Saura Sari Motor Road
Work Completed
|
Project: |
UDRP-RB |
UID: |
3206 |
Sanction Cost: |
257.07 lakh |
Length:
|
1.750 KM. |
District: |
Uttarkashi |
Block: |
Bhatwari |
Constituency: |
Gangotri |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Uttarkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 33
Package Name: 
UDRP/PWD/01/31/RD/033
Tender Date: 14-08-2014
Current Status: Agreement signed
Achieved on Date: 04-06-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/01/31/RD/033
Contractor Name: Arya Construction
|
Start Date: 11-06-2015
Intended Completion Date: 31-07-2017
Original End Date: 10-09-2016 |
Total Bond Cost: 30095179.78 (300.95 lakh)
Variation Cost: 12251575.02 (122.52 lakh) Hence Total Bond Cost is 42346754.8 (423.47 lakh)
|
Sub Project Cost: 132.39 lakh
Variation Cost of Sub Project: 10243423.12 (102.43 lakh)
Total Sub Project Cost:
234.82 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 1820808 for 121 days
LD Analysis for Milestone2: calculated LD is Rs 5567760 for 370 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 1.75 KM | 13.71 | 11-06-2015 | 31-07-2016 | 1.75 KM | 1.75 KM | 9.24 | 13.71 | 2. | R/Wall, B/ Wall Type Protection works | 628.00 m | 46.99 | 11-06-2015 | 15-06-2017 | 628.00 m | 628.00 m | 31.66 | 46.99 | 3. | GSB/RBI/G-1 | 1.65 KM | 11.41 | 01-08-2015 | 15-02-2017 | 1.65 KM | 1.65 KM | 7.69 | 11.41 | 4. | G-2 | 1.65 KM | 8.44 | 01-09-2015 | 15-06-2017 | 1.65 KM | 1.65 KM | 5.69 | 8.44 | 5. | G-3 | 1.65 KM | 8.95 | 01-03-2017 | 20-06-2017 | 1.65 KM | 1.65 KM | 6.03 | 8.95 | 6. | PC/CC i/c Prime Coat, Tack Coat | 1.65 KM | 20.73 | 01-05-2017 | 20-06-2017 | 1.65 KM | 1.65 KM | 13.97 | 20.73 | 7. | Cause Way | 4.00 No | 17.02 | 01-06-2016 | 15-06-2017 | 4.00 No | 4.00 No | 11.47 | 17.02 | 8. | Culverts/Scupper | 5.00 No | 14.51 | 01-10-2015 | 30-09-2016 | 5.00 No | 5.00 No | 9.78 | 14.51 | 9. | longitudinal Drain | 1600.00 m | 4.44 | 01-12-2015 | 15-07-2017 | 1600.00 m | 1600.00 m | 2.99 | 4.44 | 10. | Parapet | 40.00 No | 1.48 | 15-06-2017 | 15-07-2017 | 40.00 No | 40.00 No | 1 | 1.48 | 11. | Road Furniture | 30.00 No | 0.76 | 01-12-2015 | 20-06-2017 | 30.00 No | 30.00 No | 0.51 | 0.76 |
Total Amount: |
148.44 |
|
100 |
148.44 |
|
Remarks:
No Remarks
Work Program Made On:
11-08-2015 } ?>
Updation of work program on:
20-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 26-September-2015 | 7.00 lakh | 2. | 30-September-2015 | 5.15 lakh | 3. | 19-February-2016 | 16.10 lakh | 4. | 11-March-2016 | 11.08 lakh | 5. | 30-March-2016 | 3.19 lakh | 6. | 27-October-2016 | 5.43 lakh | 7. | 09-December-2016 | 5.88 lakh | 8. | 29-March-2017 | 7.63 lakh | 9. | 18-May-2017 | 5.98 lakh | 10. | 30-June-2017 | 31.57 lakh | 11. | 31-July-2017 | 33.08 lakh | 12. | 12-October-2017 | 33.13 lakh | 13. | 27-November-2017 | 20.15 lakh | 14. | 23-December-2017 | 0.58 lakh | 15. | 17-February-2018 | 36.69 lakh | 16. | 21-April-2018 | 5.27 lakh | 17. | 31-May-2018 | 10.72 lakh | 18. | 15-July-2019 | 7.35 lakh |
Total |
245.98 lakh |
% Payment | 104.75 % |
|
Advance Amount: 70.90 lakh
Recovered Amount: 70.90 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 281 No. of Test Done : 361 No. of Test Passed : 338 No. of Test Failed : 23 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 86.48 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 88 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 28-09-2017 | Ch 1/9 | Removing Defects in Plum work in progress | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
2. | 30-08-2017 | Ch0/27 | Rejected breast wall | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
3. | 30-08-2017 | Ch 0/30 | Soling rejected taken it as surface dressing | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
4. | 07-05-2017 | Ch 0/6 | Wire crate work on sinking wall portion | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
5. | 02-02-2017 | RENFORSMENT Checking in bed block km 0/23 | RENFORSMENT Checking in bed block work in progress | Sadhan Negi | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
6. | 24-01-2017 | Excavation in poundation for causeway | Work in progress | Sadhan Negi | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
7. | 15-01-2017 | 1/22 | Site visit with contractor regarding site work | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
8. | 11-01-2017 | Ch 1/23 | Causeway location | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
9. | 13-10-2016 | 0/8 | Site visit by SE new Tehri | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
10. | 02-10-2016 | Bended wall km 0/20 | Bended wall | Sadhan Negi | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
11. | 29-09-2016 | 0/14 | Drain excavation work in progress | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
12. | 28-08-2016 | 0/22 | culvert construction in progress | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
13. | 28-08-2016 | 0/4 | damage caused due to sinking of land | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
14. | 26-08-2016 | R/W 0/20 | R/W | Deepak Kumar 2 | JE | UDRP R&B Uttarkashi | See Pic |
15. | 26-08-2016 | 0/5 - 0/6 | R/w sink | Deepak Kumar 2 | JE | UDRP R&B Uttarkashi | See Pic |
16. | 22-08-2016 | Ch0/19 | Water flow In main carriageway | Neeraj Pathak | QC | DSC1 R&B WB Uttarkashi | See Pic |
17. | 22-08-2016 | Ch0/6 to 0/10 WBM G1 stock pile flaky is more than 30% instruction to contractor improve wbm g,1 quantity and recheck again | Re checking WBM g1 material than laying permission | Neeraj Pathak | QC | DSC1 R&B WB Uttarkashi | See Pic |
18. | 22-08-2016 | Ch0/6 | Sand stock pile for concrete works | Neeraj Pathak | QC | DSC1 R&B WB Uttarkashi | See Pic |
19. | 22-08-2016 | Ch0/4 | Slip cleaning | Neeraj Pathak | QC | DSC1 R&B WB Uttarkashi | See Pic |
20. | 03-08-2016 | Ch 0/20 | R/W in progress | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
|
|