Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Bridge at KM 15 of Balmara Syalde Kedar MR Agreement signed
Project: UDRP-AF(Bridge/Slope) UID: 4034 Sanction Cost: 1182.96  lakh Span: 105.000 M
District: Almora Block: Bhikiyasain Constituency: Salt Circle:
DEA: DEA Bageshwar DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision Type: Bridge
Procurement:
Package No.: 604        Package Name:  UDRP/AF/32(BR)        Tender Date: 24-08-2018        Current Status: Agreement signed        Achieved on Date: 29-11-2018

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/32(BR)      Contractor Name: Kailash Hillways Engineering Associates
Start Date:  07-12-2018      Intended Completion Date:  11-07-2022      Original End Date:  05-03-2020
Total Bond Cost: 134280079.36 (1342.8 lakh)        Variation Cost: 17918572.70 (179.19 lakh)    Hence Total Bond Cost is   152198652.06 (1521.99 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 49280760 for 734 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Env. Man & Moni Plan1.00 Job3.6307-12-201830-06-20221.00 Job1.00 Job0.293.63
2.Other Allied Works & Finishing Work 1.00 Job115.3216-09-201930-06-20221.00 Job1.00 Job9.36115.32
3.Foundation RHS1.00 Job32.0507-12-201815-03-20201.00 Job1.00 Job2.632.05
4.Foundation LHS1.00 Job13.7407-12-201815-03-20201.00 Job1.00 Job1.1113.74
5.Abutment Superstructure RHS0.00 Job0.0001-05-201901-05-20190.00 Job0.00 Job00.00
6.Abutment Superstructure LHS0.00 Job0.0001-05-201901-07-20200.00 Job0.00 Job00.00
7.Deck Cable laying, stretching and Fixing Transoms/Deck Slab 1.00 no33.7915-02-202115-03-20211.00 no1.00 no2.7433.79
8.Fixing of chequered Plate/RCC Deck173.00 sqm33.7921-05-202210-06-2022173.00 sqm173.00 sqm2.7433.79
9.Steel Railing/crush barrier1.00 m4.0410-06-202228-06-20221.00 m0.00 m00.00
10.Approach Ramp /path 2.00 m218.7520-09-201912-06-20222.00 m2.00 m17.75218.75
11.Protection Work1.00 Job39.4715-09-201915-04-20211.00 Job1.00 Job3.239.47
12.Errection Work1.00 Job146.7001-01-202115-02-20211.00 Job1.00 Job11.9146.70
13.Fabrication Work1.00 job352.8010-07-202031-12-20201.00 job1.00 job28.62352.80
14.Abutment Substructure RHS1.00 Job143.1801-08-201915-04-20201.00 Job1.00 Job11.62143.18
15.Abutment Substructure LHS1.00 Job95.4601-09-202031-12-20201.00 Job1.00 Job7.7495.46
Total Amount: 1232.72 99.67   1228.68
Remarks: No Remarks       Work Program Made On: 29-03-2019        Updation of work program on: 22-05-2022       
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.30-June-201923.28  lakh
2.31-July-201949.53  lakh
3.11-October-201950.74  lakh
4.23-October-201918.25  lakh
5.30-December-201930.02  lakh
6.02-March-202072.44  lakh
7.11-June-202084.37  lakh
8.09-November-202057.14  lakh
9.02-December-2020287.99  lakh
10.15-February-2021124.52  lakh
11.30-March-202157.65  lakh
12.18-December-202169.57  lakh
13.22-February-2022232.27  lakh
14.31-March-202251.33  lakh
15.22-August-202259.01  lakh
16.30-November-2022110.01  lakh
Total 1378.12  lakh
% Payment 100.44 %
Advance Amount:  117.56  lakh        Recovered Amount:  109.67  lakh        Balance to be Recovered  7.89  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level): No Pending Issue
Environment & Social Compliances(Sub Project level): water sprinkling
Detailed report of this subproject
Quality
No. of Test Required : 2246   No. of Test Done : 2256    No. of Test Passed : 2246   No. of Test Failed : 10   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 95.00
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 387
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.23-06-2022Km 15Deck slab Steel Binding in progressGovind Kumar ` ` See Pic
2.23-06-2022Km 15CampGovind Kumar ` ` See Pic
3.23-06-2022Km 15Health and safety training campGovind Kumar ` ` See Pic
4.23-06-2022Km 15Health checkup campGovind Kumar ` ` See Pic
5.23-06-2022Km 15Steel Binding in deck slab in progressGovind kumar ` ` See Pic
6.21-06-2022KM 15Super structureGovind kumar ` ` See Pic
7.21-06-2022KM -15Bolt torque checkingGovind kumar ` ` See Pic
8.21-06-2022Km 15Checking of bolt torque of bottom chordGovind kumar ` ` See Pic
9.21-06-2022A2Labour Health Checkup camp.Azhar ` ` See Pic
10.21-06-2022A2Labour Health Checkup campAzhar ` ` See Pic
11.15-06-2022BR-32Deck Slab Reinforcement.Azhar ` ` See Pic
12.10-06-2022Km 15Deck slab reinforcement binding in progressGovind kumar ` ` See Pic
13.10-06-2022Km 15Deck slab reinforcement binding work in progressGovind kumar ` ` See Pic
14.03-06-2022Ch 15Super structureGovind ` ` See Pic
15.03-06-2022A1BR-32Azhar ` ` See Pic
16.03-06-2022A2Bearing fixedAzhar ` ` See Pic
17.27-05-2022Bridge BR32Deck slab shuttering work in progress.Rajesh sharma ` ` See Pic
18.26-05-2022A1Shuttering work in progress.Azhar ` ` See Pic
19.26-05-2022Km 15BR -32Govind kumar ` ` See Pic
20.26-05-2022Km 15Super structureGovind kumar ` ` See Pic