Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Newgaon Sari Shrikalkhal Motor road phase 2 Work Completed
Project: UDRP-RB UID: 3238 Sanction Cost: 629.57  lakh Length: 10.000 KM.
District: Uttarkashi Block: Dunda Constituency: Gangotri Circle: Tehri WB Circle
DEA: DEA Uttarkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision Type: VR
Procurement:
Package No.: 31        Package Name:  UDRP/PWD/01/30/RD/031        Tender Date: 14-08-2014        Current Status: Agreement signed        Achieved on Date: 24-03-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/01/30/RD/031      Contractor Name: Kailash Hillways Engineering Associates
Start Date:  31-03-2015      Intended Completion Date:  28-02-2018      Original End Date:  30-06-2016
Total Bond Cost: 54495078 (544.95 lakh)        Variation Cost: 5174099.05 (51.74 lakh)    Hence Total Bond Cost is   59669177.05 (596.69 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 4168944 for +153 days        LD Analysis for Milestone2: calculated LD is Rs 7493200 for 275 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence9.00 KM8.8001-06-201531-05-20179.00 KM9.00 KM1.338.80
2.R/Wall, B/ Wall Type Protection works1400.00 m179.6201-05-201526-01-20181400.00 m1400.00 m27.24179.62
3.GSB/RBI/G-19.00 KM70.1601-06-201531-05-20169.00 KM9.00 KM10.6470.16
4.G-29.00 KM100.5901-07-201515-08-20169.00 KM9.00 KM15.25100.59
5.G-39.00 KM52.9001-09-201530-11-20169.00 KM9.00 KM8.0252.90
6.PC/CC i/c Prime Coat, Tack Coat9.72 KM136.9401-03-201630-06-20179.72 KM9.72 KM20.76136.94
7.Cause Way0.00 No0.0001-07-201515-09-20160.00 No0.00 No00.00
8.Culverts/Scupper 26.00 No64.5201-05-201531-08-201626.00 No26.00 No9.7864.52
9.longitudinal Drain9500.00 m27.3601-10-201515-12-20179500.00 m9500.00 m4.1527.36
10.Crash Barrier300.00 m6.0015-09-201731-10-2017300.00 m300.00 m0.916.00
11.Parapet350.00 No6.4801-01-201831-01-2018350.00 No350.00 No0.986.48
12.Road Furniture57.00 No1.7810-01-201831-01-201857.00 No57.00 No0.271.78
13.Env. Man & Moni Plan1.00 Job4.3601-05-201631-01-20181.00 Job1.00 Job0.664.36
Total Amount: 659.51 100   659.51
Remarks: No Remarks       Work Program Made On: 16-05-2015        Updation of work program on: 10-01-2018       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.26-September-201540.55  lakh
2.16-February-201657.73  lakh
3.30-March-201664.17  lakh
4.29-June-201622.52  lakh
5.03-October-201610.20  lakh
6.13-October-201628.49  lakh
7.14-October-201620.45  lakh
8.26-October-201626.00  lakh
9.09-December-201620.84  lakh
10.19-May-201720.33  lakh
11.17-June-201730.72  lakh
12.30-June-201768.60  lakh
13.13-October-201733.56  lakh
14.27-November-201715.31  lakh
15.23-December-20171.72  lakh
16.17-February-201826.79  lakh
17.27-February-201810.20  lakh
18.31-March-201822.82  lakh
19.31-May-201862.06  lakh
20.15-July-20198.88  lakh
Total 591.94  lakh
% Payment 99.21 %
Advance Amount:  132.46  lakh        Recovered Amount:  132.46  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 565   No. of Test Done : 708    No. of Test Passed : 677   No. of Test Failed : 31   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 87.78
Number of Notice(s) issued: 153

Mobile Pic Upload

Number of Pics Available on Web Repository: 181
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.08-02-20185/25Visit to newgaon sari Shrikalkhal MR by SE sirAnkit KuriyalJEUDRP R&B Uttarkashi See Pic
2.08-01-20181/24 causewayCausewayAnkit KuriyalJEUDRP R&B Uttarkashi See Pic
3.25-12-20170/10Breast wall in progressChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
4.25-12-20176/23Newgaon sari Shrikalkhal M/R B/WAnkit KuriyalJEUDRP R&B Uttarkashi See Pic
5.25-11-2017Ch. 0/15R/W in progressNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
6.24-10-20172/3KC drain work . Quality found good .Chandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
7.06-10-20171/27crush barrierChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
8.15-06-20177/5PC work in progressChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
9.13-06-20177/35PC work in progressChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
10.12-06-20178/2H.p bend .......proper weidthPraveen RanaSite SupervisorDSC1 R&B WB Uttarkashi See Pic
11.12-06-20178/2-3PC work in progressChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
12.12-06-20178/1PC workAnkit KuriyalJEUDRP R&B Askot See Pic
13.02-06-20175/20SS 1 ......alll R s drum ....Praveen RanaSite SupervisorDSC1 R&B WB Uttarkashi See Pic
14.26-05-20179/16P.c material temprature on site ....Praveen RanaSite SupervisorDSC1 R&B WB Uttarkashi See Pic
15.26-05-20179/14PC work in progressChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
16.25-05-20179/20-19PC work in progressChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
17.24-05-20179/24Seal coat .......from shrikhaal khaalPraveen RanaSite SupervisorDSC1 R&B WB Uttarkashi See Pic
18.24-05-20179/25Rolling for p.cPraveen RanaSite SupervisorDSC1 R&B WB Uttarkashi See Pic
19.24-05-20179/26PC workAnkit KuriyalJEUDRP R&B Askot See Pic
20.23-05-20179/26-25PC work startChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic