Naugoan Suri Motor road
Work Completed
|
Project: |
UDRP-RB |
UID: |
3185 |
Sanction Cost: |
112.41 lakh |
Length:
|
7.000 KM. |
District: |
Uttarkashi |
Block: |
Naugaon |
Constituency: |
Purola |
Circle: |
Tehri WB Circle |
DEA: |
DEA Uttarkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 3
Package Name: 
UDRP/PWD/01/34/RD/003
Tender Date: 27-03-2014
Current Status: Agreement signed
Achieved on Date: 11-07-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/01/34/RD/003
Contractor Name: Ram krishna Jayara
|
Start Date: 18-07-2014
Intended Completion Date: 15-12-2015
Original End Date: 17-10-2015 |
Total Bond Cost: 13654413.89 (136.54 lakh)
Variation Cost: 3187196.74 (31.87 lakh) Hence Total Bond Cost is 16841610.63 (168.42 lakh)
|
Sub Project Cost: 119.77 lakh
Variation Cost of Sub Project: 2595183.39 (25.95 lakh)
Total Sub Project Cost:
145.72 lakh
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | R/Wall, B/ Wall Type Protection works | 380.00 m | 39.87 | 18-07-2014 | 30-04-2015 | 380.00 m | 380.00 m | 35.81 | 39.87 | 2. | GSB/RBI/G-1 | 1.35 KM | 9.58 | 01-06-2015 | 31-08-2015 | 1.35 KM | 1.35 KM | 8.6 | 9.58 | 3. | G-2 | 1.55 KM | 9.56 | 01-07-2015 | 31-08-2015 | 1.55 KM | 1.55 KM | 8.59 | 9.56 | 4. | G-3 | 1.55 KM | 11.30 | 16-07-2015 | 30-11-2015 | 1.55 KM | 1.55 KM | 10.15 | 11.30 | 5. | PC/CC i/c Prime Coat, Tack Coat | 1.55 KM | 20.35 | 01-10-2015 | 10-10-2015 | 1.55 KM | 1.55 KM | 18.28 | 20.35 | 6. | Cause Way | 2.00 No | 5.23 | 01-05-2015 | 15-12-2015 | 2.00 No | 2.00 No | 4.7 | 5.23 | 7. | longitudinal Drain | 2800.00 m | 15.25 | 01-04-2015 | 30-11-2015 | 2800.00 m | 2800.00 m | 13.7 | 15.25 | 8. | Road Furniture | 2.00 No | 0.20 | 15-03-2015 | 15-04-2015 | 2.00 No | 2.00 No | 0.18 | 0.20 |
Total Amount: |
111.34 |
|
100 |
111.34 |
|
Remarks:
No Remarks
Work Program Made On:
21-08-2014 } ?>
Updation of work program on:
22-07-2016
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 18-December-2014 | 1.76 lakh | 2. | 27-February-2015 | 13.75 lakh | 3. | 30-March-2015 | 14.50 lakh | 4. | 29-May-2015 | 5.30 lakh | 5. | 30-June-2015 | 3.93 lakh | 6. | 30-October-2015 | 13.06 lakh | 7. | 18-May-2016 | 14.17 lakh | 8. | 08-December-2017 | 6.97 lakh |
Total |
73.44 lakh |
% Payment | 50.4 % |
|
Advance Amount: 10.10 lakh
Recovered Amount: 10.10 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Bill sh
ould be issued | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 777 No. of Test Done : 777 No. of Test Passed : 767 No. of Test Failed : 10 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 86.27 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 219 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 15-12-2016 | 0.000- 3.850 | N.O.C. By Mr. Dinesh Dhobhal, Regarding disposal and clearance of earth by contractor. | Vijayraj Singh | JE | UDRP R&B Uttarkashi | See Pic |
2. | 04-10-2016 | 1+750 | Bush cleaning required before handing over process. | Sam Allen Matthews | TL | DSC1 R&B WB | See Pic |
3. | 14-05-2016 | 2/5 | KC Drain work in progress | Baru Singh | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
4. | 12-05-2016 | Km 1+200 | Laying and Rolling of WBM Grading -2 | Baru Singh | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
5. | 12-05-2016 | Km 0+300 | Plum block | Baru Singh | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
6. | 27-02-2016 | 0+300 | Layout of Box Culvert for Garh Dewal motor road | Baru Singh | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
7. | 27-02-2016 | 2/7 | KC drain | Baru Singh | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
8. | 02-01-2016 | CH 1/6 | Screening material | Maneesh Chauhan | JE | UDRP R&B Uttarkashi | See Pic |
9. | 30-12-2015 | Chainage 2/0 | Kc drain work in progress | Maneesh Chauhan | JE | UDRP R&B Uttarkashi | See Pic |
10. | 30-12-2015 | Chainage 2/5 | Kc drain work in progress | Maneesh Chauhan | JE | UDRP R&B Uttarkashi | See Pic |
11. | 30-12-2015 | Chainage 2/9 | Kc drain work in progress | Maneesh Chauhan | JE | UDRP R&B Uttarkashi | See Pic |
12. | 30-12-2015 | Chainage 2/6 | Kc drain work is complete | Maneesh Chauhan | JE | UDRP R&B Uttarkashi | See Pic |
13. | 10-12-2015 | 2/36 | Checking of G2 grading by CE during visit | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
14. | 05-12-2015 | Chainage 9/0 | Pc work is completed | Maneesh Chauhan | JE | UDRP R&B Uttarkashi | See Pic |
15. | 04-12-2015 | 2/28 | BH | Maneesh Chauhan | JE | UDRP R&B Uttarkashi | See Pic |
16. | 04-12-2015 | Chainage 9/0 | Test of binder content for PC | Maneesh Chauhan | JE | UDRP R&B Uttarkashi | See Pic |
17. | 04-12-2015 | G | G | Maneesh Chauhan | JE | UDRP R&B Uttarkashi | See Pic |
18. | 04-12-2015 | G | G | Maneesh Chauhan | JE | UDRP R&B Uttarkashi | See Pic |
19. | 04-12-2015 | G | H | Maneesh Chauhan | JE | UDRP R&B Uttarkashi | See Pic |
20. | 04-12-2015 | H | G | Maneesh Chauhan | JE | UDRP R&B Uttarkashi | See Pic |
|
|