Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Pipli to gawana Motor road Work Completed
Project: UDRP-RB UID: 3194 Sanction Cost: 179.94  lakh Length: 2.900 KM.
District: Uttarkashi Block: Dunda Constituency: Gangotri Circle: Rudraprayag WB Circle
DEA: DEA Uttarkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 61        Package Name:  UDRP/PWD/01/30/RD/032(a)        Tender Date: 13-02-2015        Current Status: Agreement signed        Achieved on Date: 07-07-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/01/30/RD/032(a)      Contractor Name: Bharat Construction
Start Date:  14-07-2015      Intended Completion Date:  28-02-2018      Original End Date:  13-10-2016
Total Bond Cost: 36258671.4 (362.59 lakh)        Variation Cost: -2116471.67 (-21.16 lakh)    Hence Total Bond Cost is   34142199.73 (341.42 lakh) 
Sub Project Cost: 152.47  lakh        Variation Cost of Sub Project: -2008167.94  (-20.08 lakh)       Total Sub Project Cost:   132.39 lakh
LD Analysis for Milestone1: calculated LD is Rs 1685997 for 93 days        LD Analysis for Milestone2: calculated LD is Rs 5583732 for 308 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.R/Wall, B/ Wall Type Protection works620.00 m41.1301-08-201515-06-2016620.00 m620.00 m23.5441.13
2.GSB/RBI/G-12.60 KM20.8501-10-201531-03-20162.60 KM2.60 KM11.9320.85
3.G-22.60 KM16.0901-12-201530-04-20162.60 KM2.60 KM9.2116.09
4.G-32.60 KM16.8901-01-201630-11-20162.60 KM2.60 KM9.6716.89
5.PC/CC i/c Prime Coat, Tack Coat2.80 KM48.5601-05-201630-11-20162.80 KM2.80 KM27.7948.56
6.Culverts/Scupper 16.00 No17.9301-08-201531-10-201516.00 No16.00 No10.2617.93
7.longitudinal Drain2800.00 m7.2701-01-201615-06-20172800.00 m2800.00 m4.167.27
8.Parapet120.00 No4.1815-02-201828-02-2018130.00 No130.00 No2.394.18
9.Road Furniture44.00 No1.8301-01-201831-01-201888.00 No88.00 No1.051.83
Total Amount: 174.73 100   174.73
Remarks: No Remarks       Work Program Made On: 11-08-2015        Updation of work program on: 06-03-2018       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.09-November-201517.71  lakh
2.26-November-20157.33  lakh
3.21-January-201621.45  lakh
4.14-March-20168.07  lakh
5.30-March-20169.85  lakh
6.26-October-201615.35  lakh
7.28-March-201773.54  lakh
8.31-March-20182.23  lakh
9.31-May-20183.94  lakh
Total 159.47  lakh
% Payment120.45 %
Advance Amount:  94.36  lakh        Recovered Amount:  94.36  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 220   No. of Test Done : 296    No. of Test Passed : 284   No. of Test Failed : 12   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 89.79
Number of Notice(s) issued: 1

Mobile Pic Upload

Number of Pics Available on Web Repository: 201
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.27-02-20170/32Patri compaction requiredPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
2.24-02-20170/30Third party test of PCChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
3.15-01-20172/34Patri dressing & compaction required but no labour found on sitePraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
4.20-11-20160/15PC work in progressChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
5.17-11-20160/34PC work in progressChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
6.15-11-20161/3Pc workChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
7.14-11-20162/30measurement for PC work in progressPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
8.14-11-20161/4Thickness checking for WBM workPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
9.14-11-20160/40temperature of bitumen at plant found okPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
10.13-11-20161/2PC work in progressChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
11.06-11-20161/29-28PC work in progressChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
12.05-11-20162/1PC work in progressChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
13.05-11-20160/39PlantChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
14.01-11-20162/1PC work in progressChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
15.31-10-2016PlantPlant at Pipli GawanaChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
16.28-10-20162/16PC work in progressChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
17.26-10-20162/32PC PC start at Pipli Gawana pkg 32a in UttarkashiChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
18.08-10-20162+925WBM checkingChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
19.05-10-2016Ch 1/2Sample for testing for screeningNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
20.21-09-20161/9Slip clearance requiredPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic