Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Bridge at Kalpeshwar on Helang-Urgam-Kalkeshuar Bridle Road Work Completed
Project: UDRP-RB UID: 4013 Sanction Cost: 710.97  lakh Span: 80.000 M
District: Chamoli Block: Joshimath Constituency: Badrinath Circle:
DEA: DEA Gopeshwar DSC: Yongma Engineering Co. Ltd. DSC Scope: undefined Type: Bridge
Procurement:
Package No.: 526        Package Name:  UDRP/PWD/02/08/BR/19a        Tender Date: 15-12-2015        Current Status: Agreement signed        Achieved on Date: 17-03-2016

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/02/08/BR/19a      Contractor Name: Ram Kumar Contractor
Start Date:  25-03-2016      Intended Completion Date:  30-07-2018      Original End Date:  24-06-2017
Total Bond Cost: 57143358 (571.43 lakh)        Variation Cost: 12345810.62 (123.46 lakh)    Hence Total Bond Cost is   69489168.62 (694.89 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 4342944 for +152 days        LD Analysis for Milestone2: calculated LD is Rs 8714460 for 305 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Foundation RHS1.00 Job19.9323-05-201602-10-20171.00 Job1.00 Job3.7419.93
2.Foundation LHS1.00 Job12.2412-07-201615-10-20171.00 Job1.00 Job2.312.24
3.Abutment Superstructure RHS1.00 Job221.2510-12-201625-10-20171.00 Job1.00 Job41.51221.25
4.Abutment Superstructure LHS1.00 Job58.5510-04-201725-10-20171.00 Job1.00 Job10.9958.55
5.Trestle Erection and Bracing of Trestle Tower LHS 4.00 job68.4312-04-201830-04-20184.00 job4.00 job12.8468.43
6.Anchor Block Main Cable Reinforcement (3-4 Times) 1.00 job56.0525-04-201825-05-20181.00 job1.00 job10.5256.05
7.Anchor Block for Wind Cable: Reinforcement, Lewis 2.00 job25.9025-04-201810-07-20182.00 job2.00 job4.8625.90
8.Deck Cable laying, stretching and Fixing Transoms/Deck Slab 2.00 no13.7202-06-201815-07-20182.00 no2.00 no2.5713.72
9.Fixing of Saddle pulley along with Rib plate and 4.00 no13.8602-06-201815-06-20184.00 no4.00 no2.613.86
10.Main Cable Laying and Stretching 6.00 no30.9610-06-201830-07-20186.00 no6.00 no5.8130.96
11.Fixing Suspenders to Main cable with clamps and Ha104.00 no12.0825-07-201805-09-2018104.00 no104.00 no2.2712.08
Total Amount: 532.97 100   532.97
Remarks: No Remarks       Work Program Made On: 09-11-2016        Updation of work program on: 27-08-2018       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.31-August-201612.35  lakh
2.24-December-201628.74  lakh
3.24-April-201739.68  lakh
4.20-May-201744.15  lakh
5.28-July-201728.94  lakh
6.16-October-201727.20  lakh
7.30-November-2017120.31  lakh
8.31-January-201854.09  lakh
9.26-March-201872.70  lakh
10.28-April-201843.34  lakh
11.30-May-201867.19  lakh
12.02-July-201816.10  lakh
13.13-August-201819.57  lakh
14.30-August-201828.24  lakh
15.29-September-201861.66  lakh
16.20-February-201930.63  lakh
Total 694.89  lakh
% Payment 99.99 %
Advance Amount:  85.00  lakh        Recovered Amount:  85.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 718   No. of Test Done : 815    No. of Test Passed : 796   No. of Test Failed : 19   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 90.00
Number of Notice(s) issued: 60

Mobile Pic Upload

Number of Pics Available on Web Repository: 46
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.23-12-20184+850Environment interview.Anurag DevJEUDRP R&B Guptkashi See Pic
2.15-06-2018Helang urgam kalpeshwar bridge A2 sideTower Ereaction work in progressVikash SinghJEUDRP R&B Gopeshwar See Pic
3.05-06-2018Helang urgam klpeshwar site labCompresive strength testVikash SinghJEUDRP R&B Gopeshwar See Pic
4.05-06-2018A1 side helang urgam bridge siteWind anchor M25 work progressVikash SinghJEUDRP R&B Gopeshwar See Pic
5.27-04-2018Helong urgam bridge 9017Checking of erection of Tower of Helong urgam bridge 9017Jagdish ChandraQSDSC4 R&B WB Chamoli See Pic
6.27-04-20189017 Helong urgam bridgeCube testing of Helong urgam bridge 9017Jagdish ChandraQSDSC4 R&B WB Chamoli See Pic
7.11-03-2018Helong urgam bridge 9017Abutment A2 side Gabion protection work in progressJagdish ChandraQSDSC4 R&B WB Chamoli See Pic
8.11-03-2018Helong urgam bridge 9017Main anchor A2 Reinforcement and shuttering work above inspection gallery in progressJagdish ChandraQSDSC4 R&B WB Chamoli See Pic
9.24-02-20189017 Helong urgam bridgeMain Anchor A2 side column section 2nd Lift concrete & PlumJagdish ChandraQSDSC4 R&B WB Chamoli See Pic
10.03-02-2018Cube test result 17 daysUrgam BridgeSanjeev SinghAREDSC4 R&B WB Chamoli See Pic
11.03-02-2018Cube testUrgam Bridge test by EE sirSanjeev SinghAREDSC4 R&B WB Chamoli See Pic
12.03-02-2018Aiv testUrgam BridgeSanjeev SinghAREDSC4 R&B WB Chamoli See Pic
13.03-02-2018Aiv testAiv test at urgam bridgeSanjeev SinghAREDSC4 R&B WB Chamoli See Pic
14.03-02-2018Urgam bridgeFirst aid inspectionSanjeev SinghAREDSC4 R&B WB Chamoli See Pic
15.03-02-2018Helong urgam BridgeSite lab and sefteySanjeev SinghAREDSC4 R&B WB Chamoli See Pic
16.03-02-2018Inspection of 9017Urgam BridgeSanjeev SinghAREDSC4 R&B WB Chamoli See Pic
17.20-01-2018Main Anchor A2 2nd slab concrete slump testing found 95mmAt urgam bridge siteVikash SinghJEUDRP R&B Gopeshwar See Pic
18.20-01-2018Gabion box protection work in progress (A2) Heong- urgamUrgam BridgeJagdish ChandraQSDSC4 R&B WB Chamoli See Pic
19.30-10-2017Urgam kalpeshwar bridgeUrgam kalpeshwar bridgeSanjeev SinghAREDSC4 R&B WB Chamoli See Pic
20.27-06-2017Abutment A2Column abutment A2Sanjeev SinghAREDSC4 R&B WB Chamoli See Pic