Guptkashi - Jakholi Slope MR at Km No.17
Agreement signed
|
Project: |
UDRP-AF(Bridge/Slope) |
UID: |
4038 |
Sanction Cost: |
584.09 lakh |
Length:
|
0.050 KM. |
District: |
Rudraprayag |
Block: |
Ukhimath |
Constituency: |
Kedarnath |
Circle: |
|
DEA: |
DEA Guptkashi |
DSC: |
CCEE Group India Pvt. Ltd in Association with JSV |
DSC Scope: |
Design and Supervision |
Type: |
Slope Protection Work |
|
Procurement: |
Package No.: 703
Package Name: 
UDRP/AF/SL/03
Tender Date: 11-06-2018
Current Status: Agreement signed
Achieved on Date: 25-09-2018 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/SL/03
Contractor Name: Starcon Infra Projects (I) Pvt. Ltd.
|
Start Date: 30-09-2018
Intended Completion Date: 29-09-2019
|
Total Bond Cost: 34906911.01 (349.07 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 23893157 for 1369 days
LD Analysis for Milestone2: calculated LD is Rs 23893157 for 1369 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | G-2 | 0.11 KM | 1.67 | 20-03-2019 | 31-03-2019 | 0.11 KM | 0.00 KM | 0 | 0.00 | 2. | G-3 | 0.11 KM | 0.83 | 01-04-2019 | 10-04-2019 | 0.11 KM | 0.00 KM | 0 | 0.00 | 3. | PC/CC i/c Prime Coat, Tack Coat | 0.11 KM | 18.77 | 11-04-2019 | 13-04-2019 | 0.11 KM | 0.00 KM | 0 | 0.00 | 4. | Other Allied Works & Finishing Work | 1.00 Job | 3.04 | 01-12-2018 | 30-08-2019 | 1.00 Job | 0.10 Job | 0.08 | 0.30 | 5. | Gravity Bench Wall | 90.00 m | 133.44 | 01-11-2018 | 30-03-2019 | 90.00 m | 5.00 m | 2.03 | 7.41 | 6. | Anchors | 1418.50 m | 46.37 | 15-12-2018 | 10-05-2019 | 1418.50 m | 0.00 m | 0 | 0.00 | 7. | Micropile | 1050.00 m | 45.28 | 10-11-2018 | 10-02-2019 | 1050.00 m | 0.00 m | 0 | 0.00 | 8. | Gabion work | 1618.67 m | 116.56 | 01-01-2019 | 15-05-2019 | 1618.67 m | 0.00 m | 0 | 0.00 |
Total Amount: |
365.96 |
|
2.11 |
7.71 |
|
Remarks:
No Remarks
Work Program Made On:
02-11-2018 } ?>
Updation of work program on:
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
No Financial Progress.
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level):
labour licence
Environment & Social Compliances(Sub Project level):
project information board |
Detailed report of this subproject
|
|
Quality
|
Test Information not Available. |
Quality Ranking in %: 90.00 |
Number of Notice(s) issued: 8 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 9 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 24-12-2020 | Jakh jakheda | Coarse aggregate (20mm) gradation test for BR 61 a2 side 1st abutment shaft lift concrete cating | Deepak Pant | Site supervisior | UDRP AF Irrigation birahi | See Pic |
2. | 28-12-2018 | Km 17 | Site visit by EME sir. | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
3. | 28-12-2018 | Km17 | Site visit by CME sir. | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
4. | 04-12-2018 | Guptkashi mayali km 17 | Bush cutting. | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
5. | 04-12-2018 | Guptkashi jakholi km 17 | Informatory board | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
6. | 31-10-2018 | At shivganga stone crusher | Sample collection at shivganga stone crusher source of approval | Prashant Kumar | QC | DSC WB SPW Rudraprayag | See Pic |
7. | 31-10-2018 | At crusher | Sample collection at shivganga stone crusher source of approval | Prashant Kumar | QC | DSC WB SPW Rudraprayag | See Pic |
8. | 31-10-2018 | At crusher | Sample collection at shivganga stone crusher | Prashant Kumar | QC | DSC WB SPW Rudraprayag | See Pic |
9. | 10-10-2018 | Km17 | T.L sir ,RE sir site visit | Bhagwat Singh Bangari | Site Supervisor | DSC WB SPW Rudraprayag | See Pic |
|
|