Box culvert near village Tingri on Pathari river in Vidhan Sabha Lakshar
Work Completed
|
Project: |
UDRP-RB |
UID: |
4019 |
Sanction Cost: |
256.06 lakh |
Span:
|
50.000 M |
District: |
Haridwar |
Block: |
Laksar |
Constituency: |
Haridwar |
Circle: |
|
DEA: |
DEA Tehri |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Only Supervision |
Type: |
Bridge |
|
Procurement: |
Package No.: 517
Package Name: 
UDRP/PWD/13/55/BR/17
Tender Date: 27-06-2015
Current Status: Agreement signed
Achieved on Date: 02-02-2016 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/13/55/BR/17
Contractor Name: Shiv Shankar Construction Company
|
Start Date: 09-02-2016
Intended Completion Date: 10-12-2017
Original End Date: 08-10-2016 |
Total Bond Cost: 66766672.78 (667.67 lakh)
Variation Cost: 2955142.85 (29.55 lakh) Hence Total Bond Cost is 69721815.63 (697.22 lakh)
|
Sub Project Cost: 256.06 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 2670640 for +80 days
LD Analysis for Milestone2: calculated LD is Rs 8045303 for 241 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Crash Barrier | 184.00 m | 7.34 | 22-05-2017 | 05-06-2017 | 60.50 m | 60.50 m | 3.18 | 7.34 | 2. | Other Allied Works & Finishing Work | 1.00 Job | 12.47 | 01-12-2016 | 30-06-2017 | 1.00 Job | 1.00 Job | 5.4 | 12.47 | 3. | Foundation RHS | 1.00 Job | 31.01 | 20-11-2016 | 20-04-2017 | 1.00 Job | 1.00 Job | 13.43 | 31.01 | 4. | Foundation LHS | 1.00 Job | 31.01 | 20-11-2016 | 15-05-2017 | 1.00 Job | 1.00 Job | 13.43 | 31.01 | 5. | Abutment Superstructure RHS | 1.00 Job | 33.04 | 15-02-2017 | 15-05-2017 | 1.00 Job | 1.00 Job | 14.31 | 33.04 | 6. | Abutment Superstructure LHS | 1.00 Job | 33.04 | 15-02-2017 | 31-05-2017 | 1.00 Job | 1.00 Job | 14.31 | 33.04 | 7. | Fixing of chequered Plate/RCC Deck | 257.13 sqm | 28.08 | 01-03-2017 | 20-05-2017 | 257.13 sqm | 257.13 sqm | 12.16 | 28.08 | 8. | Approach Ramp /path | 184.00 m | 35.60 | 21-05-2017 | 30-06-2017 | 188.00 m | 188.00 m | 15.41 | 35.60 | 9. | Protection Work | 1.00 Job | 19.36 | 16-03-2017 | 30-06-2017 | 1.00 Job | 1.00 Job | 8.38 | 19.36 |
Total Amount: |
230.95 |
|
100 |
230.95 |
|
Remarks:
No Remarks
Work Program Made On:
23-06-2016 } ?>
Updation of work program on:
22-11-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 25-March-2017 | 56.05 lakh | 2. | 20-May-2017 | 36.27 lakh | 3. | 17-June-2017 | 58.31 lakh | 4. | 31-July-2017 | 27.64 lakh | 5. | 27-February-2018 | 3.39 lakh | 6. | 30-May-2018 | 17.83 lakh |
Total |
199.49 lakh |
% Payment | 77.91 % |
|
Advance Amount: 65.00 lakh
Recovered Amount: 65.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Bill sh
ould be issued | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 1834 No. of Test Done : 1845 No. of Test Passed : 1839 No. of Test Failed : 6 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 88.80 |
Number of Notice(s) issued: 2 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 28 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 06-04-2022 | Tingri bridge Laksar | World Bank Team | Sudhir Kumar | ` | ` | See Pic |
2. | 17-05-2018 | 0.00 | Pkg BR 017 Tigri box culvert work completed | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
3. | 17-05-2018 | 0.00 | Pkg BR 017 | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
4. | 17-05-2018 | 0.00 | PKG BR 017 Tigri box culvert work completed | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
5. | 17-04-2018 | 0.00 | Site inspection by CE Sir, SE Sir n EE Mam WB PWD Tehri | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
6. | 17-04-2018 | 0.00 | Joint inspection with Civil div | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
7. | 14-12-2017 | 0.00 | Cutting of extra steel | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
8. | 22-11-2017 | Bridge approch | Site inspection by SE sir, EE, TL, AE | Jagat Chand Ramola | JE | UDRP R&B Tehri | See Pic |
9. | 22-11-2017 | 0.00 | Site inspection by SE Sir Tehri | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
10. | 06-06-2017 | At Tigri Box culvert | Site visited by CE, DPM with WB Div. PWD Chakrata and BSC-1. | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
11. | 30-05-2017 | At Tigri Bridge Site | Site visit by world bank Team | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
12. | 30-05-2017 | At Tigri Bridge site | Visit of world bank team at Tigri Bridge site | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
13. | 23-05-2017 | Main part of bridge | RCC casting of deck slab | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
14. | 15-05-2017 | Main bridge | Shuttering under progress for crush barrier. | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
15. | 27-04-2017 | Tigri Bridge uid 4019 | Inspection of deck slab by Chief Engineer With WB PWD chakrata and DSC Staff. | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
16. | 27-04-2017 | Tigri Bridge uid 4019 | Checking of shuttering of deck slab by CE with world bank and DSC staff | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
17. | 27-04-2017 | Tigri Bridge UID 4019 | Checking of reinforcement of deck slab found ok | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
18. | 25-04-2017 | At RMC plant in Ibrahimpur,Haridwar | Slump checked at RMC plant.Found 120mm | Ashish Kalura | AE | UDRP R&B Chakrata | See Pic |
19. | 14-04-2017 | Main bridge | Inspection by wb team. | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
20. | 14-04-2017 | Main part of the bridge | Inspection by WB team. | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
|
|