Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Badethi Banchora Badrigad Slope Motor Road KM-79 Work Completed
Project: UDRP-AF(Bridge/Slope) UID: 4048 Sanction Cost: 548.42  lakh Length: 108.000 KM.
District: Tehri Block: Narain Bagar Constituency: Narendra Nagar Circle:
DEA: DEA Tehri DSC: CCEE Group India Pvt. Ltd in Association with JSV DSC Scope: Design and Supervision Type: Slope Protection Work
Procurement:
Package No.: 634        Package Name:  UDRP/AF/SL/11        Tender Date: 11-11-2019        Current Status: Agreement signed        Achieved on Date: 29-06-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/SL/11      Contractor Name: M/S Garware Technical fibers Ltd.
Start Date:  21-08-2020      Intended Completion Date:  26-10-2021      Original End Date:  20-08-2021
Total Bond Cost: 48969123.03 (489.69 lakh)        Variation Cost: -14440280.73 (-144.4 lakh)    Hence Total Bond Cost is   34528842.3 (345.29 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 11850740 for 484 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.R/Wall, B/ Wall Type Protection works110.00 m27.0721-11-202015-01-2021110.00 m110.00 m6.1927.07
2.Stressing & Grouting1.00 Job91.3001-01-202131-07-20211.00 Job1.00 Job20.8891.30
3.Env. Man & Moni Plan1.00 Job4.1720-09-202010-10-20211.00 Job1.00 Job0.954.17
4.Other Allied Works & Finishing Work 1.00 Job20.9812-01-202114-10-20211.00 Job1.00 Job4.820.98
5.Approach Ramp /path 110.00 m36.7701-03-202115-10-2021110.00 m110.00 m8.4136.77
6.Anchors4113.00 m172.0901-01-202131-07-20214113.00 m4113.00 m39.36172.09
7.Hydroseeding,3-D Net, High tensile Rolled Cable Net2700.00 sqm65.6215-03-202131-07-20212700.00 sqm2700.00 sqm15.0165.62
8.Gabion work240.00 m13.9515-10-202015-08-2021240.00 m240.00 m3.1913.95
9.Excavation in soil1386.56 cum5.2820-09-202020-06-20211386.56 cum1386.56 cum1.215.28
Total Amount: 437.23 100   437.23
Remarks: No Remarks       Work Program Made On: 12-01-2021        Updation of work program on: 21-09-2021       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.04-January-202112.39  lakh
2.27-February-2021134.07  lakh
3.31-March-202131.06  lakh
4.31-May-202141.23  lakh
Total 218.75  lakh
% Payment 63.36 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 120   No. of Test Done : 120    No. of Test Passed : 120   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 93.94
Number of Notice(s) issued: 8

Mobile Pic Upload

Number of Pics Available on Web Repository: 243
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.26-10-2021Km 79Slb culvertGanesh kumar ` ` See Pic
2.26-10-2021Km 79Road m 30Ganesh Kumar ` ` See Pic
3.26-10-2021Km 79Slab CulvertGanesh Kumar ` ` See Pic
4.26-10-2021Km 79CulvertGanesh Kumar ` ` See Pic
5.23-10-202178+465M-30 work is progress at badeti banchora km-78Deepak Shukla ` ` See Pic
6.23-10-2021Chainge 78+460M-30 work is progress at badeti banchora km-78Deepak Shukla ` ` See Pic
7.21-10-2021Badethi Banchora km 79 Road protection work TehriPQC M30 work in progressSudhir Kumar ` ` See Pic
8.27-09-202178+490Bed block work is progress for scupper at badeti banchora km-78Deepak Shukla ` ` See Pic
9.21-09-202178+490Scupper wall is progress at badeti banchora km-78Deepak Shukla ` ` See Pic
10.07-09-202178+420Curing work is progress for breast wall at badeti banchora km-78 upper sideDeepak Shukla ` ` See Pic
11.07-09-202178+425Breast wall work is progress at badeti banchora km-78 upper sideDeepak Shukla ` ` See Pic
12.07-09-202178+430Breast wall work is progress at badeti banchora km-78 upper sideDeepak Shukla ` ` See Pic
13.04-09-202178+408M-30 work is progress for road at badeti banchora km-78Deepak Shukla ` ` See Pic
14.04-09-202179+407M-30 work is progress for road at badeti banchora km-78Deepak Shukla ` ` See Pic
15.03-09-202178+403M-30 work is progress for road at badeti banchora km-78Deepak Shukla ` ` See Pic
16.03-09-202178+435Breast wall work is progress at badeti banchora km-78 upper sideDeepak Shukla ` ` See Pic
17.03-09-202178+435Breast wall work is progress at badeti banchora km-78 upper sideDeepak Shukla ` ` See Pic
18.03-09-202178+400M-30 work is progress for road at badeti banchora km-78Deepak Shukla ` ` See Pic
19.03-09-202178+400M-30 work is progress for road at badeti banchora km-78Deepak Shukla ` ` See Pic
20.02-09-202178+400M-30 work is progress for road at badeti banchora km-78Deepak Shukla ` ` See Pic