Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Box culvert near village Tingri on Pathari river in Vidhan Sabha Lakshar Work Completed
Project: UDRP-RB UID: 4019 Sanction Cost: 256.06  lakh Span: 50.000 M
District: Haridwar Block: Laksar Constituency: Haridwar Circle:
DEA: DEA Tehri DSC: Yongma Engineering Co. Ltd. DSC Scope: Only Supervision Type: Bridge
Procurement:
Package No.: 517        Package Name:  UDRP/PWD/13/55/BR/17        Tender Date: 27-06-2015        Current Status: Agreement signed        Achieved on Date: 02-02-2016

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/13/55/BR/17      Contractor Name: Shiv Shankar Construction Company
Start Date:  09-02-2016      Intended Completion Date:  10-12-2017      Original End Date:  08-10-2016
Total Bond Cost: 66766672.78 (667.67 lakh)        Variation Cost: 2955142.85 (29.55 lakh)    Hence Total Bond Cost is   69721815.63 (697.22 lakh) 
Sub Project Cost: 256.06  lakh       
LD Analysis for Milestone1: calculated LD is Rs 2670640 for +80 days        LD Analysis for Milestone2: calculated LD is Rs 8045303 for 241 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Crash Barrier184.00 m7.3422-05-201705-06-201760.50 m60.50 m3.187.34
2.Other Allied Works & Finishing Work 1.00 Job12.4701-12-201630-06-20171.00 Job1.00 Job5.412.47
3.Foundation RHS1.00 Job31.0120-11-201620-04-20171.00 Job1.00 Job13.4331.01
4.Foundation LHS1.00 Job31.0120-11-201615-05-20171.00 Job1.00 Job13.4331.01
5.Abutment Superstructure RHS1.00 Job33.0415-02-201715-05-20171.00 Job1.00 Job14.3133.04
6.Abutment Superstructure LHS1.00 Job33.0415-02-201731-05-20171.00 Job1.00 Job14.3133.04
7.Fixing of chequered Plate/RCC Deck257.13 sqm28.0801-03-201720-05-2017257.13 sqm257.13 sqm12.1628.08
8.Approach Ramp /path 184.00 m35.6021-05-201730-06-2017188.00 m188.00 m15.4135.60
9.Protection Work1.00 Job19.3616-03-201730-06-20171.00 Job1.00 Job8.3819.36
Total Amount: 230.95 100   230.95
Remarks: No Remarks       Work Program Made On: 23-06-2016        Updation of work program on: 22-11-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.25-March-201756.05  lakh
2.20-May-201736.27  lakh
3.17-June-201758.31  lakh
4.31-July-201727.64  lakh
5.27-February-20183.39  lakh
6.30-May-201817.83  lakh
Total 199.49  lakh
% Payment77.91 %
Advance Amount:  65.00  lakh        Recovered Amount:  65.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 1834   No. of Test Done : 1845    No. of Test Passed : 1839   No. of Test Failed : 6   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 88.80
Number of Notice(s) issued: 2

Mobile Pic Upload

Number of Pics Available on Web Repository: 28
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.06-04-2022Tingri bridge LaksarWorld Bank TeamSudhir Kumar ` ` See Pic
2.17-05-20180.00Pkg BR 017 Tigri box culvert work completedSudhir Kumar AEAEUDRP R&B Tehri See Pic
3.17-05-20180.00Pkg BR 017Sudhir Kumar AEAEUDRP R&B Tehri See Pic
4.17-05-20180.00PKG BR 017 Tigri box culvert work completedSudhir Kumar AEAEUDRP R&B Tehri See Pic
5.17-04-20180.00Site inspection by CE Sir, SE Sir n EE Mam WB PWD TehriSudhir Kumar AEAEUDRP R&B Tehri See Pic
6.17-04-20180.00Joint inspection with Civil divSudhir Kumar AEAEUDRP R&B Tehri See Pic
7.14-12-20170.00Cutting of extra steelSudhir Kumar AEAEUDRP R&B Tehri See Pic
8.22-11-2017Bridge approchSite inspection by SE sir, EE, TL, AEJagat Chand RamolaJEUDRP R&B Tehri See Pic
9.22-11-20170.00Site inspection by SE Sir TehriSudhir Kumar AEAEUDRP R&B Tehri See Pic
10.06-06-2017At Tigri Box culvertSite visited by CE, DPM with WB Div. PWD Chakrata and BSC-1.Dhwajvir SinghJEUDRP R&B Karnprayag See Pic
11.30-05-2017At Tigri Bridge SiteSite visit by world bank TeamDhwajvir SinghJEUDRP R&B Karnprayag See Pic
12.30-05-2017At Tigri Bridge siteVisit of world bank team at Tigri Bridge siteDhwajvir SinghJEUDRP R&B Karnprayag See Pic
13.23-05-2017Main part of bridgeRCC casting of deck slabLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
14.15-05-2017Main bridgeShuttering under progress for crush barrier.Lalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
15.27-04-2017Tigri Bridge uid 4019Inspection of deck slab by Chief Engineer With WB PWD chakrata and DSC Staff.Dhwajvir SinghJEUDRP R&B Karnprayag See Pic
16.27-04-2017Tigri Bridge uid 4019Checking of shuttering of deck slab by CE with world bank and DSC staffDhwajvir SinghJEUDRP R&B Karnprayag See Pic
17.27-04-2017Tigri Bridge UID 4019Checking of reinforcement of deck slab found okDhwajvir SinghJEUDRP R&B Karnprayag See Pic
18.25-04-2017At RMC plant in Ibrahimpur,HaridwarSlump checked at RMC plant.Found 120mmAshish KaluraAEUDRP R&B Chakrata See Pic
19.14-04-2017Main bridgeInspection by wb team.Lalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
20.14-04-2017Main part of the bridgeInspection by WB team.Lalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic