Bridge at Kotma Chilon Bridle Road
Work Completed
|
Project: |
UDRP-RB |
UID: |
4010 |
Sanction Cost: |
382.00 lakh |
Span:
|
70.000 M |
District: |
Rudraprayag |
Block: |
Ukhimath |
Constituency: |
Kedarnath |
Circle: |
|
DEA: |
DEA Guptkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
undefined |
Type: |
Bridge |
|
Procurement: |
Package No.: 510
Package Name: 
UDRP/PWD/03/40/BR/010
Tender Date: 09-04-2015
Current Status: Agreement signed
Achieved on Date: 20-02-2016 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/03/40/BR/010
Contractor Name: Prayag Construction
|
Start Date: 27-02-2016
Intended Completion Date: 31-07-2018
Original End Date: 26-11-2016 |
Total Bond Cost: 35016779.15 (350.17 lakh)
Variation Cost: -5797264.40 (-57.97 lakh) Hence Total Bond Cost is 29219514.75 (292.2 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 1593228 for +91 days
LD Analysis for Milestone2: calculated LD is Rs 9541860 for 545 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Other Allied Works & Finishing Work | 1.00 Job | 41.46 | 01-11-2016 | 30-06-2018 | 1.00 Job | 1.00 Job | 11.84 | 41.46 | 2. | Foundation RHS | 1.00 Job | 7.00 | 04-06-2016 | 30-11-2016 | 1.00 Job | 1.00 Job | 2 | 7.00 | 3. | Foundation LHS | 1.00 Job | 7.00 | 04-06-2016 | 10-01-2017 | 1.00 Job | 1.00 Job | 2 | 7.00 | 4. | Abutment Superstructure RHS | 1.00 Job | 10.90 | 30-11-2016 | 20-12-2017 | 1.00 Job | 1.00 Job | 3.11 | 10.90 | 5. | Abutment Superstructure LHS | 1.00 Job | 10.90 | 10-01-2017 | 30-12-2017 | 1.00 Job | 1.00 Job | 3.11 | 10.90 | 6. | Fixing of chequered Plate/RCC Deck | 210.00 sqm | 16.36 | 20-03-2018 | 24-06-2018 | 210.00 sqm | 210.00 sqm | 4.67 | 16.36 | 7. | Steel Railing/crush barrier | 140.00 m | 8.13 | 20-03-2018 | 24-06-2018 | 140.00 m | 140.00 m | 2.32 | 8.13 | 8. | Approach Ramp /path | 246.00 m | 58.39 | 20-11-2017 | 31-03-2018 | 246.00 m | 246.00 m | 16.68 | 58.39 | 9. | Protection Work | 1.00 Job | 51.74 | 05-03-2017 | 31-03-2018 | 1.00 Job | 1.00 Job | 14.78 | 51.74 | 10. | Errection Work | 1.00 Job | 138.27 | 05-03-2017 | 10-06-2018 | 1.00 Job | 1.00 Job | 39.49 | 138.27 |
Total Amount: |
350.15 |
|
100 |
350.15 |
|
Remarks:
No Remarks
Work Program Made On:
17-08-2016 } ?>
Updation of work program on:
20-06-2018
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 16-February-2017 | 13.08 lakh | 2. | 30-March-2017 | 9.37 lakh | 3. | 07-July-2017 | 20.67 lakh | 4. | 26-August-2017 | 28.89 lakh | 5. | 22-December-2017 | 17.60 lakh | 6. | 21-March-2018 | 120.13 lakh | 7. | 28-April-2018 | 31.90 lakh | 8. | 29-August-2018 | 76.33 lakh |
Total |
317.97 lakh |
% Payment |
108.82 % |
|
Advance Amount: 63.89 lakh
Recovered Amount: 63.89 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 408 No. of Test Done : 410 No. of Test Passed : 405 No. of Test Failed : 5 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 92.01 |
Number of Notice(s) issued: 85 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 127 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 15-02-2019 | Km3 | Anchor wall concrete | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
2. | 29-01-2019 | Km3 | Concrete work for anchor wall | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
3. | 07-08-2018 | | Kotma chilon bridge erection on progress | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
4. | 02-08-2018 | | Kotma bridge | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
5. | 18-07-2018 | Kotma chilon | L.h.s apporach path | Anurag Rawat AE | AE | UDRP R&B Guptkashi | See Pic |
6. | 11-07-2018 | | Marking bearing level by TS | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
7. | 11-07-2018 | | Doing T.S. survey for as built drawing. | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
8. | 11-07-2018 | | Erection work at Kotma chilon bridge | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
9. | 11-07-2018 | | Site visit by CME sir with EE sir & RE sir | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
10. | 17-05-2018 | Kotmachilone visit EE and CME | Kotmachilone | Deepak Pant | Site supervisior | UDRP AF Irrigation birahi | See Pic |
11. | 17-05-2018 | Kotma visit EE and CME | Kotmachilone | Deepak Pant | Site supervisior | UDRP AF Irrigation birahi | See Pic |
12. | 17-05-2018 | Kotmachilone | Visit EE and AE | Deepak Pant | Site supervisior | UDRP AF Irrigation birahi | See Pic |
13. | 14-04-2018 | Kotmachilone | Kotmachilone | Deepak Pant | Site supervisior | UDRP AF Irrigation birahi | See Pic |
14. | 07-04-2018 | Kotnachilone | Kotmachilone | Deepak Pant | Site supervisior | UDRP AF Irrigation birahi | See Pic |
15. | 03-04-2018 | Kotmachilone | Kotmachilone se Sir visit | Deepak Pant | Site supervisior | UDRP AF Irrigation birahi | See Pic |
16. | 03-04-2018 | Se Sir visit | Kotmachilone | Deepak Pant | Site supervisior | UDRP AF Irrigation birahi | See Pic |
17. | 30-03-2018 | Kotmachilone erection | Kotmachilone | Deepak Pant | Site supervisior | UDRP AF Irrigation birahi | See Pic |
18. | 30-03-2018 | Kotmachilone | Kotmachilone | Deepak Pant | Site supervisior | UDRP AF Irrigation birahi | See Pic |
19. | 20-03-2018 | | Site visit by DPM, EE, AE,JE, RE and ARE | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
20. | 20-03-2018 | | Ground erection checking by EE, RE, AE, and Bridge engineer. | Anurag Dev | JE | UDRP R&B Guptkashi | See Pic |
|
|