Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Ghanrali Pul to sarbadiyar motor road Work Completed
Project: UDRP-RB UID: 3154 Sanction Cost: 40.37  lakh Length: 2.500 KM.
District: Uttarkashi Block: Naugaon Constituency: Yamunotri Circle: Tehri WB Circle
DEA: DEA Uttarkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision Type: VR
Procurement:
Package No.: 3        Package Name:  UDRP/PWD/01/34/RD/003        Tender Date: 27-03-2014        Current Status: Agreement signed        Achieved on Date: 11-07-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/01/34/RD/003      Contractor Name: Ram krishna Jayara
Start Date:  18-07-2014      Intended Completion Date:  15-12-2015      Original End Date:  17-10-2015
Total Bond Cost: 13654413.89 (136.54 lakh)        Variation Cost: 3187196.74 (31.87 lakh)    Hence Total Bond Cost is   16841610.63 (168.42 lakh) 
Sub Project Cost: 40.83  lakh        Variation Cost of Sub Project: 64529.77  (0.65 lakh)       Total Sub Project Cost:   41.48 lakh
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.R/Wall, B/ Wall Type Protection works424.00 m16.5618-08-201417-11-2014424.00 m424.00 m39.2716.56
2.Culverts/Scupper 1.00 No7.4918-07-201417-10-20141.00 No1.00 No17.767.49
3.longitudinal Drain2500.00 m17.9101-04-201530-06-20152500.00 m2500.00 m42.4717.91
4.Road Furniture2.00 No0.2115-03-201515-05-20152.00 No2.00 No0.50.21
Total Amount: 42.17 100   42.17
Remarks: No Remarks       Work Program Made On: 21-08-2014        Updation of work program on: 22-07-2016       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.18-December-201412.60  lakh
2.27-February-20153.12  lakh
3.30-March-20151.65  lakh
4.29-May-201514.88  lakh
5.30-June-20158.09  lakh
6.18-May-20160.14  lakh
7.08-December-20171.60  lakh
8.09-February-20180.30  lakh
Total 42.38  lakh
% Payment102.17 %
Advance Amount:  10.10  lakh        Recovered Amount:  10.10  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 777   No. of Test Done : 777    No. of Test Passed : 767   No. of Test Failed : 10   Test report of this package      * Tests Information is at package level not sub project level
Quality ranking not done.
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 27
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.26-01-2015Ch/027/0/28R/wall in progNeeraj PathakQCDSC1 R&B WB Uttarkashi See Pic
2.22-01-2015CH/0/27 to0/28R.wall on progNeeraj PathakQCDSC1 R&B WB Uttarkashi See Pic
3.22-01-2015CH/0/20Joint checkingNeeraj PathakQCDSC1 R&B WB Uttarkashi See Pic
4.21-01-2015Ch0/27Joint checkingNeeraj PathakQCDSC1 R&B WB Uttarkashi See Pic
5.21-01-20150/2Joint checkingNeeraj PathakQCDSC1 R&B WB Uttarkashi See Pic
6.13-01-2015Retaining wall 0/28Work progressSadhan NegiSite SupervisorDSC1 R&B WB Uttarkashi See Pic
7.26-11-2014Km 0/27 culvert Gagrali sirbadiyarWork progressSadhan NegiSite SupervisorDSC1 R&B WB Uttarkashi See Pic
8.22-11-2014Gagradi to Sarbdiyar/ km 0/27Work in progressBaru SinghSite SupervisorDSC1 R&B WB Uttarkashi See Pic
9.22-11-2014Gagradi to Sarbdiyar/ 0/27Work in progressBaru SinghSite SupervisorDSC1 R&B WB Uttarkashi See Pic
10.22-11-2014Gagradi to Sarbdiyar / 0/27Work in progressBaru SinghSite SupervisorDSC1 R&B WB Uttarkashi See Pic
11.22-11-2014Gagradi to Sarbdiyar/ 0/27Work in progressBaru SinghSite SupervisorDSC1 R&B WB Uttarkashi See Pic
12.22-11-2014Gagradi to Sarbdiya road / km 0/27Work in progressBaru SinghSite SupervisorDSC1 R&B WB Uttarkashi See Pic
13.22-11-2014WfcjkSadhan NegiSite SupervisorDSC1 R&B WB Uttarkashi See Pic
14.21-11-2014CH:0/27Curring work in progressNeeraj PathakQCDSC1 R&B WB Uttarkashi See Pic
15.20-11-2014Km 0/27Work in progressSadhan NegiSite SupervisorDSC1 R&B WB Uttarkashi See Pic
16.19-11-2014CH!0/27Work in progressNeeraj PathakQCDSC1 R&B WB Uttarkashi See Pic
17.19-11-2014CH:0/27Work in progressNeeraj PathakQCDSC1 R&B WB Uttarkashi See Pic
18.17-11-2014Gagrali to Sarbdiyar motor road KM-0/27Calvert work progressSadhan NegiSite SupervisorDSC1 R&B WB Uttarkashi See Pic
19.17-11-2014KM-0/27 Calwat C, C Work progressWork progressSadhan NegiSite SupervisorDSC1 R&B WB Uttarkashi See Pic
20.16-11-2014Km0/27 Gagrali to Sarbdiyar motor roadR/W wallSadhan NegiSite SupervisorDSC1 R&B WB Uttarkashi See Pic