Guptkashi Kalimath Slope Motor Road at KM-8 Work Completed
Project: UDRP-AF(Bridge/Slope) UID: 4040 Sanction Cost: 1958.04  lakh Length: 0.400 KM.
District: Rudraprayag Block: Ukhimath Constituency: Kedarnath Circle:
DEA: DEA Guptkashi DSC: CCEE Group India Pvt. Ltd in Association with JSV DSC Scope: Design and Supervision Type: Slope Protection Work
Procurement:
Package No.: 701        Package Name:  UDRP/AF/SL/05        Tender Date: 24-01-2018        Current Status: Agreement signed        Achieved on Date: 23-07-2018

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/SL/05      Contractor Name: Bharat Construction
Start Date:  03-08-2018      Intended Completion Date:  02-02-2020     
Total Bond Cost: 176669009.44 (1766.69 lakh)        Variation Cost: 78479504.05 (784.8 lakh)    Hence Total Bond Cost is   255148513.49 (2551.49 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 25793820 for 292 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.GSB/RBI/G-10.40 KM6.1316-08-201922-11-20190.40 KM0.40 KM0.276.13
2.PC/CC i/c Prime Coat, Tack Coat0.40 KM25.6716-09-201901-01-20200.40 KM0.40 KM1.1325.67
3.Stressing & Grouting1.00 Job49.0108-11-201906-12-20191.00 Job1.00 Job2.1549.01
4.Env. Man & Moni Plan1.00 Job2.9401-10-201801-01-20201.00 Job1.00 Job0.132.94
5.Other Allied Works & Finishing Work 1.00 Job108.9601-11-201828-01-20201.00 Job1.00 Job4.78108.96
6.Steel Railing/crush barrier40.00 m1.1515-12-201902-02-202040.00 m40.00 m0.051.15
7.Gravity Bench Wall1725.25 m39.6810-11-201804-09-20191725.25 m1725.25 m1.7439.68
8.Anchors26695.58 m621.0305-11-201825-12-201926695.58 m26695.58 m27.26621.03
9.Hydroseeding,3-D Net, High tensile Rolled Cable Net47200.00 sqm707.4405-11-201809-01-202047200.00 sqm47200.00 sqm31.05707.44
10.Gabion work1837.00 m165.2312-11-201828-01-20201837.00 m1837.00 m7.25165.23
11.PCC in Foundation6516.63 cum529.8828-11-201825-01-20206516.63 cum6516.63 cum23.26529.88
12.Excavation in soil13177.26 cum20.9905-11-201820-01-202013177.26 cum13177.26 cum0.9220.99
Total Amount: 2278.11 100   2278.11
Remarks: No Remarks       Work Program Made On: 02-11-2018        Updation of work program on: 06-04-2021       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.08-January-2019208.45  lakh
2.28-February-2019165.50  lakh
3.08-March-201962.45  lakh
4.30-March-2019308.26  lakh
5.16-May-2019156.03  lakh
6.20-June-2019143.09  lakh
7.30-June-2019503.88  lakh
8.28-August-2019121.72  lakh
9.30-October-2019163.15  lakh
10.05-December-201918.68  lakh
11.17-February-2020235.29  lakh
12.19-May-2020191.61  lakh
Total 2278.11  lakh
% Payment 89.29 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 573   No. of Test Done : 578    No. of Test Passed : 573   No. of Test Failed : 5   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 86.13
Number of Notice(s) issued: 34

Mobile Pic Upload

Number of Pics Available on Web Repository: 224
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.04-02-20200+258Concrete Steps at Downstream of CausewayManoj BhattREDSC WB SPW Rudraprayag See Pic
2.04-02-20200+287 to 0+375Concrete Spurs on River, to Protect Gravity Bench Wall-2Manoj BhattREDSC WB SPW Rudraprayag See Pic
3.27-01-20200+340 to 0+370GI chain linking Shotcrete mesh.Sohan Singh NegiSite SupervisorDSC WB SPW Rudraprayag See Pic
4.04-01-20200+260CC steps work in progress.Sohan Singh NegiSite SupervisorDSC WB SPW Rudraprayag See Pic
5.03-01-20200+300 to 0+380Concrete for spur in ProgressManoj BhattREDSC WB SPW Rudraprayag See Pic
6.03-01-2020Chainage 0+260Steps for causeway work in progressShivam TiwariQCDSC WB SPW TEHRI See Pic
7.30-12-20190+065 to 0+085Gabion wall work in progress.Sohan Singh NegiSite SupervisorDSC WB SPW Rudraprayag See Pic
8.30-12-20190+370CC wall for high tensile area protection.Sohan Singh NegiSite SupervisorDSC WB SPW Rudraprayag See Pic
9.27-12-20190+210Providing and laying of perforated pipes for subsurface drainage.Sohan Singh NegiSite SupervisorDSC WB SPW Rudraprayag See Pic
10.27-12-20190+260CC Steps for causeway work in progress.Sohan Singh NegiSite SupervisorDSC WB SPW Rudraprayag See Pic
11.26-12-20190+295CC spur waork in progress.Sohan Singh NegiSite SupervisorDSC WB SPW Rudraprayag See Pic
12.20-12-20190+120 to 0+210Hydroseeding (1st Burm),Grass Growing up.Sohan Singh NegiSite SupervisorDSC WB SPW Rudraprayag See Pic
13.20-12-20190+290Concreting for spur work in progress.Sohan Singh NegiSite SupervisorDSC WB SPW Rudraprayag See Pic
14.20-12-20190+140Site visit by DSC Project Manager.Sohan Singh NegiSite SupervisorDSC WB SPW Rudraprayag See Pic
15.18-12-2019Chainage 0+350Gabion toe wall work on progressShivam TiwariQuality ControlDSC WB SPW Rudraprayag See Pic
16.17-12-20190+250cube casting and slump test for concrete steps.Shivam TiwariQuality ControlDSC WB SPW Rudraprayag See Pic
17.17-12-2019Site laboratoryCube testing at site laboratoryShivam TiwariQuality ControlDSC WB SPW Rudraprayag See Pic
18.16-12-20190+300Excavation for spur at River edge work in progress.Sohan Singh NegiSite SupervisorDSC WB SPW Rudraprayag See Pic
19.16-12-20190+290 to 0+340Gabion wall at river edge work in progress.Sohan Singh NegiSite SupervisorDSC WB SPW Rudraprayag See Pic
20.16-12-2019Chainage 0+230Dressing for Side DrainShivam TiwariQuality ControlDSC WB SPW Rudraprayag See Pic