Paleta Khansi Motor Road
Work Completed
|
Project: |
UDRP-RB |
UID: |
3223 |
Sanction Cost: |
257.15 lakh |
Length:
|
3.000 KM. |
District: |
Uttarkashi |
Block: |
Naugaon |
Constituency: |
Purola |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Uttarkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 87
Package Name: 
UDRP/PWD/01/34/RD/076
Tender Date: 29-12-2014
Current Status: Agreement signed
Achieved on Date: 23-06-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/01/34/RD/076
Contractor Name: Ram krishna Jayara
|
Start Date: 29-06-2015
Intended Completion Date: 09-06-2017
Original End Date: 28-09-2016 |
Total Bond Cost: 23675625.54 (236.76 lakh)
Variation Cost: 2974549.16 (29.75 lakh) Hence Total Bond Cost is 26650174.7 (266.5 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 177570 for 15 days
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 3.00 KM | 31.08 | 01-07-2015 | 31-03-2016 | 3.00 KM | 3.00 KM | 14.84 | 31.08 | 2. | R/Wall, B/ Wall Type Protection works | 1285.00 m | 72.14 | 01-07-2015 | 31-03-2016 | 1285.00 m | 1285.00 m | 34.45 | 72.14 | 3. | G-2 | 3.00 KM | 30.58 | 01-08-2015 | 15-06-2016 | 3.00 KM | 3.00 KM | 14.6 | 30.58 | 4. | G-3 | 3.00 KM | 21.37 | 01-11-2015 | 15-09-2016 | 3.00 KM | 3.00 KM | 10.21 | 21.37 | 5. | PC/CC i/c Prime Coat, Tack Coat | 3.00 KM | 34.74 | 01-04-2016 | 31-10-2016 | 3.00 KM | 3.00 KM | 16.59 | 34.74 | 6. | Culverts/Scupper | 9.00 No | 13.60 | 01-09-2015 | 30-04-2016 | 9.00 No | 9.00 No | 6.5 | 13.60 | 7. | longitudinal Drain | 3000.00 m | 5.26 | 01-08-2015 | 15-09-2016 | 3000.00 m | 3000.00 m | 2.51 | 5.26 | 8. | Crash Barrier | 0.00 m | 0.00 | 01-05-2016 | 30-11-2016 | 0.00 m | 0.00 m | 0 | 0.00 | 9. | Parapet | 0.00 No | 0.00 | 01-01-2016 | 31-07-2016 | 0.00 No | 0.00 No | 0 | 0.00 | 10. | Road Furniture | 13.00 No | 0.62 | 01-03-2016 | 30-11-2016 | 13.00 No | 13.00 No | 0.3 | 0.62 |
Total Amount: |
209.39 |
|
100 |
209.39 |
|
Remarks:
No Remarks
Work Program Made On:
13-08-2015 } ?>
Updation of work program on:
20-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 26-September-2015 | 30.54 lakh | 2. | 30-September-2015 | 0.00 lakh | 3. | 21-December-2015 | 18.67 lakh | 4. | 21-January-2016 | 8.50 lakh | 5. | 06-February-2016 | 0.06 lakh | 6. | 26-February-2016 | 5.84 lakh | 7. | 30-March-2016 | 45.97 lakh | 8. | 06-May-2016 | 27.25 lakh | 9. | 29-June-2016 | 19.54 lakh | 10. | 13-October-2016 | 15.11 lakh | 11. | 06-November-2016 | 0.84 lakh | 12. | 16-December-2016 | 15.97 lakh | 13. | 24-March-2017 | 25.41 lakh | 14. | 19-May-2017 | 36.74 lakh | 15. | 13-October-2017 | 12.45 lakh | 16. | 08-December-2017 | 3.26 lakh |
Total |
266.15 lakh |
% Payment |
99.87 % |
|
Advance Amount: 66.12 lakh
Recovered Amount: 66.12 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 210 No. of Test Done : 222 No. of Test Passed : 210 No. of Test Failed : 12 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 88.43 |
Number of Notice(s) issued: 102 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 319 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 27-04-2017 | Binder Content Test of Premix Carpet at Ch- 0/9 | Primix carpet Binder content hence satisfactory as par specification limit
Found 3.59 percent | Vijayraj Singh | JE | UDRP R&B Uttarkashi | See Pic |
2. | 26-04-2017 | Laying of Premix Carpet at Ch- 0/6 | Work in Progress | Vijayraj Singh | JE | UDRP R&B Uttarkashi | See Pic |
3. | 26-04-2017 | Rolling of premix carpet at Ch- 0/5 | Work in Progress | Vijayraj Singh | JE | UDRP R&B Uttarkashi | See Pic |
4. | 26-04-2017 | P.C. Work at Ch- 0/5 | Work in progress | Vijayraj Singh | JE | UDRP R&B Uttarkashi | See Pic |
5. | 26-04-2017 | Applying Prime Coat at Ch- 0/2 | Work in Progress | Vijayraj Singh | JE | UDRP R&B Uttarkashi | See Pic |
6. | 24-04-2017 | Laying Premix Carpet at Ch-0/25 | Work in Progress | Vijayraj Singh | JE | UDRP R&B Uttarkashi | See Pic |
7. | 24-04-2017 | Ch- 0/25 | H.P. bend at Ch- 0/25 | Vijayraj Singh | JE | UDRP R&B Uttarkashi | See Pic |
8. | 24-04-2017 | Seal Coat work at Ch- 0/26 | Work in Progress | Vijayraj Singh | JE | UDRP R&B Uttarkashi | See Pic |
9. | 24-04-2017 | Appling Prime Coat at Ch- 0/24 | Work in Progress | Vijayraj Singh | JE | UDRP R&B Uttarkashi | See Pic |
10. | 20-04-2017 | Laying seal coat at Ch- 0/39 | Work in Progress | Vijayraj Singh | JE | UDRP R&B Uttarkashi | See Pic |
11. | 20-04-2017 | P.C. Work in Progress at Ch- 0/38 | P.C. Work in progress | Vijayraj Singh | JE | UDRP R&B Uttarkashi | See Pic |
12. | 20-04-2017 | Laying of P.C. at Ch- 1/24 | Work in Progress | Vijayraj Singh | JE | UDRP R&B Uttarkashi | See Pic |
13. | 18-04-2017 | Applying Prime Coat at Ch- 1/18 | Work in progress | Vijayraj Singh | JE | UDRP R&B Uttarkashi | See Pic |
14. | 18-04-2017 | Rolling of P.C. at Ch- 1/23 | Rolling of P.C. work in progress. | Vijayraj Singh | JE | UDRP R&B Uttarkashi | See Pic |
15. | 18-04-2017 | Laying of Premix Carpet at Ch- 1/14 | P.C. work in progress | Vijayraj Singh | JE | UDRP R&B Uttarkashi | See Pic |
16. | 18-04-2017 | Appling of Prime coat at Ch- 1/16 | Applying of Prime Coat. | Vijayraj Singh | JE | UDRP R&B Uttarkashi | See Pic |
17. | 14-04-2017 | Laying Seal coat at Ch-1/3 | Work in Progress | Vijayraj Singh | JE | UDRP R&B Uttarkashi | See Pic |
18. | 14-04-2017 | P.C. Thickness at Ch- 1/3 | Checking thickness of P.C. at Ch- 1/3 found 22mm. | Vijayraj Singh | JE | UDRP R&B Uttarkashi | See Pic |
19. | 14-04-2017 | Laying and Rolling of Premix Carpet at Ch- 1/2 to 1/3 | Work in Progress | Vijayraj Singh | JE | UDRP R&B Uttarkashi | See Pic |
20. | 14-04-2017 | Ch 1/3 | P.C. work in Progress | Vijayraj Singh | JE | UDRP R&B Uttarkashi | See Pic |
|
|