2 Box culvert near village Sindhadu to connect Anthal Bujurg village on Pathri river
Work Completed
|
Project: |
UDRP-RB |
UID: |
4018 |
Sanction Cost: |
352.60 lakh |
Span:
|
46.000 M |
District: |
Haridwar |
Block: |
Laksar |
Constituency: |
Haridwar |
Circle: |
|
DEA: |
DEA Tehri |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Only Supervision |
Type: |
Bridge |
|
Procurement: |
Package No.: 517
Package Name: 
UDRP/PWD/13/55/BR/17
Tender Date: 27-06-2015
Current Status: Agreement signed
Achieved on Date: 02-02-2016 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/13/55/BR/17
Contractor Name: Shiv Shankar Construction Company
|
Start Date: 09-02-2016
Intended Completion Date: 10-12-2017
Original End Date: 08-10-2016 |
Total Bond Cost: 66766672.78 (667.67 lakh)
Variation Cost: 2955142.85 (29.55 lakh) Hence Total Bond Cost is 69721815.63 (697.22 lakh)
|
Sub Project Cost: 352.60 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 2670640 for +80 days
LD Analysis for Milestone2: calculated LD is Rs 8045303 for 241 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Other Allied Works & Finishing Work | 2.00 Job | 6.60 | 01-04-2016 | 15-02-2017 | 2.00 Job | 2.00 Job | 2.81 | 6.60 | 2. | Foundation RHS | 2.00 Job | 29.76 | 28-03-2016 | 15-12-2016 | 2.00 Job | 2.00 Job | 12.67 | 29.76 | 3. | Foundation LHS | 2.00 Job | 29.76 | 17-05-2016 | 15-12-2016 | 2.00 Job | 2.00 Job | 12.67 | 29.76 | 4. | Abutment Superstructure RHS | 2.00 Job | 27.93 | 30-05-2016 | 24-12-2016 | 2.00 Job | 2.00 Job | 11.89 | 27.93 | 5. | Abutment Superstructure LHS | 2.00 Job | 27.93 | 30-06-2016 | 24-12-2016 | 2.00 Job | 2.00 Job | 11.89 | 27.93 | 6. | Fixing of chequered Plate/RCC Deck | 376.55 sqm | 31.03 | 25-12-2016 | 09-01-2017 | 376.55 sqm | 376.55 sqm | 13.21 | 31.03 | 7. | Approach Ramp /path | 285.00 m | 40.27 | 10-01-2017 | 30-05-2017 | 283.00 m | 283.00 m | 17.14 | 40.27 | 8. | Protection Work | 2.00 Job | 41.66 | 10-01-2017 | 15-02-2017 | 2.00 Job | 2.00 Job | 17.73 | 41.66 |
Total Amount: |
234.94 |
|
100 |
234.94 |
|
Remarks:
No Remarks
Work Program Made On:
23-06-2016 } ?>
Updation of work program on:
22-11-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 23-July-2016 | 40.68 lakh | 2. | 27-September-2016 | 10.55 lakh | 3. | 20-December-2016 | 81.70 lakh | 4. | 31-January-2017 | 25.82 lakh | 5. | 28-February-2017 | 83.98 lakh | 6. | 25-March-2017 | 15.63 lakh | 7. | 20-May-2017 | 7.48 lakh | 8. | 17-June-2017 | 9.88 lakh | 9. | 27-February-2018 | 0.54 lakh | 10. | 30-May-2018 | 15.69 lakh | 11. | 30-November-2018 | 0.38 lakh |
Total |
292.33 lakh |
% Payment | 82.91 % |
|
Advance Amount: 65.00 lakh
Recovered Amount: 65.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Bill sh
ould be issued | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 1834 No. of Test Done : 1845 No. of Test Passed : 1839 No. of Test Failed : 6 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 87.78 |
Number of Notice(s) issued: 1 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 84 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 06-04-2022 | Sindharu Laksar | World Bank Team | Sudhir Kumar | ` | ` | See Pic |
2. | 06-04-2022 | Sindhadu Laksar | World Bank Team visit | Sudhir Kumar | ` | ` | See Pic |
3. | 06-04-2022 | Sidhadu bridge Laksar | World Bank Team visit | Sudhir Kumar | ` | ` | See Pic |
4. | 17-05-2018 | 0.00 | Pkg BR 017 Sindhadu Box culvert No 2 work completed | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
5. | 17-05-2018 | 0.0 | Pkg BR 017 Sindhdu box culvert No 2 work completed | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
6. | 17-05-2018 | 0.00 | Pkg BR 017 Sidhadu box culvert No 2 work completed | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
7. | 17-04-2018 | 0.000 | Joint inspection pkg BR 017 with Civil div Laksar | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
8. | 21-03-2018 | 0.00 | Site inspection by CE Sir, SE Sir n EE Mam WB PWD Tehri | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
9. | 21-03-2018 | 0.00 | Site inspection by CE Sir, SE Sir n EE Mam WB PWD Tehri | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
10. | 22-11-2017 | At bridge | Bridge inspection by SE sir, EE, TL, AE | Jagat Chand Ramola | JE | UDRP R&B Tehri | See Pic |
11. | 22-11-2017 | Bridge approch | Site visit by SE, EE, TL, AE | Jagat Chand Ramola | JE | UDRP R&B Tehri | See Pic |
12. | 22-11-2017 | At bridge | disscussion with Villegers by SE sir | Jagat Chand Ramola | JE | UDRP R&B Tehri | See Pic |
13. | 22-11-2017 | At bridge | Site inspection by SE sir, EE mam, TL, AE | Jagat Chand Ramola | JE | UDRP R&B Tehri | See Pic |
14. | 22-11-2017 | 0.00 | Site inspection by SE Sir | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
15. | 30-05-2017 | At Sindhadu bridge (3 box cell) | Visit by world bank Team | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
16. | 30-05-2017 | At Sindhadu Bridge site (5 box cell) | Site visit by world bank Team | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
17. | 15-05-2017 | Main bridge a | Finished shape of bridge | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
18. | 15-05-2017 | Main bridge | Finished surface of deck slab and crush barrier. | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
19. | 27-04-2017 | Eithal bridge uid 4018a | Inspection of bridge by Chief Engineer With WB PWD Chakrata and DSC Staff. | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
20. | 27-04-2017 | Aithal bridge of length 27.50m | Inspection of bridge by C.Er. with WB PWD Chakrata and DSC Staff. | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
|
|