Dunda Kurah Motor road Phase2
Work Completed
|
Project: |
UDRP-RB |
UID: |
3237 |
Sanction Cost: |
45.74 lakh |
Length:
|
0.750 KM. |
District: |
Uttarkashi |
Block: |
Dunda |
Constituency: |
Gangotri |
Circle: |
Tehri WB Circle |
DEA: |
DEA Uttarkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 32
Package Name: 
UDRP/PWD/01/30/RD/032
Tender Date: 21-10-2014
Current Status: Agreement signed
Achieved on Date: 03-06-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/01/30/RD/032
Contractor Name: Dilawar Singh Contractor
|
Start Date: 10-06-2015
Intended Completion Date: 17-11-2016
Original End Date: 09-09-2016 |
Total Bond Cost: 38718032.06 (387.18 lakh)
Variation Cost: 3263774.37 (32.64 lakh) Hence Total Bond Cost is 41981806.43 (419.82 lakh)
|
Sub Project Cost: 46.45 lakh
Variation Cost of Sub Project: -71683.93 (-0.72 lakh)
Total Sub Project Cost:
45.73 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 522693 for 27 days
LD Analysis for Milestone2: calculated LD is Rs 1684233 for 87 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | PC/CC i/c Prime Coat, Tack Coat | 0.75 KM | 9.90 | 01-10-2015 | 31-10-2016 | 0.75 KM | 0.75 KM | 23.46 | 9.90 | 2. | Culverts/Scupper | 6.00 No | 12.10 | 15-07-2015 | 31-01-2016 | 6.00 No | 6.00 No | 28.67 | 12.10 | 3. | longitudinal Drain | 600.00 m | 7.61 | 15-07-2015 | 29-02-2016 | 600.00 m | 600.00 m | 18.03 | 7.61 | 4. | Crash Barrier | 410.00 m | 9.38 | 01-11-2015 | 30-11-2015 | 410.00 m | 410.00 m | 22.23 | 9.38 | 5. | Parapet | 132.00 No | 2.85 | 01-12-2015 | 31-01-2016 | 132.00 No | 132.00 No | 6.75 | 2.85 | 6. | Road Furniture | 16.00 No | 0.36 | 01-10-2015 | 26-11-2016 | 16.00 No | 16.00 No | 0.85 | 0.36 |
Total Amount: |
42.2 |
|
100 |
42.2 |
|
Remarks:
No Remarks
Work Program Made On:
11-08-2015 } ?>
Updation of work program on:
20-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 26-September-2015 | 5.00 lakh | 2. | 28-October-2015 | 3.32 lakh | 3. | 18-February-2016 | 18.61 lakh | 4. | 29-March-2016 | 1.55 lakh | 5. | 22-June-2016 | 9.77 lakh | 6. | 24-September-2016 | 0.08 lakh | 7. | 24-March-2017 | 0.44 lakh | 8. | 30-June-2017 | 0.04 lakh | 9. | 23-December-2017 | 3.35 lakh | 10. | 16-May-2018 | 0.27 lakh | 11. | 08-June-2018 | 1.33 lakh | 12. | 29-August-2018 | 2.70 lakh |
Total |
46.46 lakh |
% Payment | 101.6 % |
|
Advance Amount: 60.61 lakh
Recovered Amount: 60.61 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 328 No. of Test Done : 380 No. of Test Passed : 361 No. of Test Failed : 19 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 88.52 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 88 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 20-10-2016 | 1/28 | Clean the patry and kc drain now | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
2. | 20-10-2016 | Ch 2/7 | PC work in progress | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
3. | 15-10-2016 | 1/28 | PC complete | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
4. | 13-10-2016 | 2/8 | temperature at laying found ok | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
5. | 13-10-2016 | 2/10 | Cleaning for PC work in progress ,labour do not have helmet jackets contractor has been instructed to privide | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
6. | 13-10-2016 | 1/28 | PC in progress | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
7. | 12-10-2016 | 1/35 | PC work | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
8. | 12-10-2016 | 3/3 | G3 checking | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
9. | 12-10-2016 | 1/37 | PC work | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
10. | 12-10-2016 | 2/0 | PC Work in progress | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
11. | 12-10-2016 | 1/28 | Maxwell for PC | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
12. | 10-10-2016 | 2/8 | PC work in progress | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
13. | 21-09-2016 | 2+200 | Site visit to asses the prepatory work for PC work | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
14. | 13-09-2016 | Km2 | Site visit with Ll andRE sir | Neeraj Pathak | QC | DSC1 R&B WB Uttarkashi | See Pic |
15. | 10-09-2016 | CH.2+200 | Assessing the progress and preparatory of works. | Sam Allen Matthews | TL | DSC1 R&B WB | See Pic |
16. | 29-03-2016 | 1/17 | concreting in bed block | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
17. | 28-03-2016 | 0/16,dhanari to pujargaon | Breast wall in progress | Arun Kumar Sharma | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
18. | 17-03-2016 | 0/19,dhanari to pujargaon | Abutment work in progress | Arun Kumar Sharma | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
19. | 15-03-2016 | 0/17,dhanari to pujargaon | Reinforcement for bed block | Arun Kumar Sharma | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
20. | 15-03-2016 | 0/17,dhanari to pujargaon | Concreting in bed block in progress | Arun Kumar Sharma | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
|
|