Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Bridge over indrawati river near Sada Work Completed
Project: UDRP-RB UID: 4008 Sanction Cost: 713.16  lakh Span: 80.000 M
District: Uttarkashi Block: Bhatwari Constituency: Gangotri Circle:
DEA: DEA Uttarkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: Design Type: Bridge
Procurement:
Package No.: 508        Package Name:  UDRP/PWD/01/31/BR/08        Tender Date: 04-03-2015        Current Status: Agreement signed        Achieved on Date: 04-03-2016

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/01/31/BR/08      Contractor Name: Kailash Hillways Engineering Associates
Start Date:  11-03-2016      Intended Completion Date:  31-07-2018      Original End Date:  10-06-2017
Total Bond Cost: 51808562 (518.09 lakh)        Variation Cost: 18535621.93 (185.36 lakh)    Hence Total Bond Cost is   70344183.93 (703.44 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 3937408 for +152 days        LD Analysis for Milestone2: calculated LD is Rs 9351344 for 361 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Other Allied Works & Finishing Work 1.00 Job29.7211-05-201630-06-20181.00 Job1.00 Job5.7429.72
2.Foundation RHS1.00 Job23.6311-05-201631-08-20171.00 Job1.00 Job4.5623.63
3.Foundation LHS1.00 Job5.0725-05-201631-05-20171.00 Job1.00 Job0.985.07
4.Abutment Superstructure RHS1.00 Job133.8801-06-201731-08-20171.00 Job1.00 Job25.84133.88
5.Abutment Superstructure LHS1.00 Job20.2921-08-201631-05-20171.00 Job1.00 Job3.9220.29
6.Trestle Erection and Bracing of Trestle Tower LHS 2.00 job38.0501-06-201710-05-20182.00 job2.00 job7.3538.05
7.Anchor Block Main Cable Reinforcement (3-4 Times) 1.00 job92.7101-01-201720-06-20181.00 job1.00 job17.992.71
8.Anchor Block for Wind Cable: Reinforcement, Lewis 4.00 job19.0201-04-201731-10-20174.00 job4.00 job3.6719.02
9.Anchor Block for Wind Cable: Reinforcement, Lewis (Step 2)0.00 job0.0005-06-201820-06-20180.00 job4.00 job00.00
10.Deck Cable laying, stretching and Fixing Transoms/Deck Slab 2.00 no2.8610-06-201818-06-20182.00 no2.00 no0.552.86
11.Fixing of Saddle pulley along with Rib plate and 4.00 no4.2815-05-201820-05-20184.00 no4.00 no0.834.28
12.Main Cable Laying and Stretching 6.00 no19.7220-05-201831-05-20186.00 no6.00 no3.8119.72
13.Fixing Suspenders to Main cable with clamps and Ha104.00 no2.0309-06-201819-06-2018104.00 no104.00 no0.392.03
14.Stretching Wind Guy cable, Fixing wind Ties with 52.00 m4.3425-06-201828-06-201852.00 m52.00 m0.844.34
15.Fixing longitudinal Stringers/girders76.96 m10.8110-06-201819-06-201876.96 m76.96 m2.0910.81
16.Fixing of chequered Plate/RCC Deck199.71 sqm12.3020-06-201825-06-2018199.71 sqm199.71 sqm2.3712.30
17.Steel Railing/crush barrier180.00 m6.4820-06-201825-06-2018180.00 m180.00 m1.256.48
18.Approach Ramp /path 164.00 m66.0120-04-201731-05-2018164.00 m164.00 m12.7466.01
19.Protection Work1.00 Job26.8815-05-201725-06-20181.00 Job1.00 Job5.1926.88
Total Amount: 518.08 100   518.08
Remarks: No Remarks       Work Program Made On: 17-08-2016        Updation of work program on: 26-05-2018       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.11-August-201612.58  lakh
2.27-October-201630.61  lakh
3.31-January-201733.95  lakh
4.31-March-201739.98  lakh
5.30-June-201714.28  lakh
6.23-August-201716.26  lakh
7.13-October-201735.79  lakh
8.23-November-20172.56  lakh
9.27-November-201751.02  lakh
10.23-December-20170.68  lakh
11.31-January-201862.56  lakh
12.28-February-201810.20  lakh
13.31-March-201830.61  lakh
14.10-May-201823.16  lakh
15.26-May-201882.72  lakh
16.26-July-201846.51  lakh
17.29-August-201830.00  lakh
18.29-September-201887.11  lakh
19.13-December-201893.54  lakh
20.15-July-20195.52  lakh
Total 709.64  lakh
% Payment 100.86 %
Advance Amount:  45.61  lakh        Recovered Amount:  45.61  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 1433   No. of Test Done : 1433    No. of Test Passed : 1432   No. of Test Failed : 1   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 92.33
Number of Notice(s) issued: 88

Mobile Pic Upload

Number of Pics Available on Web Repository: 83
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.18-06-2018BR /08Deck erection in ProgressChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
2.29-05-2018Sada bridge (BR 08)World Bank mission visit with SE Sir New Tehri, EE Sir Uttarkashi & TL Sir BSC-01.Manjunath NaikREDSC4 R&B WB Uttarkashi See Pic
3.26-05-2018Sada Bridge (BR-08)Inspection of Anchor Block RHS, and other site activities at Sada Bridge (BR-08).Manjunath NaikREDSC4 R&B WB Uttarkashi See Pic
4.14-05-2018Sada bridge, br-081st lift after 1st slab Conc. Work is in progress for anchor block A2Rohit KumarAssistant EngineerUDRP AF S&B Bageshwar See Pic
5.08-05-2018Sada Bridge (BR-08)Views of Erection Work in progress.Manjunath NaikREDSC4 R&B WB Uttarkashi See Pic
6.07-04-2018Sada bridge BR/08SE Sir visitChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
7.24-03-2018Didsari Bridge (BR-04)Bed preparation for Slope Protection Work on NH side.Manjunath NaikREDSC4 R&B WB Uttarkashi See Pic
8.24-03-2018A2NDT test for abutment A2Naveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
9.09-03-2018Didsari Bridge (BR-08)Chief Engineer Sir, Superintendent Engineer Sir and Executive Engineer Sir's Visit.Manjunath NaikREDSC4 R&B WB Uttarkashi See Pic
10.03-02-2018Kargi Chauk, UID no 9039,Chamasari 65 m T/B.Inspection of ground erection Chamasari 65m, T/B by SE BN Chaudhary sir, BE Shri RN Subramanian TL.Anurag SinghTLBSC R&B WB Rudraprayag See Pic
11.03-02-2018Laltapped RishikeshInspection of febrication yard 80m S/B Sada Indrawati at Rishikesh.Anurag SinghTLBSC R&B WB Rudraprayag See Pic
12.03-02-2018Mazri Grand Lal Tappad UID no 9036, Sada Indrawati S/B,Inspection of fabrication 80m Sada Indrawati suspension bridge with SE, BE, AENAnurag SinghTLBSC R&B WB Rudraprayag See Pic
13.26-01-2018SadaChecking setting out of Anchor Block at Sada Bridge (BR-08)Manjunath NaikREDSC4 R&B WB Uttarkashi See Pic
14.08-01-2018Sada, Uttarkashi.View of Sada Bridge which is under construction.Manjunath NaikREDSC4 R&B WB Uttarkashi See Pic
15.19-12-2017Sada BridgeApproach Road in progress on A-2 Side.Manjunath NaikREDSC4 R&B WB Uttarkashi See Pic
16.18-12-2017Didsari bridge in UttarkashiSTEEL Binding of A2 abutment Third lift in progress.Chandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
17.12-12-2017Sada bridgeLeft abutment sideRamesh ChandEEUDRP R&B Uttarkashi See Pic
18.06-12-2017Sada bridgeConcreting of abutment A2 first slab is in progressAbhishek TiwariAEUDRP AF SL&B Uttarkashi See Pic
19.05-12-2017Sada bridgeSite MeetingManjunath NaikREDSC4 R&B WB Uttarkashi See Pic
20.04-12-2017Sada bridgeAbutment A2 first slab concreting work is in progressRohit KumarAssistant EngineerUDRP AF S&B Bageshwar See Pic