Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

2 Box culvert near village Sindhadu to connect Anthal Bujurg village on Pathri river Work Completed
Project: UDRP-RB UID: 4018 Sanction Cost: 352.60  lakh Span: 46.000 M
District: Haridwar Block: Laksar Constituency: Haridwar Circle:
DEA: DEA Tehri DSC: Yongma Engineering Co. Ltd. DSC Scope: Only Supervision Type: Bridge
Procurement:
Package No.: 517        Package Name:  UDRP/PWD/13/55/BR/17        Tender Date: 27-06-2015        Current Status: Agreement signed        Achieved on Date: 02-02-2016

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/13/55/BR/17      Contractor Name: Shiv Shankar Construction Company
Start Date:  09-02-2016      Intended Completion Date:  10-12-2017      Original End Date:  08-10-2016
Total Bond Cost: 66766672.78 (667.67 lakh)        Variation Cost: 2955142.85 (29.55 lakh)    Hence Total Bond Cost is   69721815.63 (697.22 lakh) 
Sub Project Cost: 352.60  lakh       
LD Analysis for Milestone1: calculated LD is Rs 2670640 for +80 days        LD Analysis for Milestone2: calculated LD is Rs 8045303 for 241 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Other Allied Works & Finishing Work 2.00 Job6.6001-04-201615-02-20172.00 Job2.00 Job2.816.60
2.Foundation RHS2.00 Job29.7628-03-201615-12-20162.00 Job2.00 Job12.6729.76
3.Foundation LHS2.00 Job29.7617-05-201615-12-20162.00 Job2.00 Job12.6729.76
4.Abutment Superstructure RHS2.00 Job27.9330-05-201624-12-20162.00 Job2.00 Job11.8927.93
5.Abutment Superstructure LHS2.00 Job27.9330-06-201624-12-20162.00 Job2.00 Job11.8927.93
6.Fixing of chequered Plate/RCC Deck376.55 sqm31.0325-12-201609-01-2017376.55 sqm376.55 sqm13.2131.03
7.Approach Ramp /path 285.00 m40.2710-01-201730-05-2017283.00 m283.00 m17.1440.27
8.Protection Work2.00 Job41.6610-01-201715-02-20172.00 Job2.00 Job17.7341.66
Total Amount: 234.94 100   234.94
Remarks: No Remarks       Work Program Made On: 23-06-2016        Updation of work program on: 22-11-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.23-July-201640.68  lakh
2.27-September-201610.55  lakh
3.20-December-201681.70  lakh
4.31-January-201725.82  lakh
5.28-February-201783.98  lakh
6.25-March-201715.63  lakh
7.20-May-20177.48  lakh
8.17-June-20179.88  lakh
9.27-February-20180.54  lakh
10.30-May-201815.69  lakh
11.30-November-20180.38  lakh
Total 292.33  lakh
% Payment82.91 %
Advance Amount:  65.00  lakh        Recovered Amount:  65.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 1834   No. of Test Done : 1845    No. of Test Passed : 1839   No. of Test Failed : 6   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 87.78
Number of Notice(s) issued: 1

Mobile Pic Upload

Number of Pics Available on Web Repository: 84
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.06-04-2022Sindharu LaksarWorld Bank TeamSudhir Kumar ` ` See Pic
2.06-04-2022Sindhadu LaksarWorld Bank Team visitSudhir Kumar ` ` See Pic
3.06-04-2022Sidhadu bridge LaksarWorld Bank Team visitSudhir Kumar ` ` See Pic
4.17-05-20180.00Pkg BR 017 Sindhadu Box culvert No 2 work completedSudhir Kumar AEAEUDRP R&B Tehri See Pic
5.17-05-20180.0Pkg BR 017 Sindhdu box culvert No 2 work completedSudhir Kumar AEAEUDRP R&B Tehri See Pic
6.17-05-20180.00Pkg BR 017 Sidhadu box culvert No 2 work completedSudhir Kumar AEAEUDRP R&B Tehri See Pic
7.17-04-20180.000Joint inspection pkg BR 017 with Civil div LaksarSudhir Kumar AEAEUDRP R&B Tehri See Pic
8.21-03-20180.00Site inspection by CE Sir, SE Sir n EE Mam WB PWD TehriSudhir Kumar AEAEUDRP R&B Tehri See Pic
9.21-03-20180.00Site inspection by CE Sir, SE Sir n EE Mam WB PWD TehriSudhir Kumar AEAEUDRP R&B Tehri See Pic
10.22-11-2017At bridgeBridge inspection by SE sir, EE, TL, AEJagat Chand RamolaJEUDRP R&B Tehri See Pic
11.22-11-2017Bridge approchSite visit by SE, EE, TL, AEJagat Chand RamolaJEUDRP R&B Tehri See Pic
12.22-11-2017At bridgedisscussion with Villegers by SE sirJagat Chand RamolaJEUDRP R&B Tehri See Pic
13.22-11-2017At bridgeSite inspection by SE sir, EE mam, TL, AEJagat Chand RamolaJEUDRP R&B Tehri See Pic
14.22-11-20170.00Site inspection by SE SirSudhir Kumar AEAEUDRP R&B Tehri See Pic
15.30-05-2017At Sindhadu bridge (3 box cell)Visit by world bank TeamDhwajvir SinghJEUDRP R&B Karnprayag See Pic
16.30-05-2017At Sindhadu Bridge site (5 box cell)Site visit by world bank TeamDhwajvir SinghJEUDRP R&B Karnprayag See Pic
17.15-05-2017Main bridge aFinished shape of bridgeLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
18.15-05-2017Main bridgeFinished surface of deck slab and crush barrier.Lalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
19.27-04-2017Eithal bridge uid 4018aInspection of bridge by Chief Engineer With WB PWD Chakrata and DSC Staff.Dhwajvir SinghJEUDRP R&B Karnprayag See Pic
20.27-04-2017Aithal bridge of length 27.50mInspection of bridge by C.Er. with WB PWD Chakrata and DSC Staff.Dhwajvir SinghJEUDRP R&B Karnprayag See Pic