Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Naugoan Suri Motor road Work Completed
Project: UDRP-RB UID: 3185 Sanction Cost: 112.41  lakh Length: 7.000 KM.
District: Uttarkashi Block: Naugaon Constituency: Purola Circle: Tehri WB Circle
DEA: DEA Uttarkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision Type: VR
Procurement:
Package No.: 3        Package Name:  UDRP/PWD/01/34/RD/003        Tender Date: 27-03-2014        Current Status: Agreement signed        Achieved on Date: 11-07-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/01/34/RD/003      Contractor Name: Ram krishna Jayara
Start Date:  18-07-2014      Intended Completion Date:  15-12-2015      Original End Date:  17-10-2015
Total Bond Cost: 13654413.89 (136.54 lakh)        Variation Cost: 3187196.74 (31.87 lakh)    Hence Total Bond Cost is   16841610.63 (168.42 lakh) 
Sub Project Cost: 119.77  lakh        Variation Cost of Sub Project: 2595183.39  (25.95 lakh)       Total Sub Project Cost:   145.72 lakh
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.R/Wall, B/ Wall Type Protection works380.00 m39.8718-07-201430-04-2015380.00 m380.00 m35.8139.87
2.GSB/RBI/G-11.35 KM9.5801-06-201531-08-20151.35 KM1.35 KM8.69.58
3.G-21.55 KM9.5601-07-201531-08-20151.55 KM1.55 KM8.599.56
4.G-31.55 KM11.3016-07-201530-11-20151.55 KM1.55 KM10.1511.30
5.PC/CC i/c Prime Coat, Tack Coat1.55 KM20.3501-10-201510-10-20151.55 KM1.55 KM18.2820.35
6.Cause Way2.00 No5.2301-05-201515-12-20152.00 No2.00 No4.75.23
7.longitudinal Drain2800.00 m15.2501-04-201530-11-20152800.00 m2800.00 m13.715.25
8.Road Furniture2.00 No0.2015-03-201515-04-20152.00 No2.00 No0.180.20
Total Amount: 111.34 100   111.34
Remarks: No Remarks       Work Program Made On: 21-08-2014        Updation of work program on: 22-07-2016       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.18-December-20141.76  lakh
2.27-February-201513.75  lakh
3.30-March-201514.50  lakh
4.29-May-20155.30  lakh
5.30-June-20153.93  lakh
6.30-October-201513.06  lakh
7.18-May-201614.17  lakh
8.08-December-20176.97  lakh
Total 73.44  lakh
% Payment50.4 %
Advance Amount:  10.10  lakh        Recovered Amount:  10.10  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 777   No. of Test Done : 777    No. of Test Passed : 767   No. of Test Failed : 10   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 86.27
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 219
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.15-12-20160.000- 3.850N.O.C. By Mr. Dinesh Dhobhal, Regarding disposal and clearance of earth by contractor.Vijayraj SinghJEUDRP R&B Uttarkashi See Pic
2.04-10-20161+750Bush cleaning required before handing over process.Sam Allen MatthewsTLDSC1 R&B WB See Pic
3.14-05-20162/5KC Drain work in progressBaru SinghSite SupervisorDSC1 R&B WB Uttarkashi See Pic
4.12-05-2016Km 1+200Laying and Rolling of WBM Grading -2Baru SinghSite SupervisorDSC1 R&B WB Uttarkashi See Pic
5.12-05-2016Km 0+300Plum blockBaru SinghSite SupervisorDSC1 R&B WB Uttarkashi See Pic
6.27-02-20160+300Layout of Box Culvert for Garh Dewal motor roadBaru SinghSite SupervisorDSC1 R&B WB Uttarkashi See Pic
7.27-02-20162/7KC drainBaru SinghSite SupervisorDSC1 R&B WB Uttarkashi See Pic
8.02-01-2016CH 1/6Screening materialManeesh ChauhanJEUDRP R&B Uttarkashi See Pic
9.30-12-2015Chainage 2/0Kc drain work in progressManeesh ChauhanJEUDRP R&B Uttarkashi See Pic
10.30-12-2015Chainage 2/5Kc drain work in progressManeesh ChauhanJEUDRP R&B Uttarkashi See Pic
11.30-12-2015Chainage 2/9Kc drain work in progressManeesh ChauhanJEUDRP R&B Uttarkashi See Pic
12.30-12-2015Chainage 2/6Kc drain work is completeManeesh ChauhanJEUDRP R&B Uttarkashi See Pic
13.10-12-20152/36Checking of G2 grading by CE during visitPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
14.05-12-2015Chainage 9/0Pc work is completedManeesh ChauhanJEUDRP R&B Uttarkashi See Pic
15.04-12-20152/28BHManeesh ChauhanJEUDRP R&B Uttarkashi See Pic
16.04-12-2015Chainage 9/0Test of binder content for PCManeesh ChauhanJEUDRP R&B Uttarkashi See Pic
17.04-12-2015GGManeesh ChauhanJEUDRP R&B Uttarkashi See Pic
18.04-12-2015GGManeesh ChauhanJEUDRP R&B Uttarkashi See Pic
19.04-12-2015GHManeesh ChauhanJEUDRP R&B Uttarkashi See Pic
20.04-12-2015HGManeesh ChauhanJEUDRP R&B Uttarkashi See Pic