Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Bridge over Alaknanda river at Aarudi- Paturdi Work Completed
Project: UDRP-RB UID: 4006 Sanction Cost: 1243.00  lakh Span: 140.000 M
District: Chamoli Block: unknown Constituency: unknown Circle:
DEA: DEA Gopeshwar DSC: Yongma Engineering Co. Ltd. DSC Scope: Design Type: Bridge
Procurement:
Package No.: 506        Package Name:  UDRP/PWD/02/08/BR/06        Tender Date: 04-03-2015        Current Status: Agreement signed        Achieved on Date: 21-07-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/02/08/BR/06      Contractor Name: V. K. Gupta & Associates
Start Date:  28-07-2015      Intended Completion Date:  15-06-2019      Original End Date:  27-10-2016
Total Bond Cost: 102149390 (1021.49 lakh)        Variation Cost: 14048307.05 (140.48 lakh)    Hence Total Bond Cost is   116197697.05 (1161.98 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 7814475 for +153 days        LD Analysis for Milestone2: calculated LD is Rs 27529425 for 539 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Foundation RHS1.00 Job44.3102-12-201520-09-20171.00 Job1.00 Job9.744.31
2.Foundation LHS1.00 Job12.2411-11-201530-09-20171.00 Job1.00 Job2.6812.24
3.Abutment Superstructure RHS1.00 Job72.0801-11-201630-10-20171.00 Job1.00 Job15.7772.08
4.Abutment Superstructure LHS1.00 Job72.0801-12-201630-10-20171.00 Job1.00 Job15.7772.08
5.Trestle Erection and Bracing of Trestle Tower LHS 1.00 job25.3020-04-201815-07-20181.00 job1.00 job5.5425.30
6.Anchor Block Main Cable Reinforcement (3-4 Times) 1.00 job56.0515-05-201825-07-20181.00 job1.00 job12.2756.05
7.Anchor Block for Wind Cable: Reinforcement, Lewis 2.00 job25.9015-05-201825-07-20182.00 job2.00 job5.6725.90
8.Deck Cable laying, stretching and Fixing Transoms/Deck Slab 2.00 no13.7220-05-201830-08-20182.00 no2.00 no313.72
9.Fixing of Saddle pulley along with Rib plate and 4.00 no6.0010-11-201730-08-20184.00 no4.00 no1.316.00
10.Main Cable Laying and Stretching 1148.00 no44.9715-01-201830-08-20181148.00 no1148.00 no9.8444.97
11.Fixing Suspenders to Main cable with clamps and Ha90.00 no0.1825-02-201830-08-201890.00 no90.00 no0.040.18
12.Stretching Wind Guy cable, Fixing wind Ties with 90.00 m0.7215-05-201830-08-201890.00 m90.00 m0.160.72
13.Fixing longitudinal Stringers/girders34.70 m38.1720-05-201830-08-201834.70 m34.70 m8.3538.17
14.Fixing of chequered Plate/RCC Deck17.23 sqm15.8527-05-201815-11-201817.23 sqm17.23 sqm3.4715.85
15.Steel Railing/crush barrier306.00 m9.7920-06-201830-10-2018306.00 m306.00 m2.149.79
16.Approach Ramp /path 126.00 m19.5908-05-201830-11-2018126.00 m126.00 m4.2919.59
Total Amount: 456.95 100   456.95
Remarks: No Remarks       Work Program Made On: 01-01-2016        Updation of work program on: 06-11-2019       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.30-January-201625.29  lakh
2.27-March-201730.76  lakh
3.28-March-2017177.99  lakh
4.24-June-201734.70  lakh
5.12-October-201784.67  lakh
6.30-November-2017207.73  lakh
7.28-February-201816.61  lakh
8.26-March-201873.00  lakh
9.29-June-201846.17  lakh
10.01-September-201811.38  lakh
11.26-November-201867.66  lakh
12.31-December-201864.67  lakh
13.29-March-201960.01  lakh
14.25-May-201997.98  lakh
15.30-June-201979.55  lakh
16.12-July-20198.87  lakh
Total 1087.04  lakh
% Payment 93.56 %
Advance Amount:  393.59  lakh        Recovered Amount:  350.64  lakh        Balance to be Recovered  42.95  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 875   No. of Test Done : 1022    No. of Test Passed : 976   No. of Test Failed : 46   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 90.00
Number of Notice(s) issued: 90

Mobile Pic Upload

Number of Pics Available on Web Repository: 81
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.28-10-2021Abutment LHSEE sir site visit erection work checkingVineet kumar je ` ` See Pic
2.17-06-2020A1 sideSoil monitoring testing sample collectionVineet KumarJEUDRP R&B Guptkashi See Pic
3.16-10-2018Site labM/30, grade cube testing work on progressNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
4.16-10-2018Site labCube testing work on progress, grade M/30Neeraj PathakQCDSC WB Bridge Uttarkashi See Pic
5.16-10-2018Ch0/00"Abutment A1 site work on progressNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
6.29-05-20189020 Arudi Patudi bridgeReinforcement checking of main anchor A2 9020Jagdish ChandraQSDSC4 R&B WB Chamoli See Pic
7.29-05-20189020 BridgeChecking of reinforcement of Main anchor A2 By JE,AE and QSJagdish ChandraQSDSC4 R&B WB Chamoli See Pic
8.10-05-2018Arudi Patudi bridge 9020No work in progress last one month at Arudi Patudi bridge 9020Jagdish ChandraQSDSC4 R&B WB Chamoli See Pic
9.24-04-20189020Wind anchor 2nd Lift completeJagdish ChandraQSDSC4 R&B WB Chamoli See Pic
10.04-04-20189020 Arudi Patudi bridgeWind Anchor A2 U/S Layout checking Arudi Patudi bridge 9020Jagdish ChandraQSDSC4 R&B WB Chamoli See Pic
11.13-03-2018Arudi Patudi bridge UID 9020Site visit Mam Neha Dobhal Arudi Patudi bridge UID 9020Jagdish ChandraQSDSC4 R&B WB Chamoli See Pic
12.12-03-2018Arudi Patudi bridge 9020Checking of reinforcement of Abutment A2 side 3rd slabJagdish ChandraQSDSC4 R&B WB Chamoli See Pic
13.09-03-2018Main anchor A2 protectionA2 side 9020Sanjeev SinghAREDSC4 R&B WB Chamoli See Pic
14.25-02-2018Abutment A2Abutment inspectionSanjeev SinghAREDSC4 R&B WB Chamoli See Pic
15.25-02-2018Abutment A2Final slabSanjeev SinghAREDSC4 R&B WB Chamoli See Pic
16.02-02-2018Cube test 9020Arudi patudi bridgeSanjeev SinghAREDSC4 R&B WB Chamoli See Pic
17.02-02-2018Abutment A2Arudi patudi bridgeSanjeev SinghAREDSC4 R&B WB Chamoli See Pic
18.02-02-2018Gabion checkingArudi patudi bridgeSanjeev SinghAREDSC4 R&B WB Chamoli See Pic
19.02-02-2018Arudi patudiArudi patudi bridgeSanjeev SinghAREDSC4 R&B WB Chamoli See Pic
20.02-02-20189020 arudi patudi bridge9020Sanjeev SinghAREDSC4 R&B WB Chamoli See Pic