Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Box culvert near bichpali in akuda khurd connecting akudha khurd to Ismailpur on Pathari river Work Completed
Project: UDRP-RB UID: 4017 Sanction Cost: 224.94  lakh Span: 30.000 M
District: Haridwar Block: Laksar Constituency: Haridwar Circle:
DEA: DEA Tehri DSC: Yongma Engineering Co. Ltd. DSC Scope: Only Supervision Type: Bridge
Procurement:
Package No.: 517        Package Name:  UDRP/PWD/13/55/BR/17        Tender Date: 27-06-2015        Current Status: Agreement signed        Achieved on Date: 02-02-2016

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/13/55/BR/17      Contractor Name: Shiv Shankar Construction Company
Start Date:  09-02-2016      Intended Completion Date:  10-12-2017      Original End Date:  08-10-2016
Total Bond Cost: 66766672.78 (667.67 lakh)        Variation Cost: 2955142.85 (29.55 lakh)    Hence Total Bond Cost is   69721815.63 (697.22 lakh) 
Sub Project Cost: 224.94  lakh       
LD Analysis for Milestone1: calculated LD is Rs 2670640 for +80 days        LD Analysis for Milestone2: calculated LD is Rs 8045303 for 241 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Crash Barrier40.00 m11.7917-05-201731-05-201748.30 m48.30 m7.0311.79
2.Other Allied Works & Finishing Work 1.00 Job5.0420-11-201630-06-20171.00 Job1.00 Job3.015.04
3.Foundation RHS1.00 Job17.1320-11-201620-04-20171.00 Job1.00 Job10.2217.13
4.Foundation LHS1.00 Job17.1320-11-201615-05-20171.00 Job1.00 Job10.2217.13
5.Abutment Superstructure RHS1.00 Job20.9515-02-201715-05-20171.00 Job1.00 Job12.520.95
6.Abutment Superstructure LHS1.00 Job20.9515-02-201731-05-20171.00 Job1.00 Job12.520.95
7.Fixing of chequered Plate/RCC Deck205.28 sqm21.0101-03-201715-05-2017205.28 sqm205.28 sqm12.5421.01
8.Approach Ramp /path 40.00 m11.7906-10-201720-11-2017140.00 m140.00 m7.0311.79
9.Protection Work1.00 Job41.8216-03-201730-06-20171.00 Job1.00 Job24.9541.82
Total Amount: 167.61 100   167.61
Remarks: No Remarks       Work Program Made On: 23-06-2016        Updation of work program on: 22-11-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.28-February-201732.06  lakh
2.25-March-201712.95  lakh
3.20-May-201711.60  lakh
4.13-June-20170.01  lakh
5.17-June-201735.26  lakh
6.31-July-201712.93  lakh
7.27-February-201822.60  lakh
8.30-May-201812.15  lakh
Total 139.56  lakh
% Payment62.04 %
Advance Amount:  65.00  lakh        Recovered Amount:  65.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 1834   No. of Test Done : 1845    No. of Test Passed : 1839   No. of Test Failed : 6   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 89.02
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 62
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.17-05-20180.00BR017 Akoda Box Culvert work completedSudhir Kumar AEAEUDRP R&B Tehri See Pic
2.11-05-20180.00Joint inspection with AE PWD laksar n AE WB TehriSudhir Kumar AEAEUDRP R&B Tehri See Pic
3.11-05-20180.00BR 017 Akoda brg Work completedSudhir Kumar AEAEUDRP R&B Tehri See Pic
4.11-05-20180.00BR 017 Akoda Box culvert work completedSudhir Kumar AEAEUDRP R&B Tehri See Pic
5.11-05-20180.00Akoda brg CompleteSudhir Kumar AEAEUDRP R&B Tehri See Pic
6.10-01-20180.000Site inspection by SE Sir n EE Mam WB PWD TehriSudhir Kumar AEAEUDRP R&B Tehri See Pic
7.14-12-20170.00Approach road completedSudhir Kumar AEAEUDRP R&B Tehri See Pic
8.14-12-20170.00Spreading n Rolling of GSBSudhir Kumar AEAEUDRP R&B Tehri See Pic
9.06-12-2017Approch roadrolling work on ogpc surfaceJagat Chand RamolaJEUDRP R&B Tehri See Pic
10.06-12-2017Approch roadLaying ogpcJagat Chand RamolaJEUDRP R&B Tehri See Pic
11.06-12-2017Approch roadSpreading prime coat on g 3 surfaceJagat Chand RamolaJEUDRP R&B Tehri See Pic
12.06-12-2017Approch roadBrooming on g3 surfaceJagat Chand RamolaJEUDRP R&B Tehri See Pic
13.06-12-2017Approch roadRolling on G3 surfaceJagat Chand RamolaJEUDRP R&B Tehri See Pic
14.05-12-2017Approach roadSachin KumarQSBSC R&B WB Haridwar See Pic
15.05-12-2017Approach roadSachin KumarQSBSC R&B WB Haridwar See Pic
16.01-12-2017Approch roadLaying and rolling of g3Jagat Chand RamolaJEUDRP R&B Tehri See Pic
17.01-12-2017Approch roadDry Rollling on g3Jagat Chand RamolaJEUDRP R&B Tehri See Pic
18.30-11-2017G 2 work on approach roadSachin KumarQSBSC R&B WB Haridwar See Pic
19.28-11-20170.00Preparation of sub base for approach roadSudhir Kumar AEAEUDRP R&B Tehri See Pic
20.28-11-20170.00Preparation of sub base for Approach roadSudhir Kumar AEAEUDRP R&B Tehri See Pic