Ratura Suspension Bridge
Work Completed
|
Project: |
UDRP-RB |
UID: |
4005 |
Sanction Cost: |
685.44 lakh |
Span:
|
80.000 M |
District: |
Rudraprayag |
Block: |
August Muni |
Constituency: |
Rudraprayag |
Circle: |
|
DEA: |
DEA Guptkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design |
Type: |
Bridge |
|
Procurement: |
Package No.: 528
Package Name: 
UDRP/PWD/BR/05(N)
Tender Date: 03-08-2018
Current Status: Agreement signed
Achieved on Date: 22-10-2018 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/BR/05(N)
Contractor Name: Kailash Hillways Engineering Associates
|
Start Date: 30-10-2018
Intended Completion Date: 29-06-2019
|
Total Bond Cost: 39317818.74 (393.18 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Other Allied Works & Finishing Work | 1.00 Job | 34.29 | 01-02-2019 | 29-06-2019 | 1.00 Job | 1.00 Job | 8.72 | 34.29 | 2. | Abutment Superstructure LHS | 1.00 Job | 16.30 | 01-12-2018 | 15-04-2019 | 1.00 Job | 1.00 Job | 4.15 | 16.30 | 3. | Trestle Erection and Bracing of Trestle Tower LHS | 1.00 job | 8.00 | 01-05-2019 | 30-05-2019 | 1.00 job | 1.00 job | 2.04 | 8.00 | 4. | Anchor Block Main Cable Reinforcement (3-4 Times) | 1.00 job | 246.43 | 25-11-2018 | 10-06-2019 | 1.00 job | 1.00 job | 62.68 | 246.43 | 5. | Deck Cable laying, stretching and Fixing Transoms/Deck Slab | 2.00 no | 1.00 | 15-05-2019 | 15-06-2019 | 2.00 no | 2.00 no | 0.25 | 1.00 | 6. | Fixing of Saddle pulley along with Rib plate and | 4.00 no | 6.54 | 15-05-2019 | 10-06-2019 | 4.00 no | 4.00 no | 1.66 | 6.54 | 7. | Main Cable Laying and Stretching | 6.00 no | 3.00 | 10-04-2019 | 10-06-2019 | 6.00 no | 6.00 no | 0.76 | 3.00 | 8. | Fixing Suspenders to Main cable with clamps and Ha | 160.00 no | 10.00 | 25-04-2019 | 25-06-2019 | 160.00 no | 160.00 no | 2.54 | 10.00 | 9. | Fixing of chequered Plate/RCC Deck | 200.00 sqm | 43.12 | 01-05-2019 | 25-06-2019 | 200.00 sqm | 200.00 sqm | 10.97 | 43.12 | 10. | Approach Ramp /path | 480.00 m | 13.47 | 20-11-2018 | 25-06-2019 | 480.00 m | 480.00 m | 3.43 | 13.47 | 11. | Protection Work | 1.00 Job | 11.03 | 01-02-2019 | 29-06-2019 | 1.00 Job | 1.00 Job | 2.81 | 11.03 |
Total Amount: |
393.18 |
|
100 |
393.18 |
|
Remarks:
No Remarks
Work Program Made On:
20-11-2018 } ?>
Updation of work program on:
30-05-2019
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 09-March-2017 | 45.32 lakh | 2. | 30-March-2017 | 31.83 lakh | 3. | 28-July-2017 | 30.01 lakh | 4. | 31-January-2018 | 51.79 lakh | 5. | 28-April-2018 | 20.35 lakh | 6. | 25-September-2018 | 37.36 lakh |
Previous Package Expenditure Total |
216.66 lakh |
SNo. |
Date |
Payment |
1. | 24-December-2018 | 12.33 lakh | 2. | 22-February-2019 | 62.81 lakh | 3. | 30-March-2019 | 99.04 lakh | 4. | 31-May-2019 | 57.42 lakh | 5. | 19-June-2019 | 25.43 lakh | 6. | 30-June-2019 | 48.03 lakh | 7. | 18-July-2019 | 9.95 lakh | 8. | 28-August-2019 | 30.74 lakh | 9. | 16-October-2019 | 17.06 lakh |
Total |
362.81 lakh |
% Payment |
92.28 % |
|
Advance Amount: 35.77 lakh
Recovered Amount: 35.77 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 164 No. of Test Done : 164 No. of Test Passed : 164 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 87.05 |
Number of Notice(s) issued: 3 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 166 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 30-05-2019 | A1 side | Site visit of MR. Mark, Mr. Harish sir, SE, EE, AE | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
2. | 30-05-2019 | A1 side | Site visit of world bank | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
3. | 30-05-2019 | Road side | Deck plate and channel arrived at site | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
4. | 30-05-2019 | Site lab | 7 days cube testing | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
5. | 03-05-2019 | A2 side | Awerness program of the occasion of Labour Day distribution of fruits | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
6. | 03-05-2019 | A2 side anchorcum tower | A2 side anchorcum tower casting work in progress | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
7. | 03-05-2019 | A1 side tower | A1 side tower erection start | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
8. | 27-04-2019 | A2 side anchorcum tower | A2 side anchorcum tower casting | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
9. | 27-04-2019 | A2 side anchorcum tower wall casting | A2 side anchorcum tower casting work in progress | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
10. | 04-04-2019 | Site lab | Cube testing checking by CE and SE sir | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
11. | 04-04-2019 | A1 side | A1 abutment | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
12. | 04-04-2019 | Site lab | CE and SE sir site visit lab register checking | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
13. | 02-04-2019 | Site office | Site visit SE, EE and AE | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
14. | 29-03-2019 | Site lab | Site lab documents check by AE mem | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
15. | 29-03-2019 | A1 side | Steel checking by AE mem | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
16. | 29-03-2019 | A1 side | Steel wire mesh checking of abutment under base plate | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
17. | 26-02-2019 | Site lab | Site lab cube testing in presence of SE sir during visit | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
18. | 26-02-2019 | A1 side | Utility trolley shifting A1 side anchor block cadting | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
19. | 26-02-2019 | Sure lab | Site lab record checking by SE sir site visit | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
20. | 17-01-2019 | Site lab | Cube testing 7 days result pass | Vineet Kumar | JE | UDRP R&B Guptkashi | See Pic |
|
|