ch 130 to 160 | Open Grade Premix Carpet Laying 20 mm thick (A2 Side) | Chhatrapati Pant | ` | ` | See Pic |
7. | 20-02-2022 | Ch 130 to Ch 160 | Preparation for Laying Open Grade BC (A2 Side) | Chhatrapati Pant | ` | ` | See Pic |
8. | 30-01-2022 | A1 | Concrete work | Rajesh Bhatt | ` | ` | See Pic |
9. | 29-01-2022 | 32 m span Steel truss Bridge | Painting work in progress | Chhatrapati Pant | ` | ` | See Pic |
10. | 27-01-2022 | BR 65 | Crash Barrier penting work | Santosh Shukla | ` | ` | See Pic |
11. | 29-12-2021 | 126.5 To 155 5 | Compection WBM | Santosh shukla | ` | ` | See Pic |
12. | 25-12-2021 | Ch 0 to 87.5 | Backfilling Work @A1 side | Chhatrapati Pant | ` | ` | See Pic |
13. | 14-12-2021 | B R 65 | R R masonry work | Santosh shukla | ` | ` | See Pic |
14. | 11-12-2021 | A1 Site | RR masonry work in Progress | Santosh shukla | ` | ` | See Pic |
15. | 10-12-2021 | A1 Side approach RR Masonary work & Backfilling | Backfilling & R R Masonary work | Chhatrapati Pant | ` | ` | See Pic |
16. | 09-12-2021 | Abutment A1 | Earth Work in Progress | Santosh shukla | ` | ` | See Pic |
17. | 09-12-2021 | A2 site | Earth work compection | Santosh shukla | ` | ` | See Pic |
18. | 09-12-2021 | A1 Abutment | Earth work at site | Santosh shukla | ` | ` | See Pic |
19. | 01-12-2021 | 00+ 100 chainage | Earth work filling at sait work is Progress | Santosh shukla | ` | ` | See Pic |
20. | 30-11-2021 | 00+150M | Earth work at site | Santosh shukla | ` | ` | See Pic |
|
|