Pipli to gawana Motor road
Work Completed
|
Project: |
UDRP-RB |
UID: |
3194 |
Sanction Cost: |
179.94 lakh |
Length:
|
2.900 KM. |
District: |
Uttarkashi |
Block: |
Dunda |
Constituency: |
Gangotri |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Uttarkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 61
Package Name: 
UDRP/PWD/01/30/RD/032(a)
Tender Date: 13-02-2015
Current Status: Agreement signed
Achieved on Date: 07-07-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/01/30/RD/032(a)
Contractor Name: Bharat Construction
|
Start Date: 14-07-2015
Intended Completion Date: 28-02-2018
Original End Date: 13-10-2016 |
Total Bond Cost: 36258671.4 (362.59 lakh)
Variation Cost: -2116471.67 (-21.16 lakh) Hence Total Bond Cost is 34142199.73 (341.42 lakh)
|
Sub Project Cost: 152.47 lakh
Variation Cost of Sub Project: -2008167.94 (-20.08 lakh)
Total Sub Project Cost:
132.39 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 1685997 for 93 days
LD Analysis for Milestone2: calculated LD is Rs 5583732 for 308 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | R/Wall, B/ Wall Type Protection works | 620.00 m | 41.13 | 01-08-2015 | 15-06-2016 | 620.00 m | 620.00 m | 23.54 | 41.13 | 2. | GSB/RBI/G-1 | 2.60 KM | 20.85 | 01-10-2015 | 31-03-2016 | 2.60 KM | 2.60 KM | 11.93 | 20.85 | 3. | G-2 | 2.60 KM | 16.09 | 01-12-2015 | 30-04-2016 | 2.60 KM | 2.60 KM | 9.21 | 16.09 | 4. | G-3 | 2.60 KM | 16.89 | 01-01-2016 | 30-11-2016 | 2.60 KM | 2.60 KM | 9.67 | 16.89 | 5. | PC/CC i/c Prime Coat, Tack Coat | 2.80 KM | 48.56 | 01-05-2016 | 30-11-2016 | 2.80 KM | 2.80 KM | 27.79 | 48.56 | 6. | Culverts/Scupper | 16.00 No | 17.93 | 01-08-2015 | 31-10-2015 | 16.00 No | 16.00 No | 10.26 | 17.93 | 7. | longitudinal Drain | 2800.00 m | 7.27 | 01-01-2016 | 15-06-2017 | 2800.00 m | 2800.00 m | 4.16 | 7.27 | 8. | Parapet | 120.00 No | 4.18 | 15-02-2018 | 28-02-2018 | 130.00 No | 130.00 No | 2.39 | 4.18 | 9. | Road Furniture | 44.00 No | 1.83 | 01-01-2018 | 31-01-2018 | 88.00 No | 88.00 No | 1.05 | 1.83 |
Total Amount: |
174.73 |
|
100 |
174.73 |
|
Remarks:
No Remarks
Work Program Made On:
11-08-2015 } ?>
Updation of work program on:
06-03-2018
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 09-November-2015 | 17.71 lakh | 2. | 26-November-2015 | 7.33 lakh | 3. | 21-January-2016 | 21.45 lakh | 4. | 14-March-2016 | 8.07 lakh | 5. | 30-March-2016 | 9.85 lakh | 6. | 26-October-2016 | 15.35 lakh | 7. | 28-March-2017 | 73.54 lakh | 8. | 31-March-2018 | 2.23 lakh | 9. | 31-May-2018 | 3.94 lakh |
Total |
159.47 lakh |
% Payment | 120.45 % |
|
Advance Amount: 94.36 lakh
Recovered Amount: 94.36 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 220 No. of Test Done : 296 No. of Test Passed : 284 No. of Test Failed : 12 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 89.79 |
Number of Notice(s) issued: 1 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 201 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 27-02-2017 | 0/32 | Patri compaction required | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
2. | 24-02-2017 | 0/30 | Third party test of PC | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
3. | 15-01-2017 | 2/34 | Patri dressing & compaction required but no labour found on site | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
4. | 20-11-2016 | 0/15 | PC work in progress | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
5. | 17-11-2016 | 0/34 | PC work in progress | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
6. | 15-11-2016 | 1/3 | Pc work | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
7. | 14-11-2016 | 2/30 | measurement for PC work in progress | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
8. | 14-11-2016 | 1/4 | Thickness checking for WBM work | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
9. | 14-11-2016 | 0/40 | temperature of bitumen at plant found ok | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
10. | 13-11-2016 | 1/2 | PC work in progress | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
11. | 06-11-2016 | 1/29-28 | PC work in progress | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
12. | 05-11-2016 | 2/1 | PC work in progress | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
13. | 05-11-2016 | 0/39 | Plant | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
14. | 01-11-2016 | 2/1 | PC work in progress | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
15. | 31-10-2016 | Plant | Plant at Pipli Gawana | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
16. | 28-10-2016 | 2/16 | PC work in progress | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
17. | 26-10-2016 | 2/32 | PC PC start at Pipli Gawana pkg 32a in Uttarkashi | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
18. | 08-10-2016 | 2+925 | WBM checking | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
19. | 05-10-2016 | Ch 1/2 | Sample for testing for screening | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
20. | 21-09-2016 | 1/9 | Slip clearance required | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
|
|