Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Bridle Bridge over Power river at Block Mori Village Pandradhu to Duriyara Work Completed
Project: UDRP-RB UID: 4016 Sanction Cost: 351.89  lakh Span: 60.000 M
District: Uttarkashi Block: Mori Constituency: Purola Circle:
DEA: DEA Uttarkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: undefined Type: Bridge
Procurement:
Package No.: 516        Package Name:  UDRP/PWD/01/33/BR/016        Tender Date: 03-08-2015        Current Status: Agreement signed        Achieved on Date: 08-03-2016

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/01/33/BR/016      Contractor Name: Tons Builderes
Start Date:  15-03-2016      Intended Completion Date:  31-01-2018      Original End Date:  14-07-2017
Total Bond Cost: 24072575.5 (240.73 lakh)        Variation Cost: 9067532.49 (90.68 lakh)    Hence Total Bond Cost is   33140107.99 (331.4 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 1107312 for +92 days        LD Analysis for Milestone2: calculated LD is Rs 1504500 for 125 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Other Allied Works & Finishing Work 1.00 Job9.2807-09-201615-10-20171.00 Job1.00 Job3.869.28
2.Foundation RHS1.00 Job3.2515-05-201625-06-20161.00 Job1.00 Job1.353.25
3.Foundation LHS1.00 Job3.5022-05-201605-07-20161.00 Job1.00 Job1.453.50
4.Abutment Superstructure RHS1.00 Job7.0326-06-201625-08-20161.00 Job1.00 Job2.927.03
5.Abutment Superstructure LHS1.00 Job9.2606-07-201602-09-20161.00 Job1.00 Job3.859.26
6.Fixing of chequered Plate/RCC Deck148.25 sqm10.7715-05-201731-05-2017148.25 sqm148.25 sqm4.4710.77
7.Steel Railing/crush barrier123.00 m3.8401-05-201731-05-2017123.00 m123.00 m1.593.84
8.Approach Ramp /path 130.00 m72.4415-09-201631-05-2017130.00 m130.00 m30.0972.44
9.Protection Work1.00 Job30.6901-05-201715-10-20171.00 Job1.00 Job12.7530.69
10.Errection Work1.00 Job90.6703-09-201631-05-20171.00 Job1.00 Job37.6790.67
Total Amount: 240.73 100   240.73
Remarks: No Remarks       Work Program Made On: 17-06-2016        Updation of work program on: 09-11-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.20-August-201622.89  lakh
2.27-October-201620.41  lakh
3.06-January-201769.64  lakh
4.18-February-201729.59  lakh
5.28-March-201730.61  lakh
6.26-May-201751.02  lakh
7.22-August-201720.14  lakh
8.13-October-201720.41  lakh
9.27-November-201730.61  lakh
10.23-December-20170.03  lakh
11.24-February-201831.15  lakh
12.28-July-20183.61  lakh
13.15-July-20196.49  lakh
Total 336.6  lakh
% Payment 101.59 %
Advance Amount:  66.33  lakh        Recovered Amount:  66.33  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 160   No. of Test Done : 160    No. of Test Passed : 160   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 91.55
Number of Notice(s) issued: 62

Mobile Pic Upload

Number of Pics Available on Web Repository: 12
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.15-02-2018PandranuC. E. Sir, S. E. Sir visited pandranu bridgeRohit KumarAssistant EngineerUDRP AF S&B Bageshwar See Pic
2.15-12-2017Pandranu bridgePandranu site visitRohit KumarAssistant EngineerUDRP AF S&B Bageshwar See Pic
3.08-02-2017Pandranu truss Bridge visit by Se sir and Ee sirErection work in progressGirish BobeQSBSC R&B WB Uttarkashi See Pic
4.08-02-2017Erection work in progress at Pandranu truss bridgeErection work in progressGirish BobeQSBSC R&B WB Uttarkashi See Pic
5.15-09-2016Pandranu bridgeM-30 R.c.c cap workPrateek TalwarJEUDRP R&B Uttarkashi See Pic
6.06-08-2016PandranuAbt A1 cap rebar completed ready to pour concrete.Sunil KumarREDSC1 R&B WB Uttarkashi See Pic
7.02-08-20160+060Raft concrete A1 AbutmentVipin Chandra BenjwalAEUDRP R&B Uttarkashi See Pic
8.25-06-20160.01Abutment A2 and abutment A1 steel bindingVipin Chandra BenjwalAEUDRP R&B Uttarkashi See Pic
9.25-06-20160.01Concrete in rafting A2Vipin Chandra BenjwalAEUDRP R&B Uttarkashi See Pic
10.25-06-20160.1Setting layout for the construction of bridge at pandranuVipin Chandra BenjwalAEUDRP R&B Uttarkashi See Pic
11.20-06-20162nd lift concrete @ Abutment A2 Truss bridge PandhranuConcrete At abutment a2Girish BobeQSBSC R&B WB Uttarkashi See Pic
12.09-10-20150.0Site inspection pandranu bridgeVipin Chandra BenjwalAEUDRP R&B Uttarkashi See Pic