Bridge at Ruch Mahadev Kotimaheshwar Mandir Bridle Road
Agreement signed
|
Project: |
UDRP-RB |
UID: |
4011 |
Sanction Cost: |
503.00 lakh |
Span:
|
70.000 M |
District: |
Rudraprayag |
Block: |
Ukhimath |
Constituency: |
Kedarnath |
Circle: |
|
DEA: |
DEA Guptkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
undefined |
Type: |
Bridge |
|
Procurement: |
Package No.: 511
Package Name: 
UDRP/PWD/03/40/BR/011
Tender Date: 09-04-2015
Current Status: Agreement signed
Achieved on Date: 20-02-2016 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/03/40/BR/011
Contractor Name: Kundan Singh Prem Singh Jamnal
|
Start Date: 27-02-2016
Intended Completion Date: 13-06-2017
Original End Date: 26-11-2016 |
Total Bond Cost: 49004223.93 (490.04 lakh)
Variation Cost: -47834654.27 (-478.35 lakh) Hence Total Bond Cost is 1169569.66 (11.7 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 2229682 for 91 days
LD Analysis for Milestone2: calculated LD is Rs 7105580 for 290 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Other Allied Works & Finishing Work | 1.00 Job | 0.44 | 25-01-2017 | 10-06-2017 | 1.00 Job | 1.00 Job | 3.77 | 0.44 | 2. | Foundation RHS | 0.50 Job | 6.47 | 25-11-2016 | 28-02-2017 | 1.00 Job | 0.50 Job | 27.67 | 3.24 | 3. | Foundation LHS | 1.00 Job | 2.85 | 21-11-2016 | 10-02-2017 | 1.00 Job | 1.00 Job | 24.34 | 2.85 | 4. | Abutment Superstructure RHS | 0.00 Job | 0.00 | 01-03-2017 | 30-03-2017 | 0.00 Job | 0.00 Job | 0 | 0.00 | 5. | Abutment Superstructure LHS | 0.10 Job | 1.94 | 11-02-2017 | 30-03-2017 | 1.00 Job | 0.10 Job | 1.66 | 0.19 | 6. | Fixing of chequered Plate/RCC Deck | 0.00 sqm | 0.00 | 16-05-2017 | 30-05-2017 | 0.00 sqm | 0.00 sqm | 0 | 0.00 | 7. | Steel Railing/crush barrier | 0.00 m | 0.00 | 16-05-2017 | 01-06-2017 | 0.00 m | 0.00 m | 0 | 0.00 | 8. | Approach Ramp /path | 0.00 m | 0.00 | 30-04-2017 | 30-05-2017 | 0.00 m | 0.00 m | 0 | 0.00 | 9. | Protection Work | 0.00 Job | 0.00 | 15-03-2017 | 05-06-2017 | 0.00 Job | 0.00 Job | 0 | 0.00 | 10. | Errection Work | 0.00 Job | 0.00 | 01-04-2017 | 15-05-2017 | 0.00 Job | 0.00 Job | 0 | 0.00 |
Total Amount: |
11.7 |
|
57.43 |
6.72 |
|
Remarks:
No Remarks
Work Program Made On:
15-11-2016 } ?>
Updation of work program on:
17-11-2018
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 30-March-2017 | 6.11 lakh | 2. | 30-October-2018 | 5.59 lakh |
Total |
11.7 lakh |
% Payment |
100 % |
|
Advance Amount: 49.00 lakh
Recovered Amount: 49.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level):
No Pending Issue
Environment & Social Compliances(Sub Project level):
EMP Land Owner Consent, Sanitation Facility, water sprinkling, debris disposal, Query |
Detailed report of this subproject
|
|
Quality
|
No. of Test Required : 4 No. of Test Done : 4 No. of Test Passed : 1 No. of Test Failed : 3 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 90.00 |
Number of Notice(s) issued: 75 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 18 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 16-12-2017 | Kotma Chilon A2 Side Protection Work in progress for Approach Road | Kotma Chilon A2 Side Protection Work for Approach Road | Suresh Prasad | RE | BSC R&B WB Rudraprayag | See Pic |
2. | 15-11-2017 | Ruch mahadev | Ruch | Vijay Mishra | RE | BSC R&B WB Rudraprayag | See Pic |
3. | 15-11-2017 | Ruch mahadev | Ruch | Vijay Mishra | RE | BSC R&B WB Rudraprayag | See Pic |
4. | 15-11-2017 | Ruchh mahadev CE Visit | Ruchh mahadev CE Visit | Suresh Prasad | RE | BSC R&B WB Rudraprayag | See Pic |
5. | 12-08-2017 | RUCHH MAHADEV A2 Side | Ruchh mahadev A2 Side | Suresh Prasad | RE | BSC R&B WB Rudraprayag | See Pic |
6. | 29-06-2017 | Ruchmajadev | Excavation | Vijay Mishra | RE | BSC R&B WB Rudraprayag | See Pic |
7. | 12-04-2017 | Ruch mahadev A1 excavation | A1 excavation | Vijay Mishra | RE | BSC R&B WB Rudraprayag | See Pic |
8. | 25-02-2017 | Ruch mahadev | Excavation work on progress | Anurag Rawat AE | AE | UDRP R&B Guptkashi | See Pic |
9. | 17-01-2017 | Ruch mahadev visit EE and SE | Ruch mahadev | Vijay Mishra | RE | BSC R&B WB Rudraprayag | See Pic |
10. | 06-01-2017 | Ruksh mahadev bridge | C.E. , E.E. A.R.E. and A.E. Sir visit | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
11. | 18-12-2016 | | Excavation work in progress for A1 Side abutment | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
12. | 18-12-2016 | Ruksh mahadev bridge | Site visit by E.E. Sir. | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
13. | 19-11-2016 | Rukch mahadev | Pcc footing | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
14. | 22-10-2016 | Ruksh mahadev bridge | Site visit by S.E. Sir and E.E. Sir | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
15. | 10-05-2016 | Ruch mahadev | CE,SE & EE sir site visit | Anurag Rawat AE | AE | UDRP R&B Guptkashi | See Pic |
16. | 13-10-2015 | Tamplesideabutmentruchmahadev | Sitemanphoteo | S C Tyagi | EE | DEA WB Guptkashi | See Pic |
17. | 13-10-2015 | Roadsideruchbridge | Bridgesite | S C Tyagi | EE | DEA WB Guptkashi | See Pic |
18. | 13-10-2015 | Ruchmahadevroadside | Bridgesite | S C Tyagi | EE | DEA WB Guptkashi | See Pic |
|
|