Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Nakuri Singoth Motor road Work Completed
Project: UDRP-RB UID: 3183 Sanction Cost: 35.30  lakh Length: 6.000 KM.
District: Uttarkashi Block: Dunda Constituency: Gangotri Circle: Rudraprayag WB Circle
DEA: DEA Uttarkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision Type: VR
Procurement:
Package No.: 2        Package Name:  UDRP/PWD/01/30/RD/002        Tender Date: 20-11-2014        Current Status: Agreement signed        Achieved on Date: 03-06-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/01/30/RD/002      Contractor Name: Vinod Kumar Chauhan
Start Date:  10-06-2015      Intended Completion Date:  09-09-2016     
Total Bond Cost: 18394419.74 (183.94 lakh)        Variation Cost: 1403503.13 (14.04 lakh)    Hence Total Bond Cost is   19797922.87 (197.98 lakh) 
Sub Project Cost: 183.94  lakh        Variation Cost of Sub Project: 488755.26  (4.89 lakh)       Total Sub Project Cost:   188.83 lakh
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence4.00 KM0.6816-09-201515-10-20154.00 KM4.00 KM1.690.68
2.R/Wall, B/ Wall Type Protection works219.00 m35.5010-07-201531-08-2015219.00 m219.00 m87.7635.50
3.Cause Way1.00 No1.1101-09-201530-09-20151.00 No1.00 No2.751.11
4.Road Furniture2.00 No2.6710-06-201515-07-20152.00 No2.00 No6.62.67
5.Env. Man & Moni Plan1.00 Job0.4810-06-201509-09-20161.00 Job1.00 Job1.20.48
Total Amount: 40.44 100   40.44
Remarks: No Remarks       Work Program Made On: 02-09-2015        Updation of work program on: 16-10-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.21-August-201518.26  lakh
2.26-September-20159.00  lakh
3.30-September-20151.37  lakh
4.13-October-20152.10  lakh
5.09-November-20151.11  lakh
6.22-June-20167.66  lakh
Total 39.5  lakh
% Payment20.92 %
Advance Amount:  10.20  lakh        Recovered Amount:  10.20  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 321   No. of Test Done : 321    No. of Test Passed : 319   No. of Test Failed : 2   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 90.00
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 64
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.10-07-2016Ch0/0Site visit with TL sirNeeraj PathakQCDSC1 R&B WB Uttarkashi See Pic
2.14-06-20164/27B wallChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
3.07-06-20164/20Retaining wallChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
4.01-06-2016Retaining wall Ley out km 4/22Retaining wallSadhan NegiSite SupervisorDSC1 R&B WB Uttarkashi See Pic
5.03-02-2016Slip recorded at Nakuri singot5/21Chandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
6.03-02-20164/38SlipChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
7.14-10-20150/0CC Pavement workPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
8.05-10-20153/10Breast wall completeChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
9.27-09-20150/0 nakuri singotCauswayChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
10.06-09-20152/3-4Retaining wall completeChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
11.06-09-2015Nakhuri singoth,2/24,25breast wall completed at chaingae 2/24,25Arun Kumar SharmaSite SupervisorDSC1 R&B WB Uttarkashi See Pic
12.06-09-20150/24-25B wall completeChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
13.06-09-20150/25-26 breast Wall completeB wall completeChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
14.06-09-20154/33Nakuri singot motor road plum and r R wallChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
15.22-08-2015Chainage 0.300Visit of EE sirChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
16.17-08-2015Retaining wall km 4/33Retaining wall work in progressSadhan NegiSite SupervisorDSC1 R&B WB Uttarkashi See Pic
17.17-08-2015Site labCube testNeeraj PathakQCDSC1 R&B WB Uttarkashi See Pic
18.17-08-2015Site lab at pkg 002Cube testNeeraj PathakQCDSC1 R&B WB Uttarkashi See Pic
19.17-08-2015Site lab at pkg 002Cube testingNeeraj PathakQCDSC1 R&B WB Uttarkashi See Pic
20.17-08-2015Site lab pkg 002Cube test preparationNeeraj PathakQCDSC1 R&B WB Uttarkashi See Pic