Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Guptkashi - Jakholi Slope MR at Km No.17 Agreement signed
Project: UDRP-AF(Bridge/Slope) UID: 4038 Sanction Cost: 584.09  lakh Length: 0.050 KM.
District: Rudraprayag Block: Ukhimath Constituency: Kedarnath Circle:
DEA: DEA Guptkashi DSC: CCEE Group India Pvt. Ltd in Association with JSV DSC Scope: Design and Supervision Type: Slope Protection Work
Procurement:
Package No.: 703        Package Name:  UDRP/AF/SL/03        Tender Date: 11-06-2018        Current Status: Agreement signed        Achieved on Date: 25-09-2018

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/SL/03      Contractor Name: Starcon Infra Projects (I) Pvt. Ltd.
Start Date:  30-09-2018      Intended Completion Date:  29-09-2019     
Total Bond Cost: 34906911.01 (349.07 lakh)       
LD Analysis for Milestone1: calculated LD is Rs 23893157 for 1369 days        LD Analysis for Milestone2: calculated LD is Rs 23893157 for 1369 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.G-20.11 KM1.6720-03-201931-03-20190.11 KM0.00 KM00.00
2.G-30.11 KM0.8301-04-201910-04-20190.11 KM0.00 KM00.00
3.PC/CC i/c Prime Coat, Tack Coat0.11 KM18.7711-04-201913-04-20190.11 KM0.00 KM00.00
4.Other Allied Works & Finishing Work 1.00 Job3.0401-12-201830-08-20191.00 Job0.10 Job0.080.30
5.Gravity Bench Wall90.00 m133.4401-11-201830-03-201990.00 m5.00 m2.037.41
6.Anchors1418.50 m46.3715-12-201810-05-20191418.50 m0.00 m00.00
7.Micropile1050.00 m45.2810-11-201810-02-20191050.00 m0.00 m00.00
8.Gabion work1618.67 m116.5601-01-201915-05-20191618.67 m0.00 m00.00
Total Amount: 365.96 2.11   7.71
Remarks: No Remarks       Work Program Made On: 02-11-2018        Updation of work program on:       
Work Program Status:Program Expired.
Financial Progress
No Financial Progress.
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level): labour licence
Environment & Social Compliances(Sub Project level): project information board
Detailed report of this subproject
Quality
Test Information not Available.
Quality Ranking in %: 90.00
Number of Notice(s) issued: 8

Mobile Pic Upload

Number of Pics Available on Web Repository: 9
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.24-12-2020Jakh jakhedaCoarse aggregate (20mm) gradation test for BR 61 a2 side 1st abutment shaft lift concrete catingDeepak PantSite supervisiorUDRP AF Irrigation birahi See Pic
2.28-12-2018Km 17Site visit by EME sir.Anurag DevJEUDRP R&B Guptkashi See Pic
3.28-12-2018Km17Site visit by CME sir.Anurag DevJEUDRP R&B Guptkashi See Pic
4.04-12-2018Guptkashi mayali km 17Bush cutting.Anurag DevJEUDRP R&B Guptkashi See Pic
5.04-12-2018Guptkashi jakholi km 17Informatory boardAnurag DevJEUDRP R&B Guptkashi See Pic
6.31-10-2018At shivganga stone crusherSample collection at shivganga stone crusher source of approvalPrashant KumarQCDSC WB SPW Rudraprayag See Pic
7.31-10-2018At crusherSample collection at shivganga stone crusher source of approvalPrashant KumarQCDSC WB SPW Rudraprayag See Pic
8.31-10-2018At crusherSample collection at shivganga stone crusherPrashant KumarQCDSC WB SPW Rudraprayag See Pic
9.10-10-2018Km17T.L sir ,RE sir site visitBhagwat Singh BangariSite SupervisorDSC WB SPW Rudraprayag See Pic