Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Didsari Bridge Work Completed
Project: UDRP-RB UID: 4003 Sanction Cost: 1193.10  lakh Span: 100.000 M
District: Uttarkashi Block: Bhatwari Constituency: Gangotri Circle:
DEA: DEA Uttarkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: design Type: Bridge
Procurement:
Package No.: 504        Package Name:  UDRP/PWD/01/31/BR/04        Tender Date: 06-01-2015        Current Status: Agreement signed        Achieved on Date: 24-06-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/01/31/BR/04      Contractor Name: V. K. Gupta & Associates
Start Date:  01-07-2015      Intended Completion Date:  31-03-2018      Original End Date:  30-09-2016
Total Bond Cost: 63383025 (633.83 lakh)        Variation Cost: 50763755.77 (507.64 lakh)    Hence Total Bond Cost is   114146780.77 (1141.47 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 158460 for 5 days        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Other Allied Works & Finishing Work 1.00 Job101.7825-11-201531-03-20181.00 Job1.00 Job9.06101.78
2.Foundation RHS1.00 Job37.3925-11-201515-06-20171.00 Job1.00 Job3.3337.39
3.Foundation LHS1.00 Job39.4815-01-201615-06-20171.00 Job1.00 Job3.5139.48
4.Abutment Superstructure RHS1.00 Job87.1028-02-201631-12-20171.00 Job1.00 Job7.7587.10
5.Abutment Superstructure LHS1.00 Job104.0524-04-201620-05-20171.00 Job1.00 Job9.26104.05
6.Trestle Erection and Bracing of Trestle Tower LHS 4.00 job47.1720-05-201730-06-20174.00 job4.00 job4.247.17
7.Anchor Block Main Cable Reinforcement (3-4 Times) 1.00 job197.0818-04-201631-03-20171.00 job1.00 job17.54197.08
8.Anchor Block for Wind Cable: Reinforcement, Lewis 1.00 job90.8710-07-201631-05-20171.00 job1.00 job8.0990.87
9.Deck Cable laying, stretching and Fixing Transoms/Deck Slab 2.00 no18.9315-08-201715-12-20172.00 no2.00 no1.6918.93
10.Fixing of Saddle pulley along with Rib plate and 4.00 no6.5901-07-201715-07-20174.00 no4.00 no0.596.59
11.Main Cable Laying and Stretching 8.00 no83.8715-07-201714-08-20178.00 no8.00 no7.4783.87
12.Fixing Suspenders to Main cable with clamps and Ha130.00 no35.0116-08-201731-12-2017130.00 no130.00 no3.1235.01
13.Stretching Wind Guy cable, Fixing wind Ties with 68.00 m23.3101-01-201831-01-201868.00 m68.00 m2.0823.31
14.Fixing longitudinal Stringers/girders100.00 m36.5301-12-201731-12-2017100.00 m100.00 m3.2536.53
15.Fixing of chequered Plate/RCC Deck255.25 sqm16.8220-12-201715-01-2018255.25 sqm255.25 sqm1.516.82
16.Steel Railing/crush barrier207.00 m15.8901-02-201828-02-2018207.00 m207.00 m1.4115.89
17.Approach Ramp /path 126.00 m27.0115-12-201728-02-201870.00 m70.00 m2.427.01
18.Protection Work1.00 Job154.5002-05-201631-01-20181.00 Job1.00 Job13.75154.50
Total Amount: 1123.38 100   1123.38
Remarks: No Remarks       Work Program Made On: 17-06-2016        Updation of work program on: 25-11-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.22-December-20150.30  lakh
2.16-February-201686.81  lakh
3.22-March-201680.47  lakh
4.30-August-201636.13  lakh
5.31-August-2016112.47  lakh
6.03-October-201654.13  lakh
7.26-October-201640.71  lakh
8.06-January-201740.92  lakh
9.18-February-201742.37  lakh
10.30-March-2017205.78  lakh
11.17-June-2017107.91  lakh
12.23-August-201749.51  lakh
13.13-October-201746.41  lakh
14.08-November-201746.52  lakh
15.27-November-201751.00  lakh
16.23-December-20171.67  lakh
17.31-January-201846.18  lakh
18.31-March-201830.61  lakh
19.25-April-20184.38  lakh
20.29-August-20182.87  lakh
21.29-September-201856.31  lakh
22.15-July-20198.69  lakh
Total 1152.15  lakh
% Payment 100.95 %
Advance Amount:  232.12  lakh        Recovered Amount:  232.12  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 2553   No. of Test Done : 2514    No. of Test Passed : 2508   No. of Test Failed : 6   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 89.50
Number of Notice(s) issued: 106

Mobile Pic Upload

Number of Pics Available on Web Repository: 238
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.10-01-2019Naluna bridgeSE sir world bank New Tehri visit at Naluna bridge .Chandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
2.15-11-2018Naluna bridgeErection work of bridgeChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
3.07-05-2018Naluna Bridge (BR-03)Safety meeting conducted with Bridge Erection team.Manjunath NaikREDSC4 R&B WB Uttarkashi See Pic
4.07-04-2018DidsariS E sir visitChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
5.25-03-2018Didsari bridge, br-04site visit by E. E sir and R.E sirRohit KumarAssistant EngineerUDRP AF S&B Bageshwar See Pic
6.24-03-2018A1Deck inspectionNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
7.12-03-2018Didsari Bridge BR-04Routine Site visit with Executive EngineerManjunath NaikREDSC4 R&B WB Uttarkashi See Pic
8.25-02-2018Didsari Bridge (BR-04)Safety Meeting conducted with Labour and contractor's representative to create awareness of PPE requirements.Manjunath NaikREDSC4 R&B WB Uttarkashi See Pic
9.14-02-2018Approach road work in progressApproach road work is in progress at didsari bridgeAbhishek TiwariAEUDRP AF SL&B Uttarkashi See Pic
10.06-02-2018Didsari Bridge (BR-04)Arial view of newly constructed bridgeManjunath NaikREDSC4 R&B WB Uttarkashi See Pic
11.02-02-2018Didsari Bridge BR-08Inspection of DeckManjunath NaikREDSC4 R&B WB Uttarkashi See Pic
12.06-01-2018DidsariArial viewManjunath NaikREDSC4 R&B WB Uttarkashi See Pic
13.04-01-2018Deck work in progress at 100m span suspension bridge at Didsari, Uttarkashi.Deck work in progress.Manjunath NaikREDSC4 R&B WB Uttarkashi See Pic
14.02-01-2018Didsari bridgePainting work in progressChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
15.20-12-2017Didsari bridgeWind block w1, first slab concreting work is in progressRohit KumarAssistant EngineerUDRP AF S&B Bageshwar See Pic
16.18-12-2017Didsari bridgeDidsari bridge in progressChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
17.12-12-2017DidsariDeck work in progressManjunath NaikREDSC4 R&B WB Uttarkashi See Pic
18.12-12-2017DidsariConstruction anchor block right sideRamesh ChandEEUDRP R&B Uttarkashi See Pic
19.05-12-2017A1Erection work in progressNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
20.01-12-2017Didsari bridgeDeck Erection work in progressChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic