Chepado Bridge
Work Completed
|
Project: |
UDRP-RB |
UID: |
4004 |
Sanction Cost: |
1073.00 lakh |
Span:
|
120.000 M |
District: |
Chamoli |
Block: |
unknown |
Constituency: |
unknown |
Circle: |
|
DEA: |
DEA Karanprayag |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
design |
Type: |
Bridge |
|
Procurement: |
Package No.: 501
Package Name: 
UDRP/PWD/02/37/BR/01
Tender Date: 06-01-2015
Current Status: Agreement signed
Achieved on Date: 01-07-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/02/37/BR/01
Contractor Name: M/S.KGL Infrastructure
|
Start Date: 08-07-2015
Intended Completion Date: 28-02-2019
Original End Date: 07-10-2016 |
Total Bond Cost: 68202553.94 (682.03 lakh)
Variation Cost: 20260513.23 (202.61 lakh) Hence Total Bond Cost is 88463067.17 (884.63 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 2557575 for +75 days
LD Analysis for Milestone2: calculated LD is Rs 6956604 for 204 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Env. Man & Moni Plan | 1.00 Job | 5.36 | 01-02-2019 | 28-02-2019 | 1.00 Job | 1.00 Job | 0.59 | 5.36 | 2. | Other Allied Works & Finishing Work | 1.00 Job | 39.81 | 01-07-2017 | 03-03-2019 | 1.00 Job | 1.00 Job | 4.38 | 39.81 | 3. | Foundation RHS | 1.00 Job | 80.00 | 15-11-2016 | 15-12-2017 | 1.00 Job | 1.00 Job | 8.81 | 80.00 | 4. | Foundation LHS | 1.00 Job | 43.08 | 02-11-2016 | 30-10-2017 | 1.00 Job | 1.00 Job | 4.74 | 43.08 | 5. | Abutment Superstructure RHS | 1.00 Job | 184.61 | 15-12-2016 | 30-12-2018 | 1.00 Job | 1.00 Job | 20.33 | 184.61 | 6. | Abutment Superstructure LHS | 1.00 Job | 73.84 | 15-04-2017 | 30-01-2018 | 1.00 Job | 1.00 Job | 8.13 | 73.84 | 7. | Trestle Erection and Bracing of Trestle Tower LHS | 1.00 job | 31.43 | 20-02-2017 | 15-11-2018 | 1.00 job | 1.00 job | 3.46 | 31.43 | 8. | Anchor Block Main Cable Reinforcement (3-4 Times) | 1.00 job | 110.76 | 15-09-2017 | 20-12-2018 | 1.00 job | 1.00 job | 12.2 | 110.76 | 9. | Anchor Block for Wind Cable: Reinforcement, Lewis | 4.00 job | 123.07 | 01-10-2017 | 30-08-2018 | 4.00 job | 4.00 job | 13.55 | 123.07 | 10. | Deck Cable laying, stretching and Fixing Transoms/Deck Slab | 2.00 no | 5.24 | 01-04-2018 | 23-02-2019 | 2.00 no | 2.00 no | 0.58 | 5.24 | 11. | Fixing of Saddle pulley along with Rib plate and | 4.00 no | 15.07 | 16-02-2018 | 14-11-2018 | 4.00 no | 4.00 no | 1.66 | 15.07 | 12. | Main Cable Laying and Stretching | 8.00 no | 42.40 | 11-03-2018 | 02-02-2019 | 8.00 no | 8.00 no | 4.67 | 42.40 | 13. | Fixing Suspenders to Main cable with clamps and Ha | 158.00 no | 5.32 | 25-11-2018 | 22-02-2019 | 158.00 no | 158.00 no | 0.59 | 5.32 | 14. | Stretching Wind Guy cable, Fixing wind Ties with | 80.00 m | 9.57 | 25-11-2018 | 27-02-2019 | 80.00 m | 80.00 m | 1.05 | 9.57 | 15. | Fixing longitudinal Stringers/girders | 120.00 m | 41.52 | 15-10-2017 | 22-02-2019 | 120.00 m | 120.00 m | 4.57 | 41.52 | 16. | Fixing of chequered Plate/RCC Deck | 297.00 sqm | 16.21 | 26-11-2018 | 27-02-2019 | 297.00 sqm | 297.00 sqm | 1.79 | 16.21 | 17. | Steel Railing/crush barrier | 255.00 m | 8.73 | 16-01-2019 | 02-03-2019 | 255.00 m | 255.00 m | 0.96 | 8.73 | 18. | Approach Ramp /path | 100.00 m | 3.05 | 05-11-2018 | 03-03-2019 | 100.00 m | 100.00 m | 0.34 | 3.05 | 19. | Protection Work | 2.00 Job | 69.12 | 15-10-2017 | 01-03-2019 | 2.00 Job | 2.00 Job | 7.61 | 69.12 |
Total Amount: |
908.19 |
|
100 |
908.19 |
|
Remarks:
No Remarks
Work Program Made On:
02-01-2016 } ?>
Updation of work program on:
02-08-2019
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 09-March-2017 | 23.25 lakh | 2. | 30-March-2017 | 45.79 lakh | 3. | 31-March-2017 | 10.00 lakh | 4. | 25-May-2017 | 38.01 lakh | 5. | 24-June-2017 | 40.29 lakh | 6. | 08-August-2017 | 86.53 lakh | 7. | 13-October-2017 | 68.85 lakh | 8. | 24-November-2017 | 12.60 lakh | 9. | 30-November-2017 | 38.15 lakh | 10. | 29-December-2017 | 47.28 lakh | 11. | 31-January-2018 | 44.85 lakh | 12. | 06-March-2018 | 20.00 lakh | 13. | 28-March-2018 | 31.31 lakh | 14. | 28-April-2018 | 26.14 lakh | 15. | 31-May-2018 | 32.76 lakh | 16. | 08-August-2018 | 23.23 lakh | 17. | 09-August-2018 | 58.98 lakh | 18. | 28-September-2018 | 20.61 lakh | 19. | 31-October-2018 | 41.84 lakh | 20. | 29-November-2018 | 14.38 lakh | 21. | 29-December-2018 | 22.69 lakh | 22. | 15-February-2019 | 50.74 lakh | 23. | 27-February-2019 | 28.15 lakh | 24. | 30-March-2019 | 19.55 lakh | 25. | 30-April-2019 | 21.05 lakh | 26. | 22-May-2019 | 9.18 lakh | 27. | 10-June-2019 | 17.61 lakh | 28. | 12-June-2019 | 14.36 lakh |
Total |
908.18 lakh |
% Payment |
102.65 % |
|
Advance Amount: 68.20 lakh
Recovered Amount: 68.20 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 1785 No. of Test Done : 1831 No. of Test Passed : 1789 No. of Test Failed : 42 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 97.98 |
Number of Notice(s) issued: 97 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 72 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 05-02-2019 | Main bridge | Erection {camber}work under progress . | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
2. | 07-01-2019 | Chepdo bridge | Erection work in progress at chepdo bridge | Ankit Kumar | JE | UDRP R&B Gopeshwar | See Pic |
3. | 07-01-2019 | Chepso bridge | Deck erection work in progress at chepdo bridge | Ankit Kumar | JE | UDRP R&B Gopeshwar | See Pic |
4. | 30-11-2018 | Chepdo bridge | Anchor cum towar M30 concrete work in progress for first lift above cable gallery | Ankit Kumar | JE | UDRP R&B Gopeshwar | See Pic |
5. | 25-09-2018 | Chepdo Bridge | CME Sir Visit Chepdo Bridge | Charu Upadhyay | QS | BSC R&B WB Chamoli | See Pic |
6. | 15-07-2018 | Chepdo Bridge | PCC of Wind Anchor 1 & Wind Anchor 4 Complete | Charu Upadhyay | QS | BSC R&B WB Chamoli | See Pic |
7. | 12-07-2018 | Chepdo Bridge | Excavation of Wind Anchor 1 is in progress | Charu Upadhyay | QS | BSC R&B WB Chamoli | See Pic |
8. | 23-06-2018 | Chepdo Bridge | Casting of wall A1 Anchor Cum Tower is in progress | Charu Upadhyay | QS | BSC R&B WB Chamoli | See Pic |
9. | 11-06-2018 | Chepdo Bridge | Wind Anchor completed A2 side at Chepdo Bridge | Charu Upadhyay | QS | BSC R&B WB Chamoli | See Pic |
10. | 11-06-2018 | Chepdo Bridge | Protection work is in progress at Chepdo Bridge | Charu Upadhyay | QS | BSC R&B WB Chamoli | See Pic |
11. | 04-04-2018 | At Abutment A1 side | CE sir visit and instructions given for balance work complete on time | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
12. | 16-02-2018 | Chepro Suspension bridge 120 m, UID no 9025 | Site inspection of Chapedo | Anurag Singh | TL | BSC R&B WB Rudraprayag | See Pic |
13. | 15-02-2018 | At BR-01 Laboratory | Checking of ESMF and laboratory equipments by DPM sir | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
14. | 15-02-2018 | At Abutment A2 side | Visit by DPM sir and instructions given for balance work to complete on time. | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
15. | 17-01-2018 | Chepdo bridge | Anchor cum towar M30 concrete work in progress for 2nd lift above deck slab at chepdo bridge | Ankit Kumar | JE | UDRP R&B Gopeshwar | See Pic |
16. | 10-01-2018 | Chepdo bridge | M30 concrete work in progress for anchor cum towar RHS 1st lift above deck slab
at chepdo bridge | Ankit Kumar | JE | UDRP R&B Gopeshwar | See Pic |
17. | 04-12-2017 | Chepdo Bridge | Reinforcement Binding work is in Progress for Top raft A2 Abutment | Charu Upadhyay | QS | BSC R&B WB Chamoli | See Pic |
18. | 02-12-2017 | Didsari bridge | Deck erection work is in progress at didsari in uttarkashi | Abhishek Tiwari | AE | UDRP AF SL&B Uttarkashi | See Pic |
19. | 29-11-2017 | Chepdo bridge | RHS Anchor cum towar M30 concrete work in progress for first lift above 4th slab at chepdo bridge | Ankit Kumar | JE | UDRP R&B Gopeshwar | See Pic |
20. | 18-11-2017 | Abutment cum anchor block A-1 side | Abutment cum anchor block A -1 side | Shivam Kumar | JE | UDRP R&B Karnprayag | See Pic |
|
|