Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Narayanbagar Bridge Work Completed
Project: UDRP-RB UID: 4001 Sanction Cost: 882.72  lakh Span: 90.000 M
District: Chamoli Block: unknown Constituency: unknown Circle:
DEA: DEA Karanprayag DSC: Yongma Engineering Co. Ltd. DSC Scope: design Type: Bridge
Procurement:
Package No.: 502        Package Name:  UDRP/PWD/02/37/BR/02        Tender Date: 11-09-2015        Current Status: Agreement signed        Achieved on Date: 02-02-2016

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/02/37/BR/02      Contractor Name: D S Construction
Start Date:  09-02-2016      Intended Completion Date:  21-04-2018      Original End Date:  08-05-2017
Total Bond Cost: 82419689.55 (824.2 lakh)        Variation Cost: 2525080.65 (25.25 lakh)    Hence Total Bond Cost is   84944770.2 (849.45 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 6263920 for +152 days        LD Analysis for Milestone2: calculated LD is Rs 7871110 for 191 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Env. Man & Moni Plan1.00 Job4.0101-04-201816-04-20181.00 Job1.00 Job0.454.01
2.Other Allied Works & Finishing Work 1.00 Job18.9801-12-201615-07-20171.00 Job1.00 Job2.1518.98
3.Foundation RHS1.00 Job83.5602-11-201628-02-20171.00 Job1.00 Job9.4883.56
4.Foundation LHS1.00 Job27.8515-11-201628-02-20171.00 Job1.00 Job3.1627.85
5.Abutment Superstructure RHS1.00 Job89.1301-03-201730-04-20171.00 Job1.00 Job10.1189.13
6.Abutment Superstructure LHS1.00 Job44.5602-11-201630-03-20171.00 Job1.00 Job5.0644.56
7.Trestle Erection and Bracing of Trestle Tower LHS 2.00 job46.9501-03-201720-04-20182.00 job2.00 job5.3346.95
8.Anchor Block Main Cable Reinforcement (3-4 Times) 2.00 job200.5401-12-201631-12-20172.00 job2.00 job22.75200.54
9.Anchor Block for Wind Cable: Reinforcement, Lewis 4.00 job111.4115-03-201731-12-20174.00 job4.00 job12.64111.41
10.Deck Cable laying, stretching and Fixing Transoms/Deck Slab 2.00 no4.3501-04-201810-04-20182.00 no2.00 no0.494.35
11.Fixing of Saddle pulley along with Rib plate and 4.00 no6.5910-01-201802-02-20184.00 no4.00 no0.756.59
12.Main Cable Laying and Stretching 8.00 no32.8202-02-201818-02-20188.00 no8.00 no3.7232.82
13.Fixing Suspenders to Main cable with clamps and Ha122.00 no2.2718-02-201828-02-2018122.00 no122.00 no0.262.27
14.Stretching Wind Guy cable, Fixing wind Ties with 439.00 m6.4501-03-201820-03-2018439.00 m439.00 m0.736.45
15.Fixing longitudinal Stringers/girders110.00 m37.7720-03-201830-03-2018110.00 m110.00 m4.2937.77
16.Fixing of chequered Plate/RCC Deck227.48 sqm11.3510-04-201820-04-2018227.48 sqm227.48 sqm1.2911.35
17.Steel Railing/crush barrier192.00 m2.7410-04-201820-04-2018192.00 m192.00 m0.312.74
18.Approach Ramp /path 100.00 m7.8121-11-201721-04-2018100.00 m100.00 m0.897.81
19.Protection Work2.00 Job142.2502-11-201621-04-20172.00 Job2.00 Job16.14142.25
Total Amount: 881.39 100   881.39
Remarks: No Remarks       Work Program Made On: 17-08-2016        Updation of work program on: 02-08-2019       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.16-June-201618.75  lakh
2.23-August-201630.90  lakh
3.30-September-201630.00  lakh
4.27-October-201645.90  lakh
5.23-December-201624.40  lakh
6.30-December-201653.13  lakh
7.08-March-201725.94  lakh
8.09-March-201761.91  lakh
9.30-March-201744.42  lakh
10.31-March-201727.00  lakh
11.25-May-201729.54  lakh
12.24-June-201725.82  lakh
13.13-October-2017105.55  lakh
14.16-October-201740.97  lakh
15.30-November-201751.29  lakh
16.29-December-201740.71  lakh
17.31-January-201860.11  lakh
18.28-February-201830.41  lakh
19.28-March-201817.87  lakh
20.22-June-201848.49  lakh
21.29-November-201847.79  lakh
22.13-February-201920.47  lakh
Total 881.37  lakh
% Payment 103.76 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 2109   No. of Test Done : 2152    No. of Test Passed : 2109   No. of Test Failed : 43   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 98.15
Number of Notice(s) issued: 82

Mobile Pic Upload

Number of Pics Available on Web Repository: 108
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.01-06-2018Narayanbagar BridgeChecking of Bridge for World Bank visitCharu UpadhyayQSBSC R&B WB Chamoli See Pic
2.07-04-2018At Narayanbagad civil hospitalGeneral health check up on occasion of World health weekRajan NautiyalJEUDRP R&B Chakrata See Pic
3.07-04-2018At Narayanbagad civil hospitalGeneral checkups of labour on world health week occasionRajan NautiyalJEUDRP R&B Chakrata See Pic
4.04-04-2018At Narayanbargh A1 sideVisit of CE sir and instructions given for balance work complete on timeRajan NautiyalJEUDRP R&B Chakrata See Pic
5.04-04-2018At Abutment A1 side NarayanbagadCE visit at Narayanbagad BR-02 and instructions given for complete work on timeRajan NautiyalJEUDRP R&B Chakrata See Pic
6.15-02-2018At Anchor block A1 sideChecking of Anchor girder by DPM sir found satisfactoryRajan NautiyalJEUDRP R&B Chakrata See Pic
7.15-02-2018At Abutment A1Checking of Site work by DPM sir and found satisfactoryRajan NautiyalJEUDRP R&B Chakrata See Pic
8.15-02-2018At Abutment A1 sideVisit by DPM sir and instructions given for balance work complete on time.Rajan NautiyalJEUDRP R&B Chakrata See Pic
9.15-02-2018At A1 sideStatus of Erection workRajan NautiyalJEUDRP R&B Chakrata See Pic
10.15-02-2018PaInspection of Narayan Bagar Suspension Bridge 95m UID no 9026 wite DPM Dayanand Sir,XEN Mr. R. Chauhan, RE RK Mishra,Site inspection of Narayan Bagar UID no 9026.DPM Dayanand Sir,Anurag SinghTLBSC R&B WB Rudraprayag See Pic
11.11-01-2018At A1 sideVisit of EE sir and instructions has given for balance workRajan NautiyalJEUDRP R&B Chakrata See Pic
12.24-12-2017At Abutment A1 side erection of Tower has been startedAbutment A1 side tower erection in progressRajan NautiyalJEUDRP R&B Chakrata See Pic
13.24-12-2017At Abutment A1 sideInformation board Grivence Number corrected as instructedRajan NautiyalJEUDRP R&B Chakrata See Pic
14.24-12-2017At Abutment A1Fixing of Tower base in progress at Abutment A1 side D/sRajan NautiyalJEUDRP R&B Chakrata See Pic
15.12-12-2017At A2 sideAbutment of A2 side completedRajan NautiyalJEUDRP R&B Chakrata See Pic
16.12-12-2017At Wind anchor A2 side D/sExcavation of wind Anchor in progress in hard rockRajan NautiyalJEUDRP R&B Chakrata See Pic
17.12-12-2017At Abutment A1Deck level checkingRajan NautiyalJEUDRP R&B Chakrata See Pic
18.12-12-2017At anchor A1Fixing of Anchor girder in progressRajan NautiyalJEUDRP R&B Chakrata See Pic
19.12-12-2017At Abutment A1 Casting completedAbutment A1 CompletedRajan NautiyalJEUDRP R&B Chakrata See Pic
20.07-12-2017Nara Jadoda Muzaffar NagarInspection of ground erection UID no 9026, suspension bridge NarayanbagarAnurag SinghTLBSC R&B WB Rudraprayag See Pic