Bridge over indrawati river near Sada
Work Completed
|
Project: |
UDRP-RB |
UID: |
4008 |
Sanction Cost: |
713.16 lakh |
Span:
|
80.000 M |
District: |
Uttarkashi |
Block: |
Bhatwari |
Constituency: |
Gangotri |
Circle: |
|
DEA: |
DEA Uttarkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design |
Type: |
Bridge |
|
Procurement: |
Package No.: 508
Package Name: 
UDRP/PWD/01/31/BR/08
Tender Date: 04-03-2015
Current Status: Agreement signed
Achieved on Date: 04-03-2016 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/01/31/BR/08
Contractor Name: Kailash Hillways Engineering Associates
|
Start Date: 11-03-2016
Intended Completion Date: 31-07-2018
Original End Date: 10-06-2017 |
Total Bond Cost: 51808562 (518.09 lakh)
Variation Cost: 18535621.93 (185.36 lakh) Hence Total Bond Cost is 70344183.93 (703.44 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 3937408 for +152 days
LD Analysis for Milestone2: calculated LD is Rs 9351344 for 361 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Other Allied Works & Finishing Work | 1.00 Job | 29.72 | 11-05-2016 | 30-06-2018 | 1.00 Job | 1.00 Job | 5.74 | 29.72 | 2. | Foundation RHS | 1.00 Job | 23.63 | 11-05-2016 | 31-08-2017 | 1.00 Job | 1.00 Job | 4.56 | 23.63 | 3. | Foundation LHS | 1.00 Job | 5.07 | 25-05-2016 | 31-05-2017 | 1.00 Job | 1.00 Job | 0.98 | 5.07 | 4. | Abutment Superstructure RHS | 1.00 Job | 133.88 | 01-06-2017 | 31-08-2017 | 1.00 Job | 1.00 Job | 25.84 | 133.88 | 5. | Abutment Superstructure LHS | 1.00 Job | 20.29 | 21-08-2016 | 31-05-2017 | 1.00 Job | 1.00 Job | 3.92 | 20.29 | 6. | Trestle Erection and Bracing of Trestle Tower LHS | 2.00 job | 38.05 | 01-06-2017 | 10-05-2018 | 2.00 job | 2.00 job | 7.35 | 38.05 | 7. | Anchor Block Main Cable Reinforcement (3-4 Times) | 1.00 job | 92.71 | 01-01-2017 | 20-06-2018 | 1.00 job | 1.00 job | 17.9 | 92.71 | 8. | Anchor Block for Wind Cable: Reinforcement, Lewis | 4.00 job | 19.02 | 01-04-2017 | 31-10-2017 | 4.00 job | 4.00 job | 3.67 | 19.02 | 9. | Anchor Block for Wind Cable: Reinforcement, Lewis (Step 2) | 0.00 job | 0.00 | 05-06-2018 | 20-06-2018 | 0.00 job | 4.00 job | 0 | 0.00 | 10. | Deck Cable laying, stretching and Fixing Transoms/Deck Slab | 2.00 no | 2.86 | 10-06-2018 | 18-06-2018 | 2.00 no | 2.00 no | 0.55 | 2.86 | 11. | Fixing of Saddle pulley along with Rib plate and | 4.00 no | 4.28 | 15-05-2018 | 20-05-2018 | 4.00 no | 4.00 no | 0.83 | 4.28 | 12. | Main Cable Laying and Stretching | 6.00 no | 19.72 | 20-05-2018 | 31-05-2018 | 6.00 no | 6.00 no | 3.81 | 19.72 | 13. | Fixing Suspenders to Main cable with clamps and Ha | 104.00 no | 2.03 | 09-06-2018 | 19-06-2018 | 104.00 no | 104.00 no | 0.39 | 2.03 | 14. | Stretching Wind Guy cable, Fixing wind Ties with | 52.00 m | 4.34 | 25-06-2018 | 28-06-2018 | 52.00 m | 52.00 m | 0.84 | 4.34 | 15. | Fixing longitudinal Stringers/girders | 76.96 m | 10.81 | 10-06-2018 | 19-06-2018 | 76.96 m | 76.96 m | 2.09 | 10.81 | 16. | Fixing of chequered Plate/RCC Deck | 199.71 sqm | 12.30 | 20-06-2018 | 25-06-2018 | 199.71 sqm | 199.71 sqm | 2.37 | 12.30 | 17. | Steel Railing/crush barrier | 180.00 m | 6.48 | 20-06-2018 | 25-06-2018 | 180.00 m | 180.00 m | 1.25 | 6.48 | 18. | Approach Ramp /path | 164.00 m | 66.01 | 20-04-2017 | 31-05-2018 | 164.00 m | 164.00 m | 12.74 | 66.01 | 19. | Protection Work | 1.00 Job | 26.88 | 15-05-2017 | 25-06-2018 | 1.00 Job | 1.00 Job | 5.19 | 26.88 |
Total Amount: |
518.08 |
|
100 |
518.08 |
|
Remarks:
No Remarks
Work Program Made On:
17-08-2016 } ?>
Updation of work program on:
26-05-2018
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 11-August-2016 | 12.58 lakh | 2. | 27-October-2016 | 30.61 lakh | 3. | 31-January-2017 | 33.95 lakh | 4. | 31-March-2017 | 39.98 lakh | 5. | 30-June-2017 | 14.28 lakh | 6. | 23-August-2017 | 16.26 lakh | 7. | 13-October-2017 | 35.79 lakh | 8. | 23-November-2017 | 2.56 lakh | 9. | 27-November-2017 | 51.02 lakh | 10. | 23-December-2017 | 0.68 lakh | 11. | 31-January-2018 | 62.56 lakh | 12. | 28-February-2018 | 10.20 lakh | 13. | 31-March-2018 | 30.61 lakh | 14. | 10-May-2018 | 23.16 lakh | 15. | 26-May-2018 | 82.72 lakh | 16. | 26-July-2018 | 46.51 lakh | 17. | 29-August-2018 | 30.00 lakh | 18. | 29-September-2018 | 87.11 lakh | 19. | 13-December-2018 | 93.54 lakh | 20. | 15-July-2019 | 5.52 lakh |
Total |
709.64 lakh |
% Payment |
100.86 % |
|
Advance Amount: 45.61 lakh
Recovered Amount: 45.61 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 1433 No. of Test Done : 1433 No. of Test Passed : 1432 No. of Test Failed : 1 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 92.33 |
Number of Notice(s) issued: 88 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 83 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 18-06-2018 | BR /08 | Deck erection in Progress | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
2. | 29-05-2018 | Sada bridge (BR 08) | World Bank mission visit with SE Sir New Tehri, EE Sir Uttarkashi & TL Sir BSC-01. | Manjunath Naik | RE | DSC4 R&B WB Uttarkashi | See Pic |
3. | 26-05-2018 | Sada Bridge (BR-08) | Inspection of Anchor Block RHS, and other site activities at Sada Bridge (BR-08). | Manjunath Naik | RE | DSC4 R&B WB Uttarkashi | See Pic |
4. | 14-05-2018 | Sada bridge, br-08 | 1st lift after 1st slab Conc. Work is in progress for anchor block A2 | Rohit Kumar | Assistant Engineer | UDRP AF S&B Bageshwar | See Pic |
5. | 08-05-2018 | Sada Bridge (BR-08) | Views of Erection Work in progress. | Manjunath Naik | RE | DSC4 R&B WB Uttarkashi | See Pic |
6. | 07-04-2018 | Sada bridge BR/08 | SE Sir visit | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
7. | 24-03-2018 | Didsari Bridge (BR-04) | Bed preparation for Slope Protection Work on NH side. | Manjunath Naik | RE | DSC4 R&B WB Uttarkashi | See Pic |
8. | 24-03-2018 | A2 | NDT test for abutment A2 | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
9. | 09-03-2018 | Didsari Bridge (BR-08) | Chief Engineer Sir, Superintendent Engineer Sir and Executive Engineer Sir's Visit. | Manjunath Naik | RE | DSC4 R&B WB Uttarkashi | See Pic |
10. | 03-02-2018 | Kargi Chauk, UID no 9039,Chamasari 65 m T/B. | Inspection of ground erection Chamasari 65m, T/B by SE BN Chaudhary sir, BE Shri RN Subramanian TL. | Anurag Singh | TL | BSC R&B WB Rudraprayag | See Pic |
11. | 03-02-2018 | Laltapped Rishikesh | Inspection of febrication yard 80m S/B Sada Indrawati at Rishikesh. | Anurag Singh | TL | BSC R&B WB Rudraprayag | See Pic |
12. | 03-02-2018 | Mazri Grand Lal Tappad UID no 9036, Sada Indrawati S/B, | Inspection of fabrication 80m Sada Indrawati suspension bridge with SE, BE, AEN | Anurag Singh | TL | BSC R&B WB Rudraprayag | See Pic |
13. | 26-01-2018 | Sada | Checking setting out of Anchor Block at Sada Bridge (BR-08) | Manjunath Naik | RE | DSC4 R&B WB Uttarkashi | See Pic |
14. | 08-01-2018 | Sada, Uttarkashi. | View of Sada Bridge which is under construction. | Manjunath Naik | RE | DSC4 R&B WB Uttarkashi | See Pic |
15. | 19-12-2017 | Sada Bridge | Approach Road in progress on A-2 Side. | Manjunath Naik | RE | DSC4 R&B WB Uttarkashi | See Pic |
16. | 18-12-2017 | Didsari bridge in Uttarkashi | STEEL Binding of A2 abutment Third lift in progress. | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
17. | 12-12-2017 | Sada bridge | Left abutment side | Ramesh Chand | EE | UDRP R&B Uttarkashi | See Pic |
18. | 06-12-2017 | Sada bridge | Concreting of abutment A2 first slab is in progress | Abhishek Tiwari | AE | UDRP AF SL&B Uttarkashi | See Pic |
19. | 05-12-2017 | Sada bridge | Site Meeting | Manjunath Naik | RE | DSC4 R&B WB Uttarkashi | See Pic |
20. | 04-12-2017 | Sada bridge | Abutment A2 first slab concreting work is in progress | Rohit Kumar | Assistant Engineer | UDRP AF S&B Bageshwar | See Pic |
|
|