Bridge at Jokhna Laga Bura
Work Completed
|
Project: |
UDRP-RB |
UID: |
4015 |
Sanction Cost: |
766.01 lakh |
Span:
|
70.000 M |
District: |
Chamoli |
Block: |
Ghat |
Constituency: |
Tharali |
Circle: |
|
DEA: |
DEA Karanprayag |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
undefined |
Type: |
Bridge |
|
Procurement: |
Package No.: 515
Package Name: 
UDRP/PWD/02/08/BR/015
Tender Date: 03-08-2015
Current Status: Agreement signed
Achieved on Date: 23-12-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/02/08/BR/015
Contractor Name: M/S.KGL Infrastructure
|
Start Date: 30-12-2015
Intended Completion Date: 28-01-2019
Original End Date: 29-03-2017 |
Total Bond Cost: 68383252 (683.83 lakh)
Variation Cost: 879416.12 (8.79 lakh) Hence Total Bond Cost is 69262668.12 (692.63 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 5162992 for +151 days
LD Analysis for Milestone2: calculated LD is Rs 14497408 for 424 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Env. Man & Moni Plan | 1.00 Job | 2.60 | 01-01-2019 | 28-01-2019 | 1.00 Job | 1.00 Job | 0.37 | 2.60 | 2. | Other Allied Works & Finishing Work | 1.00 Job | 15.57 | 15-06-2017 | 31-01-2019 | 1.00 Job | 1.00 Job | 2.19 | 15.57 | 3. | Foundation RHS | 1.00 Job | 49.14 | 02-05-2016 | 15-01-2017 | 1.00 Job | 1.00 Job | 6.92 | 49.14 | 4. | Foundation LHS | 1.00 Job | 49.14 | 04-05-2016 | 10-11-2017 | 1.00 Job | 1.00 Job | 6.92 | 49.14 | 5. | Abutment Superstructure RHS | 1.00 Job | 58.96 | 20-06-2017 | 10-12-2017 | 1.00 Job | 1.00 Job | 8.3 | 58.96 | 6. | Abutment Superstructure LHS | 1.00 Job | 58.96 | 10-03-2017 | 30-11-2017 | 1.00 Job | 1.00 Job | 8.3 | 58.96 | 7. | Trestle Erection and Bracing of Trestle Tower LHS | 1.00 job | 40.80 | 30-05-2017 | 20-12-2018 | 1.00 job | 1.00 job | 5.75 | 40.80 | 8. | Anchor Block Main Cable Reinforcement (3-4 Times) | 2.00 job | 176.89 | 15-06-2017 | 30-07-2018 | 2.00 job | 2.00 job | 24.91 | 176.89 | 9. | Anchor Block for Wind Cable: Reinforcement, Lewis | 4.00 job | 98.27 | 01-01-2018 | 30-07-2018 | 4.00 job | 4.00 job | 13.84 | 98.27 | 10. | Deck Cable laying, stretching and Fixing Transoms/Deck Slab | 2.00 no | 3.73 | 01-09-2017 | 25-11-2018 | 2.00 no | 2.00 no | 0.53 | 3.73 | 11. | Fixing of Saddle pulley along with Rib plate and | 4.00 no | 14.85 | 21-01-2018 | 25-08-2018 | 4.00 no | 4.00 no | 2.09 | 14.85 | 12. | Main Cable Laying and Stretching | 6.00 no | 26.13 | 15-09-2017 | 15-11-2018 | 6.00 no | 6.00 no | 3.68 | 26.13 | 13. | Fixing Suspenders to Main cable with clamps and Ha | 102.00 no | 3.47 | 26-09-2018 | 20-11-2018 | 102.00 no | 102.00 no | 0.49 | 3.47 | 14. | Stretching Wind Guy cable, Fixing wind Ties with | 52.00 m | 7.68 | 26-09-2018 | 05-01-2019 | 52.00 m | 52.00 m | 1.08 | 7.68 | 15. | Fixing longitudinal Stringers/girders | 80.00 m | 15.13 | 01-10-2017 | 15-12-2018 | 80.00 m | 80.00 m | 2.13 | 15.13 | 16. | Fixing of chequered Plate/RCC Deck | 204.95 sqm | 10.55 | 01-10-2017 | 17-12-2018 | 204.95 sqm | 204.95 sqm | 1.49 | 10.55 | 17. | Steel Railing/crush barrier | 172.00 m | 5.58 | 21-10-2018 | 20-01-2019 | 172.00 m | 172.00 m | 0.79 | 5.58 | 18. | Approach Ramp /path | 100.00 m | 6.75 | 10-10-2018 | 25-01-2019 | 100.00 m | 100.00 m | 0.95 | 6.75 | 19. | Protection Work | 2.00 Job | 65.98 | 15-12-2017 | 25-01-2019 | 2.00 Job | 2.00 Job | 9.29 | 65.98 |
Total Amount: |
710.18 |
|
100 |
710.18 |
|
Remarks:
No Remarks
Work Program Made On:
21-05-2016 } ?>
Updation of work program on:
02-08-2019
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 09-March-2017 | 48.80 lakh | 2. | 25-May-2017 | 62.46 lakh | 3. | 24-June-2017 | 48.61 lakh | 4. | 08-August-2017 | 87.07 lakh | 5. | 13-October-2017 | 58.09 lakh | 6. | 24-November-2017 | 16.23 lakh | 7. | 29-December-2017 | 20.88 lakh | 8. | 31-January-2018 | 13.45 lakh | 9. | 28-February-2018 | 19.38 lakh | 10. | 28-March-2018 | 19.17 lakh | 11. | 31-May-2018 | 28.25 lakh | 12. | 09-August-2018 | 69.06 lakh | 13. | 31-October-2018 | 64.20 lakh | 14. | 29-November-2018 | 14.79 lakh | 15. | 31-December-2018 | 1.82 lakh | 16. | 15-February-2019 | 50.55 lakh | 17. | 28-February-2019 | 20.95 lakh | 18. | 30-March-2019 | 30.64 lakh | 19. | 30-April-2019 | 12.70 lakh | 20. | 11-June-2019 | 5.54 lakh | 21. | 12-June-2019 | 17.56 lakh |
Total |
710.2 lakh |
% Payment |
102.54 % |
|
Advance Amount: 68.38 lakh
Recovered Amount: 68.38 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 1837 No. of Test Done : 1862 No. of Test Passed : 1837 No. of Test Failed : 25 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 95.03 |
Number of Notice(s) issued: 78 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 67 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 28-03-2019 | A1 | General inspection of Completed bridge | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
2. | 17-11-2018 | A2 | Erection of bridge in progress | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
3. | 15-10-2018 | A1 side wind Guy | Binding of wind guy slab reinforcement | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
4. | 19-09-2018 | A1side wind anchor | Checking of slump found satisfactory | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
5. | 19-09-2018 | A1 side wind Guy | Casting of wind anchor slab A1 side | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
6. | 06-09-2018 | A1 side wind Guy u/s | Shuttering work of wind guy under progress | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
7. | 06-09-2018 | A1 side Erection of tower under progress today stop due to rain. | Erection of Tower under progress | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
8. | 03-09-2018 | Jokhna Lagga Bura Bridge | Tower Erection A2 side is in progress | Charu Upadhyay | QS | BSC R&B WB Chamoli | See Pic |
9. | 08-08-2018 | A1 side Tower Erection | Tower Erection is under progress. | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
10. | 02-08-2018 | Jokhna Lagga Bura Bridge | Erection of Tower A1 Abutment is in progress. | Charu Upadhyay | QS | BSC R&B WB Chamoli | See Pic |
11. | 02-08-2018 | Jokhna Lagga Bura Bridge | SE Rudrapryag and ExEn Sunil Kumar sir visit | Charu Upadhyay | QS | BSC R&B WB Chamoli | See Pic |
12. | 01-08-2018 | A1 side | Site visit by SE R K Jain and EE
Sunil Kumar Sir. | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
13. | 01-08-2018 | A1 side at Jokhna Bridge site | Site visit by SE and EE | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
14. | 01-08-2018 | LHS wire crate protection | Laying of wire crate under progress satisfactorily | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
15. | 01-08-2018 | A2 side Anchor Block | Binding of reinforcement of wind anchor under progress | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
16. | 05-07-2018 | A1 side abutment | Important Instruction given by EE at the time of visit. | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
17. | 05-07-2018 | A1 side abutment | Instruction given by EE for aligning and fixing of Wire crate | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
18. | 05-07-2018 | A2 side abutment | Checking of reinforcement at level of 1752 m need to rectification. | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
19. | 18-05-2018 | A1 side Abutment | Binding of reinforcement of abutment. | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
20. | 18-05-2018 | A2 side RHS wind block at Jokhna Lagga | Shuttering work and binding of reinforcement satisfactorily in progress | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
|
|