Badethi Banchora Badrigad Slope Motor Road KM-79
Work Completed
|
Project: |
UDRP-AF(Bridge/Slope) |
UID: |
4048 |
Sanction Cost: |
548.42 lakh |
Length:
|
108.000 KM. |
District: |
Tehri |
Block: |
Narain Bagar |
Constituency: |
Narendra Nagar |
Circle: |
|
DEA: |
DEA Tehri |
DSC: |
CCEE Group India Pvt. Ltd in Association with JSV |
DSC Scope: |
Design and Supervision |
Type: |
Slope Protection Work |
|
Procurement: |
Package No.: 634
Package Name: 
UDRP/AF/SL/11
Tender Date: 11-11-2019
Current Status: Agreement signed
Achieved on Date: 29-06-2020 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/SL/11
Contractor Name: M/S Garware Technical fibers Ltd.
|
Start Date: 21-08-2020
Intended Completion Date: 16-11-2021
Original End Date: 20-08-2021 |
Total Bond Cost: 48969123.03 (489.69 lakh)
Variation Cost: -22646955.91 (-226.47 lakh) Hence Total Bond Cost is 26322167.12 (263.22 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 13123960 for 536 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | R/Wall, B/ Wall Type Protection works | 110.00 m | 27.07 | 21-11-2020 | 15-01-2021 | 110.00 m | 110.00 m | 6.19 | 27.07 | 2. | Stressing & Grouting | 1.00 Job | 91.30 | 01-01-2021 | 31-07-2021 | 1.00 Job | 1.00 Job | 20.88 | 91.30 | 3. | Env. Man & Moni Plan | 1.00 Job | 4.17 | 20-09-2020 | 10-10-2021 | 1.00 Job | 1.00 Job | 0.95 | 4.17 | 4. | Other Allied Works & Finishing Work | 1.00 Job | 20.98 | 12-01-2021 | 14-10-2021 | 1.00 Job | 1.00 Job | 4.8 | 20.98 | 5. | Approach Ramp /path | 110.00 m | 36.77 | 01-03-2021 | 15-10-2021 | 110.00 m | 110.00 m | 8.41 | 36.77 | 6. | Anchors | 4113.00 m | 172.09 | 01-01-2021 | 31-07-2021 | 4113.00 m | 4113.00 m | 39.36 | 172.09 | 7. | Hydroseeding,3-D Net, High tensile Rolled Cable Net | 2700.00 sqm | 65.62 | 15-03-2021 | 31-07-2021 | 2700.00 sqm | 2700.00 sqm | 15.01 | 65.62 | 8. | Gabion work | 240.00 m | 13.95 | 15-10-2020 | 15-08-2021 | 240.00 m | 240.00 m | 3.19 | 13.95 | 9. | Excavation in soil | 1386.56 cum | 5.28 | 20-09-2020 | 20-06-2021 | 1386.56 cum | 1386.56 cum | 1.21 | 5.28 |
Total Amount: |
437.23 |
|
100 |
437.23 |
|
Remarks:
No Remarks
Work Program Made On:
12-01-2021 } ?>
Updation of work program on:
21-09-2021
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 04-January-2021 | 12.39 lakh | 2. | 27-February-2021 | 134.07 lakh | 3. | 31-March-2021 | 31.06 lakh | 4. | 31-May-2021 | 41.23 lakh | 5. | 06-May-2022 | 44.47 lakh |
Total |
263.22 lakh |
% Payment |
99.99 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 120 No. of Test Done : 120 No. of Test Passed : 120 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 93.94 |
Number of Notice(s) issued: 8 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 258 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 12-04-2022 | Badethi Banchora Road protection work Tehri | Site inspection by World Bank Team | Sudhir Kumar | ` | ` | See Pic |
2. | 12-04-2022 | Badethi Banchora Road protection work Tehri | Site inspection by World Bank Team | Sudhir Kumar | ` | ` | See Pic |
3. | 06-04-2022 | Badethi Banchora Road protection work | Joint inspection with AE PWD Thatyur | Sudhir Kumar | ` | ` | See Pic |
4. | 30-01-2022 | 78+480 | Project Board | MalyajDixit | ` | ` | See Pic |
5. | 30-01-2022 | 78+370 | Project Board | MalyajDixit | ` | ` | See Pic |
6. | 30-01-2022 | 78+360 | Catchpit wall | MalyajDixit | ` | ` | See Pic |
7. | 30-01-2022 | 78+380 | Parapet | MalyajDixit | ` | ` | See Pic |
8. | 30-01-2022 | 78+360 | Slab culvert | MalyajDixit | ` | ` | See Pic |
9. | 30-01-2022 | 78+410 | Drain | MalyajDixit | ` | ` | See Pic |
10. | 30-01-2022 | 78+430 | Cement concrete road | MalyajDixit | ` | ` | See Pic |
11. | 30-01-2022 | 78+450 | HSBN MAT | MalyajDixit | ` | ` | See Pic |
12. | 30-01-2022 | 78+470 | Parapet | MalyajDixit | ` | ` | See Pic |
13. | 30-01-2022 | 78+470 | Breast wall | MalyajDixit | ` | ` | See Pic |
14. | 30-01-2022 | 78+480 | Breast wall | MalyajDixit | ` | ` | See Pic |
15. | 30-01-2022 | 78+490 | Slab culvert | MalyajDixit | ` | ` | See Pic |
16. | 26-10-2021 | Km 79 | Slb culvert | Ganesh kumar | ` | ` | See Pic |
17. | 26-10-2021 | Km 79 | Road m 30 | Ganesh Kumar | ` | ` | See Pic |
18. | 26-10-2021 | Km 79 | Slab Culvert | Ganesh Kumar | ` | ` | See Pic |
19. | 26-10-2021 | Km 79 | Culvert | Ganesh Kumar | ` | ` | See Pic |
20. | 23-10-2021 | 78+465 | M-30 work is progress at badeti banchora km-78 | Deepak Shukla | ` | ` | See Pic |
|
|