Suspension Bridge over Saryu river at Nisni
Work Completed
|
Project: |
UDRP-RB |
UID: |
4026 |
Sanction Cost: |
607.00 lakh |
Span:
|
90.000 M |
District: |
Pithoragarh |
Block: |
Pithoragarh(Bin) |
Constituency: |
Pithoragarh |
Circle: |
|
DEA: |
DEA Champawat |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Only Supervision |
Type: |
Bridge |
|
Procurement: |
Package No.: 521
Package Name: 
UDRP/PWD/07/15/BR/25
Tender Date: 15-12-2015
Current Status: Agreement signed
Achieved on Date: 19-05-2016 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/07/15/BR/25
Contractor Name: K M Engineering & Construction
|
Start Date: 26-05-2016
Intended Completion Date: 31-05-2018
Original End Date: 25-08-2017 |
Total Bond Cost: 52647290.8 (526.47 lakh)
Variation Cost: 4789759.90 (47.9 lakh) Hence Total Bond Cost is 57437050.7 (574.37 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 4001248 for +152 days
LD Analysis for Milestone2: calculated LD is Rs 6607324 for 251 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Other Allied Works & Finishing Work | 1.00 Job | 3.17 | 26-05-2016 | 12-03-2018 | 1.00 Job | 1.00 Job | 0.58 | 3.17 | 2. | Foundation RHS | 1.00 Job | 5.65 | 01-07-2016 | 05-01-2017 | 1.00 Job | 1.00 Job | 1.02 | 5.65 | 3. | Foundation LHS | 1.00 Job | 8.41 | 26-06-2016 | 25-12-2016 | 1.00 Job | 1.00 Job | 1.52 | 8.41 | 4. | Abutment Superstructure RHS | 1.00 Job | 120.53 | 30-05-2017 | 20-01-2018 | 1.00 Job | 1.00 Job | 21.84 | 120.53 | 5. | Abutment Superstructure LHS | 1.00 Job | 131.94 | 30-12-2016 | 20-01-2018 | 1.00 Job | 1.00 Job | 23.91 | 131.94 | 6. | Trestle Erection and Bracing of Trestle Tower LHS | 2.00 job | 53.22 | 01-02-2018 | 20-02-2018 | 2.00 job | 2.00 job | 9.64 | 53.22 | 7. | Anchor Block Main Cable Reinforcement (3-4 Times) | 2.00 job | 40.92 | 20-02-2017 | 20-01-2018 | 2.00 job | 2.00 job | 7.42 | 40.92 | 8. | Anchor Block for Wind Cable: Reinforcement, Lewis | 4.00 job | 5.79 | 15-01-2018 | 30-01-2018 | 4.00 job | 4.00 job | 1.05 | 5.79 | 9. | Deck Cable laying, stretching and Fixing Transoms/Deck Slab | 2.00 no | 3.28 | 05-02-2018 | 28-02-2018 | 2.00 no | 2.00 no | 0.59 | 3.28 | 10. | Fixing of Saddle pulley along with Rib plate and | 4.00 no | 5.40 | 20-02-2018 | 05-03-2018 | 4.00 no | 4.00 no | 0.98 | 5.40 | 11. | Main Cable Laying and Stretching | 8.00 no | 19.31 | 01-03-2018 | 10-03-2018 | 8.00 no | 8.00 no | 3.5 | 19.31 | 12. | Fixing Suspenders to Main cable with clamps and Ha | 172.00 no | 2.06 | 25-02-2018 | 10-03-2018 | 172.00 no | 172.00 no | 0.37 | 2.06 | 13. | Stretching Wind Guy cable, Fixing wind Ties with | 256.95 m | 4.52 | 15-01-2018 | 28-02-2018 | 256.95 m | 256.95 m | 0.82 | 4.52 | 14. | Fixing longitudinal Stringers/girders | 90.00 m | 11.29 | 10-02-2018 | 28-02-2018 | 90.00 m | 90.00 m | 2.05 | 11.29 | 15. | Fixing of chequered Plate/RCC Deck | 228.71 sqm | 12.26 | 20-02-2018 | 10-03-2018 | 228.71 sqm | 228.71 sqm | 2.22 | 12.26 | 16. | Steel Railing/crush barrier | 189.00 m | 0.28 | 15-02-2018 | 12-03-2018 | 189.00 m | 189.00 m | 0.05 | 0.28 | 17. | Approach Ramp /path | 2400.00 m | 123.87 | 20-05-2017 | 12-03-2018 | 2400.00 m | 2400.00 m | 22.45 | 123.87 | 18. | Protection Work | 0.00 Job | 0.00 | 15-10-2017 | 30-12-2017 | 0.00 Job | 0.00 Job | 0 | 0.00 |
Total Amount: |
551.9 |
|
100 |
551.9 |
|
Remarks:
No Remarks
Work Program Made On:
16-11-2016 } ?>
Updation of work program on:
16-01-2018
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 31-January-2017 | 17.91 lakh | 2. | 28-February-2017 | 32.93 lakh | 3. | 30-March-2017 | 30.82 lakh | 4. | 30-April-2017 | 18.60 lakh | 5. | 31-May-2017 | 18.92 lakh | 6. | 30-June-2017 | 14.14 lakh | 7. | 31-July-2017 | 34.57 lakh | 8. | 13-September-2017 | 14.73 lakh | 9. | 25-September-2017 | 12.51 lakh | 10. | 13-October-2017 | 11.09 lakh | 11. | 25-November-2017 | 40.03 lakh | 12. | 30-December-2017 | 80.14 lakh | 13. | 31-January-2018 | 23.55 lakh | 14. | 26-February-2018 | 87.14 lakh | 15. | 22-March-2018 | 30.34 lakh | 16. | 25-April-2018 | 22.88 lakh | 17. | 30-May-2018 | 41.51 lakh | 18. | 07-August-2018 | 14.81 lakh | 19. | 25-October-2018 | 15.70 lakh | 20. | 31-October-2018 | 11.99 lakh | 21. | 01-November-2018 | 9.00 lakh | 22. | 31-December-2018 | 12.67 lakh | 23. | 25-June-2019 | 6.02 lakh |
Total |
602 lakh |
% Payment |
104.81 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 1065 No. of Test Done : 1066 No. of Test Passed : 1066 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 93.76 |
Number of Notice(s) issued: 62 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 50 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 22-04-2018 | Nisni suspension bridge over the saryu river in pithoragadh district. | Current status of the A2side foundation of Nisni suspension bridge over the saryu river in pithoragadh district. | Dhananjay Kumar Singh | RE | BSC R&B WB Pithoragarh | See Pic |
2. | 22-04-2018 | Nisni suspension bridge over the saryu river in pithoragadh district. | Current status of the Nisni suspension bridge A1side foundation in the district, pithoragadh. | Dhananjay Kumar Singh | RE | BSC R&B WB Pithoragarh | See Pic |
3. | 14-03-2018 | Abutment A1 | Fixing n grouting of tower bolts | Sanjeev Kumar | JE | UDRP R&B Champawat | See Pic |
4. | 14-03-2018 | Abutment A2 | View of Abutment A2 from abutment A1 | Sanjeev Kumar | JE | UDRP R&B Champawat | See Pic |
5. | 27-02-2018 | Haldwani workshop | Inspection of ground erection of bridge | Sanjeev Kumar | JE | UDRP R&B Champawat | See Pic |
6. | 27-02-2018 | Haldwani workshop | Inspection and ground erection | Sanjeev Kumar | JE | UDRP R&B Champawat | See Pic |
7. | 23-02-2018 | Fabricatoion yard of M/s KMEC at fabrication yard haldwani. | Inspection of ground erection of the 90 Mtr suspension bridge over the saryu river in pithoragadh district. | Dhananjay Kumar Singh | RE | BSC R&B WB Pithoragarh | See Pic |
8. | 23-02-2018 | Fabricatoion yard of M/s KMEC at fabrication yard haldwani. | Inspection of ground erection of the 90 Mtr suspension bridge over the saryu river in pithoragadh district. | Dhananjay Kumar Singh | RE | BSC R&B WB Pithoragarh | See Pic |
9. | 13-02-2018 | Fabrication yard of M/s K. M Engineering at Haldwani for the 90Mtr suspension bridge over the saryu river at Nisni district. Pithoragadh. | Inspection of the ground erection work in progress at fabrication yard haldwani of
M/s KM Engineering for the 90 Mtr suspension bridge over the saryu river in pithoragadh district. | Dhananjay Kumar Singh | RE | BSC R&B WB Pithoragarh | See Pic |
10. | 04-02-2018 | 0+890 | Cement concrete pavement for approach road | Sanjeev Kumar | JE | UDRP R&B Champawat | See Pic |
11. | 04-02-2018 | 0+680 | Cement concrete pavement approach road | Sanjeev Kumar | JE | UDRP R&B Champawat | See Pic |
12. | 04-02-2018 | Abutment A1 side | Site visit by TL Sir EE Sir RE sir AE sir | Sanjeev Kumar | JE | UDRP R&B Champawat | See Pic |
13. | 04-02-2018 | Abutment A1 | Site visit by TL,EE,RE,AE sir | Sanjeev Kumar | JE | UDRP R&B Champawat | See Pic |
14. | 04-02-2018 | 0+565 | Construction of RR dry retaining wall and laying of kharanja in bridle approach road | Sanjeev Kumar | JE | UDRP R&B Champawat | See Pic |
15. | 05-11-2017 | 90 Mtr. Nisni suspension bridge over the saryu river in pithoragadh district. | Inspection of cement during the construction works. | Dhananjay Kumar Singh | RE | BSC R&B WB Pithoragarh | See Pic |
16. | 02-11-2017 | Field PIU champawat. | MoM at champawat with CME HO, UDRP,Dehradun. | Dhananjay Kumar Singh | RE | BSC R&B WB Pithoragarh | See Pic |
17. | 20-09-2017 | Nisni bridge. | Inspection of the Nisni bridge for identification of required protection work by team leader, excutive engineer and team . | Dhananjay Kumar Singh | RE | BSC R&B WB Pithoragarh | See Pic |
18. | 14-09-2017 | Office of the superitending engineer, WB, Pithoragadh. | Progress review meeting in the office of the superitending engineer. Pithoragadh. | Dhananjay Kumar Singh | RE | BSC R&B WB Pithoragarh | See Pic |
19. | 03-08-2017 | Monthly management meeting at FPIU Champawat. | Monthly management meeting in the office of Executive Engineer champawat for progress review and it's recovery. | Dhananjay Kumar Singh | RE | BSC R&B WB Pithoragarh | See Pic |
20. | 21-07-2017 | KMVN Pithoragadh. | Workshop to share the findings on 3rd enveronmantal and social audits during Dec-16 to March-17 on dated 20/07 at Pithoragadh. | Dhananjay Kumar Singh | RE | BSC R&B WB Pithoragarh | See Pic |
|
|