Guptkashi Kalimath Slope Motor Road at KM-8
Work Completed
|
Project: |
UDRP-AF(Bridge/Slope) |
UID: |
4040 |
Sanction Cost: |
1958.04 lakh |
Length:
|
0.400 KM. |
District: |
Rudraprayag |
Block: |
Ukhimath |
Constituency: |
Kedarnath |
Circle: |
|
DEA: |
DEA Guptkashi |
DSC: |
CCEE Group India Pvt. Ltd in Association with JSV |
DSC Scope: |
Design and Supervision |
Type: |
Slope Protection Work |
|
Procurement: |
Package No.: 701
Package Name: 
UDRP/AF/SL/05
Tender Date: 24-01-2018
Current Status: Agreement signed
Achieved on Date: 23-07-2018 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/SL/05
Contractor Name: Bharat Construction
|
Start Date: 03-08-2018
Intended Completion Date: 02-02-2020
|
Total Bond Cost: 176669009.44 (1766.69 lakh)
Variation Cost: 78479504.05 (784.8 lakh) Hence Total Bond Cost is 255148513.49 (2551.49 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 25793820 for 292 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | GSB/RBI/G-1 | 0.40 KM | 6.13 | 16-08-2019 | 22-11-2019 | 0.40 KM | 0.40 KM | 0.27 | 6.13 | 2. | PC/CC i/c Prime Coat, Tack Coat | 0.40 KM | 25.67 | 16-09-2019 | 01-01-2020 | 0.40 KM | 0.40 KM | 1.13 | 25.67 | 3. | Stressing & Grouting | 1.00 Job | 49.01 | 08-11-2019 | 06-12-2019 | 1.00 Job | 1.00 Job | 2.15 | 49.01 | 4. | Env. Man & Moni Plan | 1.00 Job | 2.94 | 01-10-2018 | 01-01-2020 | 1.00 Job | 1.00 Job | 0.13 | 2.94 | 5. | Other Allied Works & Finishing Work | 1.00 Job | 108.96 | 01-11-2018 | 28-01-2020 | 1.00 Job | 1.00 Job | 4.78 | 108.96 | 6. | Steel Railing/crush barrier | 40.00 m | 1.15 | 15-12-2019 | 02-02-2020 | 40.00 m | 40.00 m | 0.05 | 1.15 | 7. | Gravity Bench Wall | 1725.25 m | 39.68 | 10-11-2018 | 04-09-2019 | 1725.25 m | 1725.25 m | 1.74 | 39.68 | 8. | Anchors | 26695.58 m | 621.03 | 05-11-2018 | 25-12-2019 | 26695.58 m | 26695.58 m | 27.26 | 621.03 | 9. | Hydroseeding,3-D Net, High tensile Rolled Cable Net | 47200.00 sqm | 707.44 | 05-11-2018 | 09-01-2020 | 47200.00 sqm | 47200.00 sqm | 31.05 | 707.44 | 10. | Gabion work | 1837.00 m | 165.23 | 12-11-2018 | 28-01-2020 | 1837.00 m | 1837.00 m | 7.25 | 165.23 | 11. | PCC in Foundation | 6516.63 cum | 529.88 | 28-11-2018 | 25-01-2020 | 6516.63 cum | 6516.63 cum | 23.26 | 529.88 | 12. | Excavation in soil | 13177.26 cum | 20.99 | 05-11-2018 | 20-01-2020 | 13177.26 cum | 13177.26 cum | 0.92 | 20.99 |
Total Amount: |
2278.11 |
|
100 |
2278.11 |
|
Remarks:
No Remarks
Work Program Made On:
02-11-2018 } ?>
Updation of work program on:
06-04-2021
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 08-January-2019 | 208.45 lakh | 2. | 28-February-2019 | 165.50 lakh | 3. | 08-March-2019 | 62.45 lakh | 4. | 30-March-2019 | 308.26 lakh | 5. | 16-May-2019 | 156.03 lakh | 6. | 20-June-2019 | 143.09 lakh | 7. | 30-June-2019 | 503.88 lakh | 8. | 28-August-2019 | 121.72 lakh | 9. | 30-October-2019 | 163.15 lakh | 10. | 05-December-2019 | 18.68 lakh | 11. | 17-February-2020 | 235.29 lakh | 12. | 19-May-2020 | 191.61 lakh |
Total |
2278.11 lakh |
% Payment |
89.29 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Bill sh
ould be issued | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 573 No. of Test Done : 578 No. of Test Passed : 573 No. of Test Failed : 5 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 86.13 |
Number of Notice(s) issued: 34 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 224 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 04-02-2020 | 0+258 | Concrete Steps at Downstream of Causeway | Manoj Bhatt | RE | DSC WB SPW Rudraprayag | See Pic |
2. | 04-02-2020 | 0+287 to 0+375 | Concrete Spurs on River, to Protect Gravity Bench Wall-2 | Manoj Bhatt | RE | DSC WB SPW Rudraprayag | See Pic |
3. | 27-01-2020 | 0+340 to 0+370 | GI chain linking Shotcrete mesh. | Sohan Singh Negi | Site Supervisor | DSC WB SPW Rudraprayag | See Pic |
4. | 04-01-2020 | 0+260 | CC steps work in progress. | Sohan Singh Negi | Site Supervisor | DSC WB SPW Rudraprayag | See Pic |
5. | 03-01-2020 | 0+300 to 0+380 | Concrete for spur in Progress | Manoj Bhatt | RE | DSC WB SPW Rudraprayag | See Pic |
6. | 03-01-2020 | Chainage 0+260 | Steps for causeway work in progress | Shivam Tiwari | QC | DSC WB SPW TEHRI | See Pic |
7. | 30-12-2019 | 0+065 to 0+085 | Gabion wall work in progress. | Sohan Singh Negi | Site Supervisor | DSC WB SPW Rudraprayag | See Pic |
8. | 30-12-2019 | 0+370 | CC wall for high tensile area protection. | Sohan Singh Negi | Site Supervisor | DSC WB SPW Rudraprayag | See Pic |
9. | 27-12-2019 | 0+210 | Providing and laying of perforated pipes for subsurface drainage. | Sohan Singh Negi | Site Supervisor | DSC WB SPW Rudraprayag | See Pic |
10. | 27-12-2019 | 0+260 | CC Steps for causeway work in progress. | Sohan Singh Negi | Site Supervisor | DSC WB SPW Rudraprayag | See Pic |
11. | 26-12-2019 | 0+295 | CC spur waork in progress. | Sohan Singh Negi | Site Supervisor | DSC WB SPW Rudraprayag | See Pic |
12. | 20-12-2019 | 0+120 to 0+210 | Hydroseeding (1st Burm),Grass Growing up. | Sohan Singh Negi | Site Supervisor | DSC WB SPW Rudraprayag | See Pic |
13. | 20-12-2019 | 0+290 | Concreting for spur work in progress. | Sohan Singh Negi | Site Supervisor | DSC WB SPW Rudraprayag | See Pic |
14. | 20-12-2019 | 0+140 | Site visit by DSC Project Manager. | Sohan Singh Negi | Site Supervisor | DSC WB SPW Rudraprayag | See Pic |
15. | 18-12-2019 | Chainage 0+350 | Gabion toe wall work on progress | Shivam Tiwari | Quality Control | DSC WB SPW Rudraprayag | See Pic |
16. | 17-12-2019 | 0+250 | cube casting and slump test for concrete steps. | Shivam Tiwari | Quality Control | DSC WB SPW Rudraprayag | See Pic |
17. | 17-12-2019 | Site laboratory | Cube testing at site laboratory | Shivam Tiwari | Quality Control | DSC WB SPW Rudraprayag | See Pic |
18. | 16-12-2019 | 0+300 | Excavation for spur at River edge work in progress. | Sohan Singh Negi | Site Supervisor | DSC WB SPW Rudraprayag | See Pic |
19. | 16-12-2019 | 0+290 to 0+340 | Gabion wall at river edge work in progress. | Sohan Singh Negi | Site Supervisor | DSC WB SPW Rudraprayag | See Pic |
20. | 16-12-2019 | Chainage 0+230 | Dressing for Side Drain | Shivam Tiwari | Quality Control | DSC WB SPW Rudraprayag | See Pic |
|
|