Newgaon Sari Shrikalkhal Motor road phase 2
Work Completed
|
Project: |
UDRP-RB |
UID: |
3238 |
Sanction Cost: |
629.57 lakh |
Length:
|
10.000 KM. |
District: |
Uttarkashi |
Block: |
Dunda |
Constituency: |
Gangotri |
Circle: |
Tehri WB Circle |
DEA: |
DEA Uttarkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 31
Package Name: 
UDRP/PWD/01/30/RD/031
Tender Date: 14-08-2014
Current Status: Agreement signed
Achieved on Date: 24-03-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/01/30/RD/031
Contractor Name: Kailash Hillways Engineering Associates
|
Start Date: 31-03-2015
Intended Completion Date: 28-02-2018
Original End Date: 30-06-2016 |
Total Bond Cost: 54495078 (544.95 lakh)
Variation Cost: 5174099.05 (51.74 lakh) Hence Total Bond Cost is 59669177.05 (596.69 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 4168944 for +153 days
LD Analysis for Milestone2: calculated LD is Rs 7493200 for 275 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 9.00 KM | 8.80 | 01-06-2015 | 31-05-2017 | 9.00 KM | 9.00 KM | 1.33 | 8.80 | 2. | R/Wall, B/ Wall Type Protection works | 1400.00 m | 179.62 | 01-05-2015 | 26-01-2018 | 1400.00 m | 1400.00 m | 27.24 | 179.62 | 3. | GSB/RBI/G-1 | 9.00 KM | 70.16 | 01-06-2015 | 31-05-2016 | 9.00 KM | 9.00 KM | 10.64 | 70.16 | 4. | G-2 | 9.00 KM | 100.59 | 01-07-2015 | 15-08-2016 | 9.00 KM | 9.00 KM | 15.25 | 100.59 | 5. | G-3 | 9.00 KM | 52.90 | 01-09-2015 | 30-11-2016 | 9.00 KM | 9.00 KM | 8.02 | 52.90 | 6. | PC/CC i/c Prime Coat, Tack Coat | 9.72 KM | 136.94 | 01-03-2016 | 30-06-2017 | 9.72 KM | 9.72 KM | 20.76 | 136.94 | 7. | Cause Way | 0.00 No | 0.00 | 01-07-2015 | 15-09-2016 | 0.00 No | 0.00 No | 0 | 0.00 | 8. | Culverts/Scupper | 26.00 No | 64.52 | 01-05-2015 | 31-08-2016 | 26.00 No | 26.00 No | 9.78 | 64.52 | 9. | longitudinal Drain | 9500.00 m | 27.36 | 01-10-2015 | 15-12-2017 | 9500.00 m | 9500.00 m | 4.15 | 27.36 | 10. | Crash Barrier | 300.00 m | 6.00 | 15-09-2017 | 31-10-2017 | 300.00 m | 300.00 m | 0.91 | 6.00 | 11. | Parapet | 350.00 No | 6.48 | 01-01-2018 | 31-01-2018 | 350.00 No | 350.00 No | 0.98 | 6.48 | 12. | Road Furniture | 57.00 No | 1.78 | 10-01-2018 | 31-01-2018 | 57.00 No | 57.00 No | 0.27 | 1.78 | 13. | Env. Man & Moni Plan | 1.00 Job | 4.36 | 01-05-2016 | 31-01-2018 | 1.00 Job | 1.00 Job | 0.66 | 4.36 |
Total Amount: |
659.51 |
|
100 |
659.51 |
|
Remarks:
No Remarks
Work Program Made On:
16-05-2015 } ?>
Updation of work program on:
10-01-2018
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 26-September-2015 | 40.55 lakh | 2. | 16-February-2016 | 57.73 lakh | 3. | 30-March-2016 | 64.17 lakh | 4. | 29-June-2016 | 22.52 lakh | 5. | 03-October-2016 | 10.20 lakh | 6. | 13-October-2016 | 28.49 lakh | 7. | 14-October-2016 | 20.45 lakh | 8. | 26-October-2016 | 26.00 lakh | 9. | 09-December-2016 | 20.84 lakh | 10. | 19-May-2017 | 20.33 lakh | 11. | 17-June-2017 | 30.72 lakh | 12. | 30-June-2017 | 68.60 lakh | 13. | 13-October-2017 | 33.56 lakh | 14. | 27-November-2017 | 15.31 lakh | 15. | 23-December-2017 | 1.72 lakh | 16. | 17-February-2018 | 26.79 lakh | 17. | 27-February-2018 | 10.20 lakh | 18. | 31-March-2018 | 22.82 lakh | 19. | 31-May-2018 | 62.06 lakh | 20. | 15-July-2019 | 8.88 lakh |
Total |
591.94 lakh |
% Payment |
99.21 % |
|
Advance Amount: 132.46 lakh
Recovered Amount: 132.46 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 565 No. of Test Done : 708 No. of Test Passed : 677 No. of Test Failed : 31 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 87.78 |
Number of Notice(s) issued: 153 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 181 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 08-02-2018 | 5/25 | Visit to newgaon sari Shrikalkhal MR by SE sir | Ankit Kuriyal | JE | UDRP R&B Uttarkashi | See Pic |
2. | 08-01-2018 | 1/24 causeway | Causeway | Ankit Kuriyal | JE | UDRP R&B Uttarkashi | See Pic |
3. | 25-12-2017 | 0/10 | Breast wall in progress | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
4. | 25-12-2017 | 6/23 | Newgaon sari Shrikalkhal M/R B/W | Ankit Kuriyal | JE | UDRP R&B Uttarkashi | See Pic |
5. | 25-11-2017 | Ch. 0/15 | R/W in progress | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
6. | 24-10-2017 | 2/3 | KC drain work . Quality found good . | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
7. | 06-10-2017 | 1/27 | crush barrier | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
8. | 15-06-2017 | 7/5 | PC work in progress | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
9. | 13-06-2017 | 7/35 | PC work in progress | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
10. | 12-06-2017 | 8/2 | H.p bend .......proper weidth | Praveen Rana | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
11. | 12-06-2017 | 8/2-3 | PC work in progress | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
12. | 12-06-2017 | 8/1 | PC work | Ankit Kuriyal | JE | UDRP R&B Askot | See Pic |
13. | 02-06-2017 | 5/20 | SS 1 ......alll R s drum .... | Praveen Rana | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
14. | 26-05-2017 | 9/16 | P.c material temprature on site .... | Praveen Rana | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
15. | 26-05-2017 | 9/14 | PC work in progress | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
16. | 25-05-2017 | 9/20-19 | PC work in progress | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
17. | 24-05-2017 | 9/24 | Seal coat .......from shrikhaal khaal | Praveen Rana | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
18. | 24-05-2017 | 9/25 | Rolling for p.c | Praveen Rana | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
19. | 24-05-2017 | 9/26 | PC work | Ankit Kuriyal | JE | UDRP R&B Askot | See Pic |
20. | 23-05-2017 | 9/26-25 | PC work start | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
|
|