Guptkashi Kalimath Slope Motor Road at KM-2 & KM-3
Work Completed
|
Project: |
UDRP-AF(Bridge/Slope) |
UID: |
4041 |
Sanction Cost: |
1526.43 lakh |
Length:
|
0.812 KM. |
District: |
Rudraprayag |
Block: |
Ukhimath |
Constituency: |
Kedarnath |
Circle: |
|
DEA: |
DEA Guptkashi |
DSC: |
CCEE Group India Pvt. Ltd in Association with JSV |
DSC Scope: |
Design and Supervision |
Type: |
Slope Protection Work |
|
Procurement: |
Package No.: 702
Package Name: 
UDRP/AF/SL/06
Tender Date: 24-01-2018
Current Status: Agreement signed
Achieved on Date: 23-07-2018 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/SL/06
Contractor Name: Bharat Construction
|
Start Date: 03-08-2018
Intended Completion Date: 02-02-2020
|
Total Bond Cost: 138496385.36 (1384.96 lakh)
Variation Cost: 22846749.05 (228.47 lakh) Hence Total Bond Cost is 161343134.41 (1613.43 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 19804928 for 286 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | GSB/RBI/G-1 | 0.75 KM | 9.24 | 15-09-2019 | 15-12-2019 | 0.75 KM | 0.75 KM | 0.65 | 9.24 | 2. | PC/CC i/c Prime Coat, Tack Coat | 0.75 KM | 102.52 | 15-10-2019 | 01-01-2020 | 0.75 KM | 0.75 KM | 7.17 | 102.52 | 3. | Env. Man & Moni Plan | 1.00 Job | 3.09 | 10-10-2018 | 01-01-2020 | 1.00 Job | 1.00 Job | 0.22 | 3.09 | 4. | Other Allied Works & Finishing Work | 1.00 Job | 44.37 | 01-11-2018 | 01-01-2020 | 1.00 Job | 1.00 Job | 3.11 | 44.37 | 5. | Steel Railing/crush barrier | 0.20 m | 5.99 | 01-11-2019 | 01-01-2020 | 0.20 m | 0.20 m | 0.42 | 5.99 | 6. | Gravity Bench Wall | 364.00 m | 42.56 | 02-11-2018 | 01-01-2020 | 364.00 m | 364.00 m | 2.98 | 42.56 | 7. | Anchors | 4963.33 m | 411.13 | 05-11-2018 | 25-09-2019 | 4963.33 m | 4963.33 m | 28.77 | 411.13 | 8. | Gabion work | 7151.50 m | 244.29 | 15-11-2018 | 05-02-2019 | 7151.50 m | 7151.50 m | 17.1 | 244.29 | 9. | PCC in Foundation | 6611.13 cum | 509.62 | 10-11-2018 | 11-09-2019 | 6611.13 cum | 6611.13 cum | 35.66 | 509.62 | 10. | Excavation in soil | 9229.89 cum | 56.23 | 05-11-2018 | 10-09-2019 | 9229.89 cum | 9229.89 cum | 3.94 | 56.23 |
Total Amount: |
1429.04 |
|
100 |
1429.04 |
|
Remarks:
No Remarks
Work Program Made On:
02-11-2018 } ?>
Updation of work program on:
03-04-2021
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 08-January-2019 | 125.63 lakh | 2. | 28-February-2019 | 175.95 lakh | 3. | 08-March-2019 | 183.99 lakh | 4. | 30-March-2019 | 112.14 lakh | 5. | 21-May-2019 | 135.96 lakh | 6. | 20-June-2019 | 37.07 lakh | 7. | 30-June-2019 | 315.17 lakh | 8. | 28-August-2019 | 33.50 lakh | 9. | 23-October-2019 | 64.05 lakh | 10. | 31-December-2019 | 43.21 lakh | 11. | 17-February-2020 | 13.46 lakh | 12. | 19-May-2020 | 210.59 lakh |
Total |
1450.72 lakh |
% Payment |
89.92 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Bill sh
ould be issued | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 494 No. of Test Done : 495 No. of Test Passed : 494 No. of Test Failed : 1 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 82.84 |
Number of Notice(s) issued: 35 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 150 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 27-11-2021 | A1 Abutment | Excavation in foundation of LHS Abutment | Prem Prakash AE | ` | ` | See Pic |
2. | 27-11-2020 | 086 | Hffth | Deepak Pant | Site supervisior | UDRP AF Irrigation birahi | See Pic |
3. | 04-02-2020 | 1+060 | Interlocking Paving Tile | Manoj Bhatt | RE | DSC WB SPW Rudraprayag | See Pic |
4. | 04-02-2020 | 0+430 | MBCB Fixing in Progress | Manoj Bhatt | RE | DSC WB SPW Rudraprayag | See Pic |
5. | 04-01-2020 | Chainage 1+150 | Cleaning of Gabion nala .... | Shivam Tiwari | QC | DSC WB SPW TEHRI | See Pic |
6. | 27-12-2019 | 0+400 to 0+450 | Interlocking paving tiles work in progress. | Sohan Singh Negi | Site Supervisor | DSC WB SPW Rudraprayag | See Pic |
7. | 20-12-2019 | 0+395 | Site visit by DSC Project Manager. | Sohan Singh Negi | Site Supervisor | DSC WB SPW Rudraprayag | See Pic |
8. | 16-12-2019 | Chainage 1+080 | Gabion wall work on progress at valley side | Shivam Tiwari | Quality Control | DSC WB SPW Rudraprayag | See Pic |
9. | 02-12-2019 | 1+090 | Paving concrete interlocking tile work in progress | Manoj Bhatt | RE | DSC WB SPW Rudraprayag | See Pic |
10. | 02-12-2019 | 0+410 | Gabion Wall edging in Progress | Manoj Bhatt | RE | DSC WB SPW Rudraprayag | See Pic |
11. | 20-11-2019 | Chainage 1+040 | Gabion wall work in progress | Shivam Tiwari | Quality Control | DSC WB SPW Rudraprayag | See Pic |
12. | 15-11-2019 | Chainage 0+020 | Interlocking tiles work on progress .... | Shivam Tiwari | Quality Control | DSC WB SPW Rudraprayag | See Pic |
13. | 12-11-2019 | 0+100 | Site sample collection for Thickness and Gradation of WBM. | Manoj Bhatt | RE | DSC WB SPW Rudraprayag | See Pic |
14. | 12-11-2019 | Chainage 0+60 | Social expert visit | Shivam Tiwari | Quality Control | DSC WB SPW Rudraprayag | See Pic |
15. | 12-11-2019 | 0+100 | Site inspected by Social Expert of PIU | Manoj Bhatt | RE | DSC WB SPW Rudraprayag | See Pic |
16. | 12-11-2019 | 0+100 | Site Visit of Social Expert from PIU | Manoj Bhatt | RE | DSC WB SPW Rudraprayag | See Pic |
17. | 12-11-2019 | 0+060 | Site inspected by Design Expert and PM of DSC | Manoj Bhatt | RE | DSC WB SPW Rudraprayag | See Pic |
18. | 11-11-2019 | 1+150 | Site inspected by Design expert,PM of DSC with EE. | Manoj Bhatt | RE | DSC WB SPW Rudraprayag | See Pic |
19. | 11-11-2019 | Chainage 1+150 | Site visit by Exn and DSC Team | Shivam Tiwari | Quality Control | DSC WB SPW Rudraprayag | See Pic |
20. | 07-11-2019 | At site camp | World bank social Environment site | Shivam Tiwari | Quality Control | DSC WB SPW Rudraprayag | See Pic |
|
|