Bridge at KM 1 of Balmara Syalde Kedar MR
Work Completed
|
Project: |
UDRP-AF(Bridge/Slope) |
UID: |
4033 |
Sanction Cost: |
215.14 lakh |
Span:
|
30.000 M |
District: |
Almora |
Block: |
Sult |
Constituency: |
Salt |
Circle: |
|
DEA: |
DEA Bageshwar |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
Type: |
Bridge |
|
Procurement: |
Package No.: 603
Package Name: 
UDRP/AF/31(BR)
Tender Date: 29-06-2018
Current Status: Agreement signed
Achieved on Date: 28-09-2018 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/31(BR)
Contractor Name: Maa Shailputri Associates
|
Start Date: 05-10-2018
Intended Completion Date: 11-07-2020
Original End Date: 04-10-2019 |
Total Bond Cost: 16477350.4 (164.77 lakh)
Variation Cost: 1230028.08 (12.3 lakh) Hence Total Bond Cost is 17707378.48 (177.07 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 2685914 for 326 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Env. Man & Moni Plan | 1.00 Job | 3.05 | 06-10-2018 | 15-03-2020 | 1.00 Job | 1.00 Job | 1.72 | 3.05 | 2. | Other Allied Works & Finishing Work | 1.00 Job | 1.70 | 01-04-2019 | 15-09-2020 | 1.00 Job | 1.00 Job | 0.96 | 1.70 | 3. | Foundation RHS | 1.00 Job | 12.42 | 06-10-2018 | 15-03-2020 | 1.00 Job | 1.00 Job | 7.01 | 12.42 | 4. | Foundation LHS | 1.00 Job | 12.42 | 01-11-2018 | 15-03-2020 | 1.00 Job | 1.00 Job | 7.01 | 12.42 | 5. | Abutment Superstructure RHS | 1.00 Job | 26.38 | 15-01-2019 | 15-03-2020 | 1.00 Job | 1.00 Job | 14.9 | 26.38 | 6. | Abutment Superstructure LHS | 1.00 Job | 26.38 | 01-02-2019 | 15-03-2020 | 1.00 Job | 1.00 Job | 14.9 | 26.38 | 7. | Fixing of chequered Plate/RCC Deck | 201.24 sqm | 3.07 | 05-07-2019 | 20-09-2019 | 201.24 sqm | 201.24 sqm | 1.74 | 3.07 | 8. | Steel Railing/crush barrier | 76.00 m | 3.94 | 20-09-2019 | 04-10-2019 | 76.00 m | 76.00 m | 2.23 | 3.94 | 9. | Approach Ramp /path | 140.00 m | 35.53 | 20-04-2019 | 15-09-2020 | 140.00 m | 140.00 m | 20.06 | 35.53 | 10. | Protection Work | 1.00 Job | 8.91 | 01-04-2019 | 15-03-2020 | 1.00 Job | 1.00 Job | 5.03 | 8.91 | 11. | Errection Work | 1.00 Job | 43.28 | 18-06-2019 | 15-03-2020 | 1.00 Job | 1.00 Job | 24.44 | 43.28 |
Total Amount: |
177.08 |
|
100 |
177.08 |
|
Remarks:
No Remarks
Work Program Made On:
22-12-2018 } ?>
Updation of work program on:
17-03-2021
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 16-May-2019 | 52.40 lakh | 2. | 30-June-2019 | 18.25 lakh | 3. | 30-December-2019 | 42.30 lakh | 4. | 04-July-2020 | 30.25 lakh | 5. | 09-April-2021 | 33.87 lakh |
Total |
177.07 lakh |
% Payment |
100 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 369 No. of Test Done : 370 No. of Test Passed : 370 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 95.00 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 134 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 07-07-2021 | 30 mtr span steel girder bridge at balmara syalde kedar mr km 01 | Information sign board in hindi | Jagdish narayan meena | ` | ` | See Pic |
2. | 07-07-2021 | 30 mtr span steel girder bridge at balmara syalde kedar mr km 01 | Information sign board | Jagdish narayan meena | ` | ` | See Pic |
3. | 14-07-2020 | KM-1 | Seal Coat Complete A1 Side at 31(BR) | Charu Upadhyay | QS | DSC WB Bridge Almora | See Pic |
4. | 14-07-2020 | KM-1 | A1 side OGPC Complete. | Charu Upadhyay | QS | DSC WB Bridge Almora | See Pic |
5. | 11-07-2020 | KM-1 Balmara Kedar Sakde Motor Road. | Seal Coat Complete A2 Side Approach Road. | Charu Upadhyay | QS | DSC WB Bridge Almora | See Pic |
6. | 11-07-2020 | KM-1 Balmara Kedar Syalde Motor Road. | OGPC work Complete A2 Side Approach Road At 31(BR) | Charu Upadhyay | QS | DSC WB Bridge Almora | See Pic |
7. | 06-07-2020 | Km01 | EXEN sir visit at BR-31 | Govind kumar | unknown | unknown | See Pic |
8. | 03-07-2020 | Balmara Kedar Syalde M/R KM-1 | ExEn sir visit 31(BR) | Charu Upadhyay | QS | DSC WB Bridge Almora | See Pic |
9. | 25-06-2020 | KM 01 | Deck slab BR-31 | Govind kumar | unknown | unknown | See Pic |
10. | 20-06-2020 | Bridge BR 32 | Deck slab and crash barrier | Rajesh sharma | unknown | unknown | See Pic |
11. | 20-06-2020 | Deck slab BR 31 | Deck slab | Rajesh sharma | unknown | unknown | See Pic |
12. | 20-02-2020 | Deck slab | Reinforcement work in progress | Rajesh sharma | unknown | unknown | See Pic |
13. | 10-02-2020 | Bolt tightening of girder | Left girder bolt tightening | Rajesh sharma | unknown | unknown | See Pic |
14. | 10-02-2020 | A1 side dirt wall reinforcement and shuttering in progess | Reinforcement and shuttering in progress | Rajesh sharma | unknown | unknown | See Pic |
15. | 03-02-2020 | BR31 | Bolt tightening of steel girder | Rajesh sharma | unknown | unknown | See Pic |
16. | 16-12-2019 | 30m span bridge at km 01 of balamara kedar syalde motor road dist. Almora | Erection work is in progress | Rohit Kumar | Assistant Engineer | UDRP AF S&B Bageshwar | See Pic |
17. | 11-12-2019 | 30m span bridge at km 01 of balamara kedar syalde motor road dist almora | Erection work is in progress | Rohit Kumar | Assistant Engineer | UDRP AF S&B Bageshwar | See Pic |
18. | 06-12-2019 | 30 m span steel gurder bridge At km 01 of balmara kedar syalde motor road dist. Almora | Structural steel reached at site | Rohit Kumar | Assistant Engineer | UDRP AF S&B Bageshwar | See Pic |
19. | 09-09-2019 | KM 1 of Balmara-Kedar-Syalde MR | Excavation for A2 Side Approach Road in progress. | Charu Upadhyay | QS | DSC WB Bridge Almora | See Pic |
20. | 10-08-2019 | 30 M Span Bridge at KM-1 Balmara -Kedar-Syalde Motor Road | Stone masonry Work is in progress A1 Side. | Charu Upadhyay | QS | DSC WB Bridge Almora | See Pic |
|
|