Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Bridge at KM 1 of Balmara Syalde Kedar MR Work Completed
Project: UDRP-AF(Bridge/Slope) UID: 4033 Sanction Cost: 215.14  lakh Span: 30.000 M
District: Almora Block: Sult Constituency: Salt Circle:
DEA: DEA Bageshwar DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision Type: Bridge
Procurement:
Package No.: 603        Package Name:  UDRP/AF/31(BR)        Tender Date: 29-06-2018        Current Status: Agreement signed        Achieved on Date: 28-09-2018

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/31(BR)      Contractor Name: Maa Shailputri Associates
Start Date:  05-10-2018      Intended Completion Date:  11-07-2020      Original End Date:  04-10-2019
Total Bond Cost: 16477350.4 (164.77 lakh)        Variation Cost: 1230028.08 (12.3 lakh)    Hence Total Bond Cost is   17707378.48 (177.07 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 2685914 for 326 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Env. Man & Moni Plan1.00 Job3.0506-10-201815-03-20201.00 Job1.00 Job1.723.05
2.Other Allied Works & Finishing Work 1.00 Job1.7001-04-201915-09-20201.00 Job1.00 Job0.961.70
3.Foundation RHS1.00 Job12.4206-10-201815-03-20201.00 Job1.00 Job7.0112.42
4.Foundation LHS1.00 Job12.4201-11-201815-03-20201.00 Job1.00 Job7.0112.42
5.Abutment Superstructure RHS1.00 Job26.3815-01-201915-03-20201.00 Job1.00 Job14.926.38
6.Abutment Superstructure LHS1.00 Job26.3801-02-201915-03-20201.00 Job1.00 Job14.926.38
7.Fixing of chequered Plate/RCC Deck201.24 sqm3.0705-07-201920-09-2019201.24 sqm201.24 sqm1.743.07
8.Steel Railing/crush barrier76.00 m3.9420-09-201904-10-201976.00 m76.00 m2.233.94
9.Approach Ramp /path 140.00 m35.5320-04-201915-09-2020140.00 m140.00 m20.0635.53
10.Protection Work1.00 Job8.9101-04-201915-03-20201.00 Job1.00 Job5.038.91
11.Errection Work1.00 Job43.2818-06-201915-03-20201.00 Job1.00 Job24.4443.28
Total Amount: 177.08 100   177.08
Remarks: No Remarks       Work Program Made On: 22-12-2018        Updation of work program on: 17-03-2021       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.16-May-201952.40  lakh
2.30-June-201918.25  lakh
3.30-December-201942.30  lakh
4.04-July-202030.25  lakh
5.09-April-202133.87  lakh
Total 177.07  lakh
% Payment 100 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 369   No. of Test Done : 370    No. of Test Passed : 370   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 95.00
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 134
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.07-07-202130 mtr span steel girder bridge at balmara syalde kedar mr km 01Information sign board in hindiJagdish narayan meena ` ` See Pic
2.07-07-202130 mtr span steel girder bridge at balmara syalde kedar mr km 01Information sign boardJagdish narayan meena ` ` See Pic
3.14-07-2020KM-1Seal Coat Complete A1 Side at 31(BR)Charu UpadhyayQSDSC WB Bridge Almora See Pic
4.14-07-2020KM-1A1 side OGPC Complete.Charu UpadhyayQSDSC WB Bridge Almora See Pic
5.11-07-2020KM-1 Balmara Kedar Sakde Motor Road.Seal Coat Complete A2 Side Approach Road.Charu UpadhyayQSDSC WB Bridge Almora See Pic
6.11-07-2020KM-1 Balmara Kedar Syalde Motor Road.OGPC work Complete A2 Side Approach Road At 31(BR)Charu UpadhyayQSDSC WB Bridge Almora See Pic
7.06-07-2020Km01EXEN sir visit at BR-31Govind kumarunknownunknown See Pic
8.03-07-2020Balmara Kedar Syalde M/R KM-1ExEn sir visit 31(BR)Charu UpadhyayQSDSC WB Bridge Almora See Pic
9.25-06-2020KM 01Deck slab BR-31Govind kumarunknownunknown See Pic
10.20-06-2020Bridge BR 32Deck slab and crash barrierRajesh sharmaunknownunknown See Pic
11.20-06-2020Deck slab BR 31Deck slabRajesh sharmaunknownunknown See Pic
12.20-02-2020Deck slabReinforcement work in progressRajesh sharmaunknownunknown See Pic
13.10-02-2020Bolt tightening of girderLeft girder bolt tighteningRajesh sharmaunknownunknown See Pic
14.10-02-2020A1 side dirt wall reinforcement and shuttering in progessReinforcement and shuttering in progressRajesh sharmaunknownunknown See Pic
15.03-02-2020BR31Bolt tightening of steel girderRajesh sharmaunknownunknown See Pic
16.16-12-201930m span bridge at km 01 of balamara kedar syalde motor road dist. AlmoraErection work is in progressRohit KumarAssistant EngineerUDRP AF S&B Bageshwar See Pic
17.11-12-201930m span bridge at km 01 of balamara kedar syalde motor road dist almoraErection work is in progressRohit KumarAssistant EngineerUDRP AF S&B Bageshwar See Pic
18.06-12-201930 m span steel gurder bridge At km 01 of balmara kedar syalde motor road dist. AlmoraStructural steel reached at siteRohit KumarAssistant EngineerUDRP AF S&B Bageshwar See Pic
19.09-09-2019KM 1 of Balmara-Kedar-Syalde MRExcavation for A2 Side Approach Road in progress.Charu UpadhyayQSDSC WB Bridge Almora See Pic
20.10-08-201930 M Span Bridge at KM-1 Balmara -Kedar-Syalde Motor RoadStone masonry Work is in progress A1 Side.Charu UpadhyayQSDSC WB Bridge Almora See Pic