Paleta Khansi Motor Road Work Completed
Project: UDRP-RB UID: 3223 Sanction Cost: 257.15  lakh Length: 3.000 KM.
District: Uttarkashi Block: Naugaon Constituency: Purola Circle: Rudraprayag WB Circle
DEA: DEA Uttarkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 87        Package Name:  UDRP/PWD/01/34/RD/076        Tender Date: 29-12-2014        Current Status: Agreement signed        Achieved on Date: 23-06-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/01/34/RD/076      Contractor Name: Ram krishna Jayara
Start Date:  29-06-2015      Intended Completion Date:  09-06-2017      Original End Date:  28-09-2016
Total Bond Cost: 23675625.54 (236.76 lakh)        Variation Cost: 2974549.16 (29.75 lakh)    Hence Total Bond Cost is   26650174.7 (266.5 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 177570 for 15 days        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence3.00 KM31.0801-07-201531-03-20163.00 KM3.00 KM14.8431.08
2.R/Wall, B/ Wall Type Protection works1285.00 m72.1401-07-201531-03-20161285.00 m1285.00 m34.4572.14
3.G-23.00 KM30.5801-08-201515-06-20163.00 KM3.00 KM14.630.58
4.G-33.00 KM21.3701-11-201515-09-20163.00 KM3.00 KM10.2121.37
5.PC/CC i/c Prime Coat, Tack Coat3.00 KM34.7401-04-201631-10-20163.00 KM3.00 KM16.5934.74
6.Culverts/Scupper 9.00 No13.6001-09-201530-04-20169.00 No9.00 No6.513.60
7.longitudinal Drain3000.00 m5.2601-08-201515-09-20163000.00 m3000.00 m2.515.26
8.Crash Barrier0.00 m0.0001-05-201630-11-20160.00 m0.00 m00.00
9.Parapet0.00 No0.0001-01-201631-07-20160.00 No0.00 No00.00
10.Road Furniture13.00 No0.6201-03-201630-11-201613.00 No13.00 No0.30.62
Total Amount: 209.39 100   209.39
Remarks: No Remarks       Work Program Made On: 13-08-2015        Updation of work program on: 20-05-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.26-September-201530.54  lakh
2.30-September-20150.00  lakh
3.21-December-201518.67  lakh
4.21-January-20168.50  lakh
5.06-February-20160.06  lakh
6.26-February-20165.84  lakh
7.30-March-201645.97  lakh
8.06-May-201627.25  lakh
9.29-June-201619.54  lakh
10.13-October-201615.11  lakh
11.06-November-20160.84  lakh
12.16-December-201615.97  lakh
13.24-March-201725.41  lakh
14.19-May-201736.74  lakh
15.13-October-201712.45  lakh
16.08-December-20173.26  lakh
Total 266.15  lakh
% Payment 99.87 %
Advance Amount:  66.12  lakh        Recovered Amount:  66.12  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 210   No. of Test Done : 222    No. of Test Passed : 210   No. of Test Failed : 12   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 88.43
Number of Notice(s) issued: 102

Mobile Pic Upload

Number of Pics Available on Web Repository: 319
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.27-04-2017Binder Content Test of Premix Carpet at Ch- 0/9Primix carpet Binder content hence satisfactory as par specification limit Found 3.59 percentVijayraj SinghJEUDRP R&B Uttarkashi See Pic
2.26-04-2017Laying of Premix Carpet at Ch- 0/6Work in ProgressVijayraj SinghJEUDRP R&B Uttarkashi See Pic
3.26-04-2017Rolling of premix carpet at Ch- 0/5Work in ProgressVijayraj SinghJEUDRP R&B Uttarkashi See Pic
4.26-04-2017P.C. Work at Ch- 0/5Work in progressVijayraj SinghJEUDRP R&B Uttarkashi See Pic
5.26-04-2017Applying Prime Coat at Ch- 0/2Work in ProgressVijayraj SinghJEUDRP R&B Uttarkashi See Pic
6.24-04-2017Laying Premix Carpet at Ch-0/25Work in ProgressVijayraj SinghJEUDRP R&B Uttarkashi See Pic
7.24-04-2017Ch- 0/25H.P. bend at Ch- 0/25Vijayraj SinghJEUDRP R&B Uttarkashi See Pic
8.24-04-2017Seal Coat work at Ch- 0/26Work in ProgressVijayraj SinghJEUDRP R&B Uttarkashi See Pic
9.24-04-2017Appling Prime Coat at Ch- 0/24Work in ProgressVijayraj SinghJEUDRP R&B Uttarkashi See Pic
10.20-04-2017Laying seal coat at Ch- 0/39Work in ProgressVijayraj SinghJEUDRP R&B Uttarkashi See Pic
11.20-04-2017P.C. Work in Progress at Ch- 0/38P.C. Work in progressVijayraj SinghJEUDRP R&B Uttarkashi See Pic
12.20-04-2017Laying of P.C. at Ch- 1/24Work in ProgressVijayraj SinghJEUDRP R&B Uttarkashi See Pic
13.18-04-2017Applying Prime Coat at Ch- 1/18Work in progressVijayraj SinghJEUDRP R&B Uttarkashi See Pic
14.18-04-2017Rolling of P.C. at Ch- 1/23Rolling of P.C. work in progress.Vijayraj SinghJEUDRP R&B Uttarkashi See Pic
15.18-04-2017Laying of Premix Carpet at Ch- 1/14P.C. work in progressVijayraj SinghJEUDRP R&B Uttarkashi See Pic
16.18-04-2017Appling of Prime coat at Ch- 1/16Applying of Prime Coat.Vijayraj SinghJEUDRP R&B Uttarkashi See Pic
17.14-04-2017Laying Seal coat at Ch-1/3Work in ProgressVijayraj SinghJEUDRP R&B Uttarkashi See Pic
18.14-04-2017P.C. Thickness at Ch- 1/3Checking thickness of P.C. at Ch- 1/3 found 22mm.Vijayraj SinghJEUDRP R&B Uttarkashi See Pic
19.14-04-2017Laying and Rolling of Premix Carpet at Ch- 1/2 to 1/3Work in ProgressVijayraj SinghJEUDRP R&B Uttarkashi See Pic
20.14-04-2017Ch 1/3P.C. work in ProgressVijayraj SinghJEUDRP R&B Uttarkashi See Pic