Didsari Bridge
Work Completed
|
Project: |
UDRP-RB |
UID: |
4003 |
Sanction Cost: |
1193.10 lakh |
Span:
|
100.000 M |
District: |
Uttarkashi |
Block: |
Bhatwari |
Constituency: |
Gangotri |
Circle: |
|
DEA: |
DEA Uttarkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
design |
Type: |
Bridge |
|
Procurement: |
Package No.: 504
Package Name: 
UDRP/PWD/01/31/BR/04
Tender Date: 06-01-2015
Current Status: Agreement signed
Achieved on Date: 24-06-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/01/31/BR/04
Contractor Name: V. K. Gupta & Associates
|
Start Date: 01-07-2015
Intended Completion Date: 31-03-2018
Original End Date: 30-09-2016 |
Total Bond Cost: 63383025 (633.83 lakh)
Variation Cost: 50763755.77 (507.64 lakh) Hence Total Bond Cost is 114146780.77 (1141.47 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 158460 for 5 days
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Other Allied Works & Finishing Work | 1.00 Job | 101.78 | 25-11-2015 | 31-03-2018 | 1.00 Job | 1.00 Job | 9.06 | 101.78 | 2. | Foundation RHS | 1.00 Job | 37.39 | 25-11-2015 | 15-06-2017 | 1.00 Job | 1.00 Job | 3.33 | 37.39 | 3. | Foundation LHS | 1.00 Job | 39.48 | 15-01-2016 | 15-06-2017 | 1.00 Job | 1.00 Job | 3.51 | 39.48 | 4. | Abutment Superstructure RHS | 1.00 Job | 87.10 | 28-02-2016 | 31-12-2017 | 1.00 Job | 1.00 Job | 7.75 | 87.10 | 5. | Abutment Superstructure LHS | 1.00 Job | 104.05 | 24-04-2016 | 20-05-2017 | 1.00 Job | 1.00 Job | 9.26 | 104.05 | 6. | Trestle Erection and Bracing of Trestle Tower LHS | 4.00 job | 47.17 | 20-05-2017 | 30-06-2017 | 4.00 job | 4.00 job | 4.2 | 47.17 | 7. | Anchor Block Main Cable Reinforcement (3-4 Times) | 1.00 job | 197.08 | 18-04-2016 | 31-03-2017 | 1.00 job | 1.00 job | 17.54 | 197.08 | 8. | Anchor Block for Wind Cable: Reinforcement, Lewis | 1.00 job | 90.87 | 10-07-2016 | 31-05-2017 | 1.00 job | 1.00 job | 8.09 | 90.87 | 9. | Deck Cable laying, stretching and Fixing Transoms/Deck Slab | 2.00 no | 18.93 | 15-08-2017 | 15-12-2017 | 2.00 no | 2.00 no | 1.69 | 18.93 | 10. | Fixing of Saddle pulley along with Rib plate and | 4.00 no | 6.59 | 01-07-2017 | 15-07-2017 | 4.00 no | 4.00 no | 0.59 | 6.59 | 11. | Main Cable Laying and Stretching | 8.00 no | 83.87 | 15-07-2017 | 14-08-2017 | 8.00 no | 8.00 no | 7.47 | 83.87 | 12. | Fixing Suspenders to Main cable with clamps and Ha | 130.00 no | 35.01 | 16-08-2017 | 31-12-2017 | 130.00 no | 130.00 no | 3.12 | 35.01 | 13. | Stretching Wind Guy cable, Fixing wind Ties with | 68.00 m | 23.31 | 01-01-2018 | 31-01-2018 | 68.00 m | 68.00 m | 2.08 | 23.31 | 14. | Fixing longitudinal Stringers/girders | 100.00 m | 36.53 | 01-12-2017 | 31-12-2017 | 100.00 m | 100.00 m | 3.25 | 36.53 | 15. | Fixing of chequered Plate/RCC Deck | 255.25 sqm | 16.82 | 20-12-2017 | 15-01-2018 | 255.25 sqm | 255.25 sqm | 1.5 | 16.82 | 16. | Steel Railing/crush barrier | 207.00 m | 15.89 | 01-02-2018 | 28-02-2018 | 207.00 m | 207.00 m | 1.41 | 15.89 | 17. | Approach Ramp /path | 126.00 m | 27.01 | 15-12-2017 | 28-02-2018 | 70.00 m | 70.00 m | 2.4 | 27.01 | 18. | Protection Work | 1.00 Job | 154.50 | 02-05-2016 | 31-01-2018 | 1.00 Job | 1.00 Job | 13.75 | 154.50 |
Total Amount: |
1123.38 |
|
100 |
1123.38 |
|
Remarks:
No Remarks
Work Program Made On:
17-06-2016 } ?>
Updation of work program on:
25-11-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 22-December-2015 | 0.30 lakh | 2. | 16-February-2016 | 86.81 lakh | 3. | 22-March-2016 | 80.47 lakh | 4. | 30-August-2016 | 36.13 lakh | 5. | 31-August-2016 | 112.47 lakh | 6. | 03-October-2016 | 54.13 lakh | 7. | 26-October-2016 | 40.71 lakh | 8. | 06-January-2017 | 40.92 lakh | 9. | 18-February-2017 | 42.37 lakh | 10. | 30-March-2017 | 205.78 lakh | 11. | 17-June-2017 | 107.91 lakh | 12. | 23-August-2017 | 49.51 lakh | 13. | 13-October-2017 | 46.41 lakh | 14. | 08-November-2017 | 46.52 lakh | 15. | 27-November-2017 | 51.00 lakh | 16. | 23-December-2017 | 1.67 lakh | 17. | 31-January-2018 | 46.18 lakh | 18. | 31-March-2018 | 30.61 lakh | 19. | 25-April-2018 | 4.38 lakh | 20. | 29-August-2018 | 2.87 lakh | 21. | 29-September-2018 | 56.31 lakh | 22. | 15-July-2019 | 8.69 lakh |
Total |
1152.15 lakh |
% Payment |
100.95 % |
|
Advance Amount: 232.12 lakh
Recovered Amount: 232.12 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 2553 No. of Test Done : 2514 No. of Test Passed : 2508 No. of Test Failed : 6 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 89.50 |
Number of Notice(s) issued: 106 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 238 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 10-01-2019 | Naluna bridge | SE sir world bank New Tehri visit at Naluna bridge . | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
2. | 15-11-2018 | Naluna bridge | Erection work of bridge | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
3. | 07-05-2018 | Naluna Bridge (BR-03) | Safety meeting conducted with Bridge Erection team. | Manjunath Naik | RE | DSC4 R&B WB Uttarkashi | See Pic |
4. | 07-04-2018 | Didsari | S E sir visit | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
5. | 25-03-2018 | Didsari bridge, br-04 | site visit by E. E sir and R.E sir | Rohit Kumar | Assistant Engineer | UDRP AF S&B Bageshwar | See Pic |
6. | 24-03-2018 | A1 | Deck inspection | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
7. | 12-03-2018 | Didsari Bridge BR-04 | Routine Site visit with Executive Engineer | Manjunath Naik | RE | DSC4 R&B WB Uttarkashi | See Pic |
8. | 25-02-2018 | Didsari Bridge (BR-04) | Safety Meeting conducted with Labour and contractor's representative to create awareness of PPE requirements. | Manjunath Naik | RE | DSC4 R&B WB Uttarkashi | See Pic |
9. | 14-02-2018 | Approach road work in progress | Approach road work is in progress at didsari bridge | Abhishek Tiwari | AE | UDRP AF SL&B Uttarkashi | See Pic |
10. | 06-02-2018 | Didsari Bridge (BR-04) | Arial view of newly constructed bridge | Manjunath Naik | RE | DSC4 R&B WB Uttarkashi | See Pic |
11. | 02-02-2018 | Didsari Bridge BR-08 | Inspection of Deck | Manjunath Naik | RE | DSC4 R&B WB Uttarkashi | See Pic |
12. | 06-01-2018 | Didsari | Arial view | Manjunath Naik | RE | DSC4 R&B WB Uttarkashi | See Pic |
13. | 04-01-2018 | Deck work in progress at 100m span suspension bridge at Didsari, Uttarkashi. | Deck work in progress. | Manjunath Naik | RE | DSC4 R&B WB Uttarkashi | See Pic |
14. | 02-01-2018 | Didsari bridge | Painting work in progress | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
15. | 20-12-2017 | Didsari bridge | Wind block w1, first slab concreting work is in progress | Rohit Kumar | Assistant Engineer | UDRP AF S&B Bageshwar | See Pic |
16. | 18-12-2017 | Didsari bridge | Didsari bridge in progress | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
17. | 12-12-2017 | Didsari | Deck work in progress | Manjunath Naik | RE | DSC4 R&B WB Uttarkashi | See Pic |
18. | 12-12-2017 | Didsari | Construction anchor block right side | Ramesh Chand | EE | UDRP R&B Uttarkashi | See Pic |
19. | 05-12-2017 | A1 | Erection work in progress | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
20. | 01-12-2017 | Didsari bridge | Deck Erection work in progress | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
|
|