Bridge at KM 15 of Balmara Syalde Kedar MR
Agreement signed
|
Project: |
UDRP-AF(Bridge/Slope) |
UID: |
4034 |
Sanction Cost: |
1182.96 lakh |
Span:
|
105.000 M |
District: |
Almora |
Block: |
Bhikiyasain |
Constituency: |
Salt |
Circle: |
|
DEA: |
DEA Bageshwar |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
Type: |
Bridge |
|
Procurement: |
Package No.: 604
Package Name: 
UDRP/AF/32(BR)
Tender Date: 24-08-2018
Current Status: Agreement signed
Achieved on Date: 29-11-2018 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/32(BR)
Contractor Name: Kailash Hillways Engineering Associates
|
Start Date: 07-12-2018
Intended Completion Date: 11-07-2022
Original End Date: 05-03-2020 |
Total Bond Cost: 134280079.36 (1342.8 lakh)
Variation Cost: 17918572.70 (179.19 lakh) Hence Total Bond Cost is 152198652.06 (1521.99 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 49280760 for 734 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Env. Man & Moni Plan | 1.00 Job | 3.63 | 07-12-2018 | 30-06-2022 | 1.00 Job | 1.00 Job | 0.29 | 3.63 | 2. | Other Allied Works & Finishing Work | 1.00 Job | 115.32 | 16-09-2019 | 30-06-2022 | 1.00 Job | 1.00 Job | 9.36 | 115.32 | 3. | Foundation RHS | 1.00 Job | 32.05 | 07-12-2018 | 15-03-2020 | 1.00 Job | 1.00 Job | 2.6 | 32.05 | 4. | Foundation LHS | 1.00 Job | 13.74 | 07-12-2018 | 15-03-2020 | 1.00 Job | 1.00 Job | 1.11 | 13.74 | 5. | Abutment Superstructure RHS | 0.00 Job | 0.00 | 01-05-2019 | 01-05-2019 | 0.00 Job | 0.00 Job | 0 | 0.00 | 6. | Abutment Superstructure LHS | 0.00 Job | 0.00 | 01-05-2019 | 01-07-2020 | 0.00 Job | 0.00 Job | 0 | 0.00 | 7. | Deck Cable laying, stretching and Fixing Transoms/Deck Slab | 1.00 no | 33.79 | 15-02-2021 | 15-03-2021 | 1.00 no | 1.00 no | 2.74 | 33.79 | 8. | Fixing of chequered Plate/RCC Deck | 173.00 sqm | 33.79 | 21-05-2022 | 10-06-2022 | 173.00 sqm | 173.00 sqm | 2.74 | 33.79 | 9. | Steel Railing/crush barrier | 1.00 m | 4.04 | 10-06-2022 | 28-06-2022 | 1.00 m | 0.00 m | 0 | 0.00 | 10. | Approach Ramp /path | 2.00 m | 218.75 | 20-09-2019 | 12-06-2022 | 2.00 m | 2.00 m | 17.75 | 218.75 | 11. | Protection Work | 1.00 Job | 39.47 | 15-09-2019 | 15-04-2021 | 1.00 Job | 1.00 Job | 3.2 | 39.47 | 12. | Errection Work | 1.00 Job | 146.70 | 01-01-2021 | 15-02-2021 | 1.00 Job | 1.00 Job | 11.9 | 146.70 | 13. | Fabrication Work | 1.00 job | 352.80 | 10-07-2020 | 31-12-2020 | 1.00 job | 1.00 job | 28.62 | 352.80 | 14. | Abutment Substructure RHS | 1.00 Job | 143.18 | 01-08-2019 | 15-04-2020 | 1.00 Job | 1.00 Job | 11.62 | 143.18 | 15. | Abutment Substructure LHS | 1.00 Job | 95.46 | 01-09-2020 | 31-12-2020 | 1.00 Job | 1.00 Job | 7.74 | 95.46 |
Total Amount: |
1232.72 |
|
99.67 |
1228.68 |
|
Remarks:
No Remarks
Work Program Made On:
29-03-2019 } ?>
Updation of work program on:
22-05-2022
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 30-June-2019 | 23.28 lakh | 2. | 31-July-2019 | 49.53 lakh | 3. | 11-October-2019 | 50.74 lakh | 4. | 23-October-2019 | 18.25 lakh | 5. | 30-December-2019 | 30.02 lakh | 6. | 02-March-2020 | 72.44 lakh | 7. | 11-June-2020 | 84.37 lakh | 8. | 09-November-2020 | 57.14 lakh | 9. | 02-December-2020 | 287.99 lakh | 10. | 15-February-2021 | 124.52 lakh | 11. | 30-March-2021 | 57.65 lakh | 12. | 18-December-2021 | 69.57 lakh | 13. | 22-February-2022 | 232.27 lakh | 14. | 31-March-2022 | 51.33 lakh | 15. | 22-August-2022 | 59.01 lakh | 16. | 30-November-2022 | 110.01 lakh |
Total |
1378.12 lakh |
% Payment |
100.44 % |
|
Advance Amount: 117.56 lakh
Recovered Amount: 109.67 lakh
Balance to be Recovered 7.89 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level):
No Pending Issue
Environment & Social Compliances(Sub Project level):
water sprinkling |
Detailed report of this subproject
|
|
Quality
|
No. of Test Required : 2246 No. of Test Done : 2256 No. of Test Passed : 2246 No. of Test Failed : 10 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 95.00 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 387 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 23-06-2022 | Km 15 | Deck slab Steel Binding in progress | Govind Kumar | ` | ` | See Pic |
2. | 23-06-2022 | Km 15 | Camp | Govind Kumar | ` | ` | See Pic |
3. | 23-06-2022 | Km 15 | Health and safety training camp | Govind Kumar | ` | ` | See Pic |
4. | 23-06-2022 | Km 15 | Health checkup camp | Govind Kumar | ` | ` | See Pic |
5. | 23-06-2022 | Km 15 | Steel Binding in deck slab in progress | Govind kumar | ` | ` | See Pic |
6. | 21-06-2022 | KM 15 | Super structure | Govind kumar | ` | ` | See Pic |
7. | 21-06-2022 | KM -15 | Bolt torque checking | Govind kumar | ` | ` | See Pic |
8. | 21-06-2022 | Km 15 | Checking of bolt torque of bottom chord | Govind kumar | ` | ` | See Pic |
9. | 21-06-2022 | A2 | Labour Health Checkup camp. | Azhar | ` | ` | See Pic |
10. | 21-06-2022 | A2 | Labour Health Checkup camp | Azhar | ` | ` | See Pic |
11. | 15-06-2022 | BR-32 | Deck Slab Reinforcement. | Azhar | ` | ` | See Pic |
12. | 10-06-2022 | Km 15 | Deck slab reinforcement binding in progress | Govind kumar | ` | ` | See Pic |
13. | 10-06-2022 | Km 15 | Deck slab reinforcement binding work in progress | Govind kumar | ` | ` | See Pic |
14. | 03-06-2022 | Ch 15 | Super structure | Govind | ` | ` | See Pic |
15. | 03-06-2022 | A1 | BR-32 | Azhar | ` | ` | See Pic |
16. | 03-06-2022 | A2 | Bearing fixed | Azhar | ` | ` | See Pic |
17. | 27-05-2022 | Bridge BR32 | Deck slab shuttering work in progress. | Rajesh sharma | ` | ` | See Pic |
18. | 26-05-2022 | A1 | Shuttering work in progress. | Azhar | ` | ` | See Pic |
19. | 26-05-2022 | Km 15 | BR -32 | Govind kumar | ` | ` | See Pic |
20. | 26-05-2022 | Km 15 | Super structure | Govind kumar | ` | ` | See Pic |
|
|