Bridge over Aglad river at Gaivd-Chamasari Work Completed
Project: UDRP-RB UID: 4009 Sanction Cost: 467.00  lakh Span: 60.000 M
District: Tehri Block: Jaunpur Constituency: Dhanaulti Circle:
DEA: DEA Tehri DSC: Yongma Engineering Co. Ltd. DSC Scope: Design Type: Bridge
Procurement:
Package No.: 509        Package Name:  UDRP/PWD/04/49/BR/09        Tender Date: 25-02-2016        Current Status: Agreement signed        Achieved on Date: 16-06-2016

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/04/49/BR/09      Contractor Name: Triveni Construction Company
Start Date:  23-06-2016      Intended Completion Date:  31-07-2018      Original End Date:  22-03-2017
Total Bond Cost: 43324330.14 (433.24 lakh)       
LD Analysis for Milestone1: calculated LD is Rs 1949580 for +90 days        LD Analysis for Milestone2: calculated LD is Rs 8946406 for 413 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Other Allied Works & Finishing Work 1.00 Job3.6125-10-201624-06-20171.00 Job1.00 Job0.833.61
2.Foundation RHS1.00 Job10.0625-10-201612-12-20161.00 Job1.00 Job2.3210.06
3.Foundation LHS1.00 Job18.6630-10-201615-12-20161.00 Job1.00 Job4.3118.66
4.Abutment Superstructure RHS1.00 Job16.2020-12-201605-02-20171.00 Job1.00 Job3.7416.20
5.Abutment Superstructure LHS1.00 Job24.0920-12-201610-02-20171.00 Job1.00 Job5.5624.09
6.Fixing of chequered Plate/RCC Deck185.40 sqm12.5501-06-201723-06-2017185.40 sqm185.40 sqm2.912.55
7.Steel Railing/crush barrier123.80 m4.3805-06-201723-06-2017130.00 m130.00 m1.014.38
8.Approach Ramp /path 120.00 m47.3001-03-201720-06-2017200.00 m200.00 m10.9247.30
9.Protection Work1.00 Job169.6411-12-201624-02-20171196.00 Job1196.00 Job39.17169.64
10.Errection Work1.00 Job126.6611-02-201730-05-20171.00 Job1.00 Job29.24126.66
Total Amount: 433.15 100   433.15
Remarks: No Remarks       Work Program Made On: 15-11-2016        Updation of work program on: 18-11-2016       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.04-February-201735.83  lakh
2.07-March-201721.12  lakh
3.28-March-201717.63  lakh
4.21-June-201731.27  lakh
5.24-July-201716.68  lakh
6.28-October-201748.25  lakh
7.28-February-201863.70  lakh
8.26-March-201852.45  lakh
9.24-July-201838.58  lakh
10.30-August-201829.52  lakh
11.31-October-201851.78  lakh
12.31-December-201824.86  lakh
Total 431.67  lakh
% Payment 99.63 %
Advance Amount:  43.32  lakh        Recovered Amount:  43.32  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 159   No. of Test Done : 160    No. of Test Passed : 160   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 90.00
Number of Notice(s) issued: 58

Mobile Pic Upload

Number of Pics Available on Web Repository: 32
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.01-11-2019Abutment A2Construction of 48m span steel truss bridge at kot VishanAE Saurab ChauhanAssistant EngineerUDRP R&B Tehri See Pic
2.07-05-2018At bridgeErection work on progressJagat Chand RamolaJEUDRP R&B Tehri See Pic
3.28-04-2018At bridgeErection work on progressJagat Chand RamolaJEUDRP R&B Tehri See Pic
4.28-04-2018At bridgeBottom bracing erection work on progressJagat Chand RamolaJEUDRP R&B Tehri See Pic
5.03-02-2018Kargi Chauk, DehradunInspection of ground erection of Chamasari 65m Truss Bridge, UID no 9039.by SE Sir, BE Shri RN Subramanian & TLAnurag SinghTLBSC R&B WB Rudraprayag See Pic
6.24-01-2018Bearing plate workshop for chamasari bridge at yumnanagerChecking of Vertical load test for free POT-PTFE bearing by SE sir, TL sir, Bridge Engineer sir, AE sirJagat Chand RamolaJEUDRP R&B Tehri See Pic
7.08-01-2018RHS of bridgeSite visit by SE sir,Jagat Chand RamolaJEUDRP R&B Tehri See Pic
8.08-01-2018LHS abutmentLHS abutment checking by SE sir, TL sir, and EE mamJagat Chand RamolaJEUDRP R&B Tehri See Pic
9.06-01-2018Febrication workshop near kargi chowk dehradunGround Erection work on progressJagat Chand RamolaJEUDRP R&B Tehri See Pic
10.31-12-2017Abutment A1Abutment A 1 concret work on progressJagat Chand RamolaJEUDRP R&B Tehri See Pic
11.31-12-2017Abutment A 1Cube casting for abutment m30 grade concreteJagat Chand RamolaJEUDRP R&B Tehri See Pic
12.19-12-2017At Bridge siteFire safetyJagat Chand RamolaJEUDRP R&B Tehri See Pic
13.19-12-2017A2 abutmentA2 abutment checking by EE mamJagat Chand RamolaJEUDRP R&B Tehri See Pic
14.19-12-2017At bridgeSite visit by EE mamJagat Chand RamolaJEUDRP R&B Tehri See Pic
15.19-12-2017Abutment A1abutment A1 checking by EE mamJagat Chand RamolaJEUDRP R&B Tehri See Pic
16.15-12-2017Febrication Workshop near kargi chowk dehradunSample collection for testingJagat Chand RamolaJEUDRP R&B Tehri See Pic
17.15-12-2017Fabrication Workshop near kargi chowkSample collection for structural steel testingJagat Chand RamolaJEUDRP R&B Tehri See Pic
18.15-12-2017Bridge Approch roadImprovement of Approch roadJagat Chand RamolaJEUDRP R&B Tehri See Pic
19.15-12-2017Bridge protectionGeotextile mactex behind gabionsJagat Chand RamolaJEUDRP R&B Tehri See Pic
20.14-12-2017A2 abutmentA2 AbutmentJagat Chand RamolaJEUDRP R&B Tehri See Pic