Dobra Bhliyana Slope Motor Road KM-10
Work Completed
|
Project: |
UDRP-AF(Bridge/Slope) |
UID: |
4047 |
Sanction Cost: |
420.06 lakh |
Length:
|
90.000 KM. |
District: |
Tehri |
Block: |
Kouldhar |
Constituency: |
Pratapnagar |
Circle: |
|
DEA: |
DEA Tehri |
DSC: |
CCEE Group India Pvt. Ltd in Association with JSV |
DSC Scope: |
Design and Supervision |
Type: |
Slope Protection Work |
|
Procurement: |
Package No.: 706
Package Name: 
UDRP/AF/SL/09
Tender Date: 21-12-2019
Current Status: Agreement signed
Achieved on Date: 19-06-2020 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/SL/09
Contractor Name: Global Construction
|
Start Date: 13-07-2020
Intended Completion Date: 12-07-2021
|
Total Bond Cost: 37759210.37 (377.59 lakh)
Variation Cost: -2146380.88 (-21.46 lakh) Hence Total Bond Cost is 35612829.49 (356.13 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 4342400 for 230 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | R/Wall, B/ Wall Type Protection works | 120.00 m | 26.14 | 27-08-2020 | 15-06-2021 | 120.00 m | 120.00 m | 7.73 | 26.14 | 2. | Stressing & Grouting | 1.00 Job | 109.95 | 27-09-2020 | 25-03-2021 | 1.00 Job | 1.00 Job | 32.52 | 109.95 | 3. | Env. Man & Moni Plan | 1.00 Job | 5.38 | 15-07-2020 | 18-06-2021 | 1.00 Job | 1.00 Job | 1.59 | 5.38 | 4. | Other Allied Works & Finishing Work | 1.00 Job | 15.84 | 20-08-2020 | 30-06-2021 | 1.00 Job | 1.00 Job | 4.69 | 15.84 | 5. | Approach Ramp /path | 120.00 m | 24.73 | 25-11-2020 | 25-03-2021 | 120.00 m | 120.00 m | 7.32 | 24.73 | 6. | Anchors | 3665.00 m | 18.18 | 27-09-2020 | 25-03-2021 | 3665.00 m | 3665.00 m | 5.38 | 18.18 | 7. | Hydroseeding,3-D Net, High tensile Rolled Cable Net | 12420.00 sqm | 102.96 | 05-11-2020 | 15-03-2021 | 12420.00 sqm | 12420.00 sqm | 30.46 | 102.96 | 8. | Gabion work | 489.00 m | 34.88 | 29-08-2020 | 20-03-2021 | 489.00 m | 489.00 m | 10.32 | 34.88 |
Total Amount: |
338.06 |
|
100 |
338.06 |
|
Remarks:
No Remarks
Work Program Made On:
21-10-2020 } ?>
Updation of work program on:
24-06-2021
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 29-October-2020 | 19.60 lakh | 2. | 11-November-2020 | 42.24 lakh | 3. | 18-December-2020 | 73.74 lakh | 4. | 04-February-2021 | 52.76 lakh | 5. | 27-February-2021 | 48.83 lakh | 6. | 31-May-2021 | 78.94 lakh | 7. | 30-September-2021 | 40.03 lakh |
Total |
356.14 lakh |
% Payment |
100 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 229 No. of Test Done : 230 No. of Test Passed : 229 No. of Test Failed : 1 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 91.43 |
Number of Notice(s) issued: 14 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 253 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 28-01-2022 | Dobra km 10 | Protection work by high tensile wire mesh, B/wall,R/wall, parapet. | Sohan Negi | ` | ` | See Pic |
2. | 28-01-2022 | 0+000 to 0+090 | Slope protection work at sub project | Sohan Negi | ` | ` | See Pic |
3. | 28-01-2022 | 0+30 | R/wall protection at sub project. | Sohan Negi | ` | ` | See Pic |
4. | 28-01-2022 | 0+60 | Parapet Protection with White washing | Sohan Negi | ` | ` | See Pic |
5. | 28-01-2022 | 0+110 | Wire mesh protection work with Anchor and plates. | Sohan Negi | ` | ` | See Pic |
6. | 28-01-2022 | 0+080 | B/wall protection work | Sohan Negi | ` | ` | See Pic |
7. | 28-01-2022 | 0+000 to 0+110 | High tensile wire mesh protection work at sub project | Sohan Negi | ` | ` | See Pic |
8. | 28-01-2022 | 0+070 | Parapet protection work at sub project | Sohan Negi | ` | ` | See Pic |
9. | 28-01-2022 | 0+000 to 0+ 110 | Rigid pavement CC work at sub project | Sohan Negi | ` | ` | See Pic |
10. | 28-01-2022 | 0+30 | B/wall work at sub project | Sohan Negi | ` | ` | See Pic |
11. | 28-01-2022 | 0+000 | Slope protection work at sub project | Sohan Negi | ` | ` | See Pic |
12. | 06-09-2021 | 6+500 | Dumping zone | Kishan Singh Rawat | ` | ` | See Pic |
13. | 06-09-2021 | 6+500 | Dumping zone | Kishan Singh Rawat | ` | ` | See Pic |
14. | 06-09-2021 | 0+060 | CC road | Kishan Singh Rawat | ` | ` | See Pic |
15. | 07-07-2021 | At site | Laboratory | Kishan Singh Rawat | ` | ` | See Pic |
16. | 07-07-2021 | At site | Washroom | Kishan Singh Rawat | ` | ` | See Pic |
17. | 07-07-2021 | 0+00 | PPE kit | Kishan Singh Rawat | ` | ` | See Pic |
18. | 07-07-2021 | 0+00 | Dustbin | Kishan Singh Rawat | ` | ` | See Pic |
19. | 07-07-2021 | 0+000 | Fire extinguisher | Kishan Singh Rawat | ` | ` | See Pic |
20. | 07-07-2021 | 6+500 | Dumping zone dobra km10 | Kishan Singh Rawat | ` | ` | See Pic |
|
|