Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Ratura Suspension Bridge Work Completed
Project: UDRP-RB UID: 4005 Sanction Cost: 685.44  lakh Span: 80.000 M
District: Rudraprayag Block: August Muni Constituency: Rudraprayag Circle:
DEA: DEA Guptkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: Design Type: Bridge
Procurement:
Package No.: 528        Package Name:  UDRP/PWD/BR/05(N)        Tender Date: 03-08-2018        Current Status: Agreement signed        Achieved on Date: 22-10-2018

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/BR/05(N)      Contractor Name: Kailash Hillways Engineering Associates
Start Date:  30-10-2018      Intended Completion Date:  29-06-2019     
Total Bond Cost: 39317818.74 (393.18 lakh)       
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Other Allied Works & Finishing Work 1.00 Job34.2901-02-201929-06-20191.00 Job1.00 Job8.7234.29
2.Abutment Superstructure LHS1.00 Job16.3001-12-201815-04-20191.00 Job1.00 Job4.1516.30
3.Trestle Erection and Bracing of Trestle Tower LHS 1.00 job8.0001-05-201930-05-20191.00 job1.00 job2.048.00
4.Anchor Block Main Cable Reinforcement (3-4 Times) 1.00 job246.4325-11-201810-06-20191.00 job1.00 job62.68246.43
5.Deck Cable laying, stretching and Fixing Transoms/Deck Slab 2.00 no1.0015-05-201915-06-20192.00 no2.00 no0.251.00
6.Fixing of Saddle pulley along with Rib plate and 4.00 no6.5415-05-201910-06-20194.00 no4.00 no1.666.54
7.Main Cable Laying and Stretching 6.00 no3.0010-04-201910-06-20196.00 no6.00 no0.763.00
8.Fixing Suspenders to Main cable with clamps and Ha160.00 no10.0025-04-201925-06-2019160.00 no160.00 no2.5410.00
9.Fixing of chequered Plate/RCC Deck200.00 sqm43.1201-05-201925-06-2019200.00 sqm200.00 sqm10.9743.12
10.Approach Ramp /path 480.00 m13.4720-11-201825-06-2019480.00 m480.00 m3.4313.47
11.Protection Work1.00 Job11.0301-02-201929-06-20191.00 Job1.00 Job2.8111.03
Total Amount: 393.18 100   393.18
Remarks: No Remarks       Work Program Made On: 20-11-2018        Updation of work program on: 30-05-2019       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.09-March-201745.32  lakh
2.30-March-201731.83  lakh
3.28-July-201730.01  lakh
4.31-January-201851.79  lakh
5.28-April-201820.35  lakh
6.25-September-201837.36  lakh
Previous Package Expenditure Total 216.66  lakh
SNo. Date Payment
1.24-December-201812.33  lakh
2.22-February-201962.81  lakh
3.30-March-201999.04  lakh
4.31-May-201957.42  lakh
5.19-June-201925.43  lakh
6.30-June-201948.03  lakh
7.18-July-20199.95  lakh
8.28-August-201930.74  lakh
9.16-October-201917.06  lakh
Total 362.81  lakh
% Payment 92.28 %
Advance Amount:  35.77  lakh        Recovered Amount:  35.77  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 164   No. of Test Done : 164    No. of Test Passed : 164   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 87.05
Number of Notice(s) issued: 3

Mobile Pic Upload

Number of Pics Available on Web Repository: 166
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.30-05-2019A1 sideSite visit of MR. Mark, Mr. Harish sir, SE, EE, AEVineet KumarJEUDRP R&B Guptkashi See Pic
2.30-05-2019A1 sideSite visit of world bankVineet KumarJEUDRP R&B Guptkashi See Pic
3.30-05-2019Road sideDeck plate and channel arrived at siteVineet KumarJEUDRP R&B Guptkashi See Pic
4.30-05-2019Site lab7 days cube testingVineet KumarJEUDRP R&B Guptkashi See Pic
5.03-05-2019A2 sideAwerness program of the occasion of Labour Day distribution of fruitsVineet KumarJEUDRP R&B Guptkashi See Pic
6.03-05-2019A2 side anchorcum towerA2 side anchorcum tower casting work in progressVineet KumarJEUDRP R&B Guptkashi See Pic
7.03-05-2019A1 side towerA1 side tower erection startVineet KumarJEUDRP R&B Guptkashi See Pic
8.27-04-2019A2 side anchorcum towerA2 side anchorcum tower castingVineet KumarJEUDRP R&B Guptkashi See Pic
9.27-04-2019A2 side anchorcum tower wall castingA2 side anchorcum tower casting work in progressVineet KumarJEUDRP R&B Guptkashi See Pic
10.04-04-2019Site labCube testing checking by CE and SE sirVineet KumarJEUDRP R&B Guptkashi See Pic
11.04-04-2019A1 sideA1 abutmentVineet KumarJEUDRP R&B Guptkashi See Pic
12.04-04-2019Site labCE and SE sir site visit lab register checkingVineet KumarJEUDRP R&B Guptkashi See Pic
13.02-04-2019Site officeSite visit SE, EE and AEVineet KumarJEUDRP R&B Guptkashi See Pic
14.29-03-2019Site labSite lab documents check by AE memVineet KumarJEUDRP R&B Guptkashi See Pic
15.29-03-2019A1 sideSteel checking by AE memVineet KumarJEUDRP R&B Guptkashi See Pic
16.29-03-2019A1 sideSteel wire mesh checking of abutment under base plateVineet KumarJEUDRP R&B Guptkashi See Pic
17.26-02-2019Site labSite lab cube testing in presence of SE sir during visitVineet KumarJEUDRP R&B Guptkashi See Pic
18.26-02-2019A1 sideUtility trolley shifting A1 side anchor block cadtingVineet KumarJEUDRP R&B Guptkashi See Pic
19.26-02-2019Sure labSite lab record checking by SE sir site visitVineet KumarJEUDRP R&B Guptkashi See Pic
20.17-01-2019Site labCube testing 7 days result passVineet KumarJEUDRP R&B Guptkashi See Pic