Bridge over Alaknanda river at Aarudi- Paturdi
Work Completed
|
Project: |
UDRP-RB |
UID: |
4006 |
Sanction Cost: |
1243.00 lakh |
Span:
|
140.000 M |
District: |
Chamoli |
Block: |
unknown |
Constituency: |
unknown |
Circle: |
|
DEA: |
DEA Gopeshwar |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design |
Type: |
Bridge |
|
Procurement: |
Package No.: 506
Package Name: 
UDRP/PWD/02/08/BR/06
Tender Date: 04-03-2015
Current Status: Agreement signed
Achieved on Date: 21-07-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/02/08/BR/06
Contractor Name: V. K. Gupta & Associates
|
Start Date: 28-07-2015
Intended Completion Date: 15-06-2019
Original End Date: 27-10-2016 |
Total Bond Cost: 102149390 (1021.49 lakh)
Variation Cost: 14048307.05 (140.48 lakh) Hence Total Bond Cost is 116197697.05 (1161.98 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 7814475 for +153 days
LD Analysis for Milestone2: calculated LD is Rs 27529425 for 539 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Foundation RHS | 1.00 Job | 44.31 | 02-12-2015 | 20-09-2017 | 1.00 Job | 1.00 Job | 9.7 | 44.31 | 2. | Foundation LHS | 1.00 Job | 12.24 | 11-11-2015 | 30-09-2017 | 1.00 Job | 1.00 Job | 2.68 | 12.24 | 3. | Abutment Superstructure RHS | 1.00 Job | 72.08 | 01-11-2016 | 30-10-2017 | 1.00 Job | 1.00 Job | 15.77 | 72.08 | 4. | Abutment Superstructure LHS | 1.00 Job | 72.08 | 01-12-2016 | 30-10-2017 | 1.00 Job | 1.00 Job | 15.77 | 72.08 | 5. | Trestle Erection and Bracing of Trestle Tower LHS | 1.00 job | 25.30 | 20-04-2018 | 15-07-2018 | 1.00 job | 1.00 job | 5.54 | 25.30 | 6. | Anchor Block Main Cable Reinforcement (3-4 Times) | 1.00 job | 56.05 | 15-05-2018 | 25-07-2018 | 1.00 job | 1.00 job | 12.27 | 56.05 | 7. | Anchor Block for Wind Cable: Reinforcement, Lewis | 2.00 job | 25.90 | 15-05-2018 | 25-07-2018 | 2.00 job | 2.00 job | 5.67 | 25.90 | 8. | Deck Cable laying, stretching and Fixing Transoms/Deck Slab | 2.00 no | 13.72 | 20-05-2018 | 30-08-2018 | 2.00 no | 2.00 no | 3 | 13.72 | 9. | Fixing of Saddle pulley along with Rib plate and | 4.00 no | 6.00 | 10-11-2017 | 30-08-2018 | 4.00 no | 4.00 no | 1.31 | 6.00 | 10. | Main Cable Laying and Stretching | 1148.00 no | 44.97 | 15-01-2018 | 30-08-2018 | 1148.00 no | 1148.00 no | 9.84 | 44.97 | 11. | Fixing Suspenders to Main cable with clamps and Ha | 90.00 no | 0.18 | 25-02-2018 | 30-08-2018 | 90.00 no | 90.00 no | 0.04 | 0.18 | 12. | Stretching Wind Guy cable, Fixing wind Ties with | 90.00 m | 0.72 | 15-05-2018 | 30-08-2018 | 90.00 m | 90.00 m | 0.16 | 0.72 | 13. | Fixing longitudinal Stringers/girders | 34.70 m | 38.17 | 20-05-2018 | 30-08-2018 | 34.70 m | 34.70 m | 8.35 | 38.17 | 14. | Fixing of chequered Plate/RCC Deck | 17.23 sqm | 15.85 | 27-05-2018 | 15-11-2018 | 17.23 sqm | 17.23 sqm | 3.47 | 15.85 | 15. | Steel Railing/crush barrier | 306.00 m | 9.79 | 20-06-2018 | 30-10-2018 | 306.00 m | 306.00 m | 2.14 | 9.79 | 16. | Approach Ramp /path | 126.00 m | 19.59 | 08-05-2018 | 30-11-2018 | 126.00 m | 126.00 m | 4.29 | 19.59 |
Total Amount: |
456.95 |
|
100 |
456.95 |
|
Remarks:
No Remarks
Work Program Made On:
01-01-2016 } ?>
Updation of work program on:
06-11-2019
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 30-January-2016 | 25.29 lakh | 2. | 27-March-2017 | 30.76 lakh | 3. | 28-March-2017 | 177.99 lakh | 4. | 24-June-2017 | 34.70 lakh | 5. | 12-October-2017 | 84.67 lakh | 6. | 30-November-2017 | 207.73 lakh | 7. | 28-February-2018 | 16.61 lakh | 8. | 26-March-2018 | 73.00 lakh | 9. | 29-June-2018 | 46.17 lakh | 10. | 01-September-2018 | 11.38 lakh | 11. | 26-November-2018 | 67.66 lakh | 12. | 31-December-2018 | 64.67 lakh | 13. | 29-March-2019 | 60.01 lakh | 14. | 25-May-2019 | 97.98 lakh | 15. | 30-June-2019 | 79.55 lakh | 16. | 12-July-2019 | 8.87 lakh |
Total |
1087.04 lakh |
% Payment |
93.56 % |
|
Advance Amount: 393.59 lakh
Recovered Amount: 350.64 lakh
Balance to be Recovered 42.95 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 875 No. of Test Done : 1022 No. of Test Passed : 976 No. of Test Failed : 46 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 90.00 |
Number of Notice(s) issued: 90 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 81 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 28-10-2021 | Abutment LHS | EE sir site visit erection work checking | Vineet kumar je | ` | ` | See Pic |
2. | 17-06-2020 | A1 side | Soil monitoring testing sample collection | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
3. | 16-10-2018 | Site lab | M/30, grade cube testing work on progress | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
4. | 16-10-2018 | Site lab | Cube testing work on progress, grade M/30 | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
5. | 16-10-2018 | Ch0/00" | Abutment A1 site work on progress | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
6. | 29-05-2018 | 9020 Arudi Patudi bridge | Reinforcement checking of main anchor A2 9020 | Jagdish Chandra | QS | DSC4 R&B WB Chamoli | See Pic |
7. | 29-05-2018 | 9020 Bridge | Checking of reinforcement of Main anchor A2 By JE,AE and QS | Jagdish Chandra | QS | DSC4 R&B WB Chamoli | See Pic |
8. | 10-05-2018 | Arudi Patudi bridge 9020 | No work in progress last one month at Arudi Patudi bridge 9020 | Jagdish Chandra | QS | DSC4 R&B WB Chamoli | See Pic |
9. | 24-04-2018 | 9020 | Wind anchor 2nd Lift complete | Jagdish Chandra | QS | DSC4 R&B WB Chamoli | See Pic |
10. | 04-04-2018 | 9020 Arudi Patudi bridge | Wind Anchor A2 U/S Layout checking Arudi Patudi bridge 9020 | Jagdish Chandra | QS | DSC4 R&B WB Chamoli | See Pic |
11. | 13-03-2018 | Arudi Patudi bridge UID 9020 | Site visit Mam Neha Dobhal Arudi Patudi bridge UID 9020 | Jagdish Chandra | QS | DSC4 R&B WB Chamoli | See Pic |
12. | 12-03-2018 | Arudi Patudi bridge 9020 | Checking of reinforcement of Abutment A2 side 3rd slab | Jagdish Chandra | QS | DSC4 R&B WB Chamoli | See Pic |
13. | 09-03-2018 | Main anchor A2 protection | A2 side 9020 | Sanjeev Singh | ARE | DSC4 R&B WB Chamoli | See Pic |
14. | 25-02-2018 | Abutment A2 | Abutment inspection | Sanjeev Singh | ARE | DSC4 R&B WB Chamoli | See Pic |
15. | 25-02-2018 | Abutment A2 | Final slab | Sanjeev Singh | ARE | DSC4 R&B WB Chamoli | See Pic |
16. | 02-02-2018 | Cube test 9020 | Arudi patudi bridge | Sanjeev Singh | ARE | DSC4 R&B WB Chamoli | See Pic |
17. | 02-02-2018 | Abutment A2 | Arudi patudi bridge | Sanjeev Singh | ARE | DSC4 R&B WB Chamoli | See Pic |
18. | 02-02-2018 | Gabion checking | Arudi patudi bridge | Sanjeev Singh | ARE | DSC4 R&B WB Chamoli | See Pic |
19. | 02-02-2018 | Arudi patudi | Arudi patudi bridge | Sanjeev Singh | ARE | DSC4 R&B WB Chamoli | See Pic |
20. | 02-02-2018 | 9020 arudi patudi bridge | 9020 | Sanjeev Singh | ARE | DSC4 R&B WB Chamoli | See Pic |
|
|