Bridge over Benakuli river near Khiro
Work Completed
|
Project: |
UDRP-RB |
UID: |
4014 |
Sanction Cost: |
417.26 lakh |
Span:
|
45.000 M |
District: |
Chamoli |
Block: |
Joshimath |
Constituency: |
Badrinath |
Circle: |
|
DEA: |
DEA Gopeshwar |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
undefined |
Type: |
Bridge |
|
Procurement: |
Package No.: 519
Package Name: 
UDRP/PWD/02/08/BR/19
Tender Date: 15-02-2016
Current Status: Agreement signed
Achieved on Date: 05-05-2016 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/02/08/BR/19
Contractor Name: Triveni Construction Company
|
Start Date: 12-05-2016
Intended Completion Date: 31-07-2018
Original End Date: 11-08-2017 |
Total Bond Cost: 37791414.82 (377.91 lakh)
Variation Cost: -4692687.88 (-46.93 lakh) Hence Total Bond Cost is 33098726.94 (330.99 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 2872192 for +152 days
LD Analysis for Milestone2: calculated LD is Rs 6046720 for 320 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Crash Barrier | 143.60 m | 5.44 | 28-07-2018 | 10-09-2018 | 143.60 m | 143.60 m | 1.42 | 5.44 | 2. | Other Allied Works & Finishing Work | 1.00 Job | 16.29 | 15-10-2017 | 31-07-2018 | 1.00 Job | 1.00 Job | 4.25 | 16.29 | 3. | Foundation RHS | 1.00 Job | 14.27 | 15-10-2016 | 20-08-2017 | 1.00 Job | 1.00 Job | 3.72 | 14.27 | 4. | Foundation LHS | 1.00 Job | 17.31 | 20-09-2016 | 30-08-2017 | 1.00 Job | 1.00 Job | 4.52 | 17.31 | 5. | Abutment Superstructure RHS | 1.00 Job | 16.31 | 30-03-2017 | 05-12-2017 | 1.00 Job | 1.00 Job | 4.25 | 16.31 | 6. | Abutment Superstructure LHS | 1.00 Job | 23.08 | 30-03-2017 | 31-12-2017 | 1.00 Job | 1.00 Job | 6.02 | 23.08 | 7. | Fixing of chequered Plate/RCC Deck | 227.50 sqm | 18.52 | 01-03-2018 | 31-08-2018 | 227.50 sqm | 227.50 sqm | 4.83 | 18.52 | 8. | Steel Railing/crush barrier | 143.60 m | 5.44 | 28-07-2018 | 10-09-2018 | 143.60 m | 143.60 m | 1.42 | 5.44 | 9. | Approach Ramp /path | 140.00 m | 20.41 | 01-02-2018 | 15-08-2018 | 140.00 m | 140.00 m | 5.33 | 20.41 | 10. | Protection Work | 1.00 Job | 96.62 | 15-05-2017 | 15-07-2018 | 1.00 Job | 1.00 Job | 25.2 | 96.62 | 11. | Errection Work | 1.00 Job | 149.67 | 15-02-2018 | 25-07-2018 | 1.00 Job | 1.00 Job | 39.04 | 149.67 |
Total Amount: |
383.36 |
|
100 |
383.36 |
|
Remarks:
No Remarks
Work Program Made On:
24-08-2016 } ?>
Updation of work program on:
05-09-2018
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 31-March-2017 | 10.22 lakh | 2. | 25-May-2017 | 31.64 lakh | 3. | 28-July-2017 | 16.35 lakh | 4. | 30-November-2017 | 100.28 lakh | 5. | 17-February-2018 | 41.95 lakh | 6. | 26-March-2018 | 26.30 lakh | 7. | 30-May-2018 | 31.56 lakh | 8. | 13-August-2018 | 14.78 lakh | 9. | 30-August-2018 | 27.43 lakh | 10. | 20-October-2018 | 12.53 lakh | 11. | 31-December-2018 | 17.28 lakh |
Total |
330.32 lakh |
% Payment |
99.82 % |
|
Advance Amount: 79.29 lakh
Recovered Amount: 79.29 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 183 No. of Test Done : 218 No. of Test Passed : 214 No. of Test Failed : 4 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 88.45 |
Number of Notice(s) issued: 59 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 65 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 16-10-2018 | Ch/00 | Bridge protection work on progress | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
2. | 06-07-2018 | Benakuli bridge | Erection work in progress | Vikash Singh | JE | UDRP R&B Gopeshwar | See Pic |
3. | 18-06-2018 | 9019 Benakuli bridge | Erection work in progress at Benakuli bridge 9019 | Jagdish Chandra | QS | DSC4 R&B WB Chamoli | See Pic |
4. | 15-06-2018 | Benakuli bridge site A2 side | Pavement Quality concrete work in progress | Vikash Singh | JE | UDRP R&B Gopeshwar | See Pic |
5. | 15-06-2018 | Benakuli bridge A2 side approach work | Pavement quality concrete work | Vikash Singh | JE | UDRP R&B Gopeshwar | See Pic |
6. | 05-06-2018 | Benakuli bridge site | Tree plantation at benakuli bridge site | Vikash Singh | JE | UDRP R&B Gopeshwar | See Pic |
7. | 05-06-2018 | Benakuli bridge site | Tree Plantation at benakuli bridge | Vikash Singh | JE | UDRP R&B Gopeshwar | See Pic |
8. | 05-06-2018 | Benakuli bridge site | Erection work in progress at benakuli bridge site | Vikash Singh | JE | UDRP R&B Gopeshwar | See Pic |
9. | 29-05-2018 | 9019 Benakuli | Vertical members erection in progress at Benakuli bridge 9019 | Jagdish Chandra | QS | DSC4 R&B WB Chamoli | See Pic |
10. | 29-05-2018 | 9019 Benakmuli | Vertical members erection in progress at Benamuli | Jagdish Chandra | QS | DSC4 R&B WB Chamoli | See Pic |
11. | 18-04-2018 | Erection work in progress Benakuli bridge 9019 | Erection work in progress of Benakuli bridge 9019 | Jagdish Chandra | QS | DSC4 R&B WB Chamoli | See Pic |
12. | 19-03-2018 | Erection tower of 9019 | Benakuli bridge | Sanjeev Singh | ARE | DSC4 R&B WB Chamoli | See Pic |
13. | 09-03-2018 | Benakuli bridge erection tower | A1 side erection tower | Sanjeev Singh | ARE | DSC4 R&B WB Chamoli | See Pic |
14. | 21-02-2018 | 9019 Benakuli Bridge | Protection work with Gabion box in progress | Jagdish Chandra | QS | DSC4 R&B WB Chamoli | See Pic |
15. | 01-02-2018 | Abutment A1 pedestal lift cast | Benakuli bridge | Sanjeev Singh | ARE | DSC4 R&B WB Chamoli | See Pic |
16. | 01-02-2018 | A2 side protection work | Benakuli bridge | Sanjeev Singh | ARE | DSC4 R&B WB Chamoli | See Pic |
17. | 01-02-2018 | Abutment A2 protection work | Benakuli bridge | Sanjeev Singh | ARE | DSC4 R&B WB Chamoli | See Pic |
18. | 01-02-2018 | Abutment A1 protection work | Benakuli bridge | Sanjeev Singh | ARE | DSC4 R&B WB Chamoli | See Pic |
19. | 20-01-2018 | A2 bridge side | Gabion protection work at benakuli bridge A2 side | Vikash Singh | JE | UDRP R&B Gopeshwar | See Pic |
20. | 20-01-2018 | A2 abutment protection work | Benakuli bridge | Sanjeev Singh | ARE | DSC4 R&B WB Chamoli | See Pic |
|
|