Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Tachla Naur Slope Motor Road KM-1 Work Completed
Project: UDRP-AF(Bridge/Slope) UID: 4051 Sanction Cost: 612.54  lakh Length: 150.000 KM.
District: Tehri Block: Narendra Nagar Constituency: Narendra Nagar Circle:
DEA: DEA Tehri DSC: CCEE Group India Pvt. Ltd in Association with JSV DSC Scope: Design and Supervision Type: Slope Protection Work
Procurement:
Package No.: 709        Package Name:  UDRP/AF/SL/12        Tender Date: 11-11-2019        Current Status: Agreement signed        Achieved on Date: 02-06-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/SL/12      Contractor Name: Global Construction
Start Date:  09-07-2020      Intended Completion Date:  06-09-2021      Original End Date:  08-07-2021
Total Bond Cost: 54390157.29 (543.9 lakh)        Variation Cost: 181827.89 (1.82 lakh)    Hence Total Bond Cost is   54571985.18 (545.72 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 7152285 for 263 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.R/Wall, B/ Wall Type Protection works221.00 m38.2028-09-202020-08-2021221.00 m221.00 m7.9538.20
2.Stressing & Grouting1.00 Job226.8728-09-202030-06-20211.00 Job1.00 Job47.19226.87
3.Env. Man & Moni Plan1.00 Job4.7324-09-202003-09-20211.00 Job1.00 Job0.984.73
4.Other Allied Works & Finishing Work 1.00 Job18.0913-09-202028-06-20211.00 Job1.00 Job3.7618.09
5.Approach Ramp /path 150.00 m22.4129-01-202105-09-2021150.00 m150.00 m4.6622.41
6.Anchors8739.00 m36.6728-09-202011-06-20218739.00 m8739.00 m7.6336.67
7.Hydroseeding,3-D Net, High tensile Rolled Cable Net8250.00 sqm122.4312-11-202015-08-20218250.00 sqm8250.00 sqm25.47122.43
8.Gabion work150.00 m11.3628-09-202029-08-2021150.00 m150.00 m2.3611.36
Total Amount: 480.76 100   480.76
Remarks: No Remarks       Work Program Made On: 21-10-2020        Updation of work program on: 21-09-2021       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.11-November-202071.52  lakh
2.18-December-2020137.01  lakh
3.04-February-202136.12  lakh
4.27-February-202139.14  lakh
5.31-May-202133.93  lakh
6.06-July-202164.23  lakh
7.31-August-202168.64  lakh
8.30-September-202146.85  lakh
9.22-February-202248.08  lakh
Total 545.52  lakh
% Payment 99.97 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 347   No. of Test Done : 347    No. of Test Passed : 347   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 92.32
Number of Notice(s) issued: 5

Mobile Pic Upload

Number of Pics Available on Web Repository: 348
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.06-04-2022Tachhla Naur km 1World Bank Team visitSudhir Kumar ` ` See Pic
2.06-04-2022Tachhla Naur km 1World Bank Team visitSudhir Kumar ` ` See Pic
3.06-04-2022Tachhla Naur km 1World Bank Team visitSudhir Kumar ` ` See Pic
4.28-01-20220+85R/wall at sub project.Sohan Negi ` ` See Pic
5.27-01-20220+095 to 0+130White washing for parapet & B/wallSohan negi ` ` See Pic
6.27-01-20220+070Soil Erosion control Coir mat.Sohan Negi ` ` See Pic
7.27-01-20220+025Installation of PVC pipe for drainage out of seepage area water.Sohan Negi ` ` See Pic
8.27-01-20220+110Breast wall protection at sub projectSohan Negi ` ` See Pic
9.27-01-20220+055Breast wall protection at sub projectSohan Negi ` ` See Pic
10.27-01-20220+000Rigid pavement CC roadSohan Negi ` ` See Pic
11.27-01-20220+040Parapet protectionSohan Negi ` ` See Pic
12.27-01-20220+00Road and wire mesh protectionRajveer Tomar ` ` See Pic
13.27-01-202200+00Wire mesh protectionRajveer Tomar ` ` See Pic
14.27-01-202200+00Wire mesh protectionRajveer Tomar ` ` See Pic
15.27-01-20220+085to0+110Retaining wall in progressRajveer Tomar ` ` See Pic
16.27-01-20220+000Slope protection work with high tensile wire mesh, Anchoring and anchor platesSohan Negi ` ` See Pic
17.27-01-20220+00 to 0+80High tensile wire mesh work in progressRajveer Tomar ` ` See Pic
18.27-01-20220+080To0+110Retaining wall in progressRajveer Tomar ` ` See Pic
19.27-01-20220+090to0+110Retaining wall in progressRajveer Tomar ` ` See Pic
20.12-11-2021Tachhla Naur km 1 TehriJoint inspection with AE PWD Narendra NagarSudhir Kumar ` ` See Pic