Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Gagnani Motor Pull to Bhangeli Motor Road Work Completed
Project: UDRP-RB UID: 3151 Sanction Cost: 474.13  lakh Length: 4.600 KM.
District: Uttarkashi Block: Bhatwari Constituency: Gangotri Circle: Rudraprayag WB Circle
DEA: DEA Uttarkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 83        Package Name:  UDRP/PWD/01/31/RD/072        Tender Date: 29-12-2014        Current Status: Agreement signed        Achieved on Date: 04-06-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/01/31/RD/072      Contractor Name: Seema Construction Company
Start Date:  11-06-2015      Intended Completion Date:  20-06-2017      Original End Date:  10-09-2016
Total Bond Cost: 42946810.39 (429.47 lakh)        Variation Cost: 4223665.86 (42.24 lakh)    Hence Total Bond Cost is   47170476.25 (471.7 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 2104354 for 98 days        LD Analysis for Milestone2: calculated LD is Rs 4509330 for 210 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence4.60 KM32.6411-06-201515-04-20164.60 KM4.60 KM7.4532.64
2.R/Wall, B/ Wall Type Protection works2965.00 m158.2811-06-201515-06-20172965.00 m2965.00 m36.13158.28
3.G-24.60 KM63.8601-07-201531-03-20174.60 KM4.60 KM14.5863.86
4.G-34.60 KM33.9601-10-201531-03-20174.60 KM4.60 KM7.7533.96
5.PC/CC i/c Prime Coat, Tack Coat4.60 KM57.1101-04-201710-06-20174.60 KM4.60 KM13.0457.11
6.Cause Way1.00 No34.6501-06-201715-06-20171.00 No1.00 No7.9134.65
7.Culverts/Scupper 7.00 No30.9601-08-201531-03-20167.00 No7.00 No7.0730.96
8.longitudinal Drain2500.00 m13.1501-08-201515-06-20172500.00 m2500.00 m313.15
9.Crash Barrier200.00 m0.4801-06-201718-06-2017200.00 m200.00 m0.110.48
10.Parapet267.00 No11.7825-03-201715-06-2017267.00 No267.00 No2.6911.78
11.Road Furniture39.00 No1.2001-05-201620-06-201739.00 No39.00 No0.271.20
Total Amount: 438.07 100   438.07
Remarks: No Remarks       Work Program Made On: 11-08-2015        Updation of work program on: 30-06-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.26-September-201512.00  lakh
2.30-September-20158.24  lakh
3.19-December-20150.03  lakh
4.21-January-201629.59  lakh
5.19-February-201639.76  lakh
6.30-March-201610.06  lakh
7.25-April-201624.92  lakh
8.13-July-201640.18  lakh
9.26-October-201645.30  lakh
10.31-January-201737.41  lakh
11.18-May-201735.73  lakh
12.20-May-201721.38  lakh
13.30-June-201780.92  lakh
14.12-October-201717.21  lakh
15.13-October-201714.40  lakh
16.23-December-201725.75  lakh
17.31-January-201817.62  lakh
18.31-May-201810.57  lakh
Total 471.07  lakh
% Payment 99.85 %
Advance Amount:  96.82  lakh        Recovered Amount:  96.82  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 477   No. of Test Done : 535    No. of Test Passed : 511   No. of Test Failed : 24   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 92.72
Number of Notice(s) issued: 117

Mobile Pic Upload

Number of Pics Available on Web Repository: 154
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.28-09-2017Ch 1/30Road Damaged due to sinkingNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
2.28-09-2017Ch 3/20Slip at 3/20Naveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
3.30-08-2017Ch. 2/10Thickness Checking of PC found 22mm okNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
4.07-05-2017Ch 4/17P.c work in progressNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
5.21-04-2017Ch 3/18SE world bank tehri visitNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
6.23-01-20174/13Weep hole not found ,slop not proper in KC drain instructed to rectify the workPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
7.31-12-2016WBM G 2 km 1/18WBM G 2 work in progressSadhan NegiSite SupervisorDSC1 R&B WB Uttarkashi See Pic
8.21-12-2016Ch 4/6Crust checkingNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
9.12-12-2016WBM G. 3 KM 1/1 to 1/4WBM G. 3Sadhan NegiSite SupervisorDSC1 R&B WB Uttarkashi See Pic
10.12-12-2016WBM G.3 km 1/3WBM G.3Sadhan NegiSite SupervisorDSC1 R&B WB Uttarkashi See Pic
11.01-12-20161/20G2 grading stone collection in progressPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
12.24-11-2016WBM G. 2 km 1/21WBM G. 2Sadhan NegiSite SupervisorDSC1 R&B WB Uttarkashi See Pic
13.14-10-2016Site visit SE SIRSE SIR site visitSadhan NegiSite SupervisorDSC1 R&B WB Uttarkashi See Pic
14.13-10-20160/35inspection of sinking portion during site visit by SE New TehriPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
15.13-10-20164/18WBM gradation test on site found oversized rejected from 4/15 to 4/24Praveen GuptaREDSC1 R&B WB Uttarkashi See Pic
16.05-10-2016Ch 0/6Damages during monsoonNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
17.05-10-2016WBM G.3 km 4/10WBM G.3Sadhan NegiSite SupervisorDSC1 R&B WB Uttarkashi See Pic
18.05-10-2016Aiv testing km.4/11Aiv testingSadhan NegiSite SupervisorDSC1 R&B WB Uttarkashi See Pic
19.29-09-20164/2profile correction work in progressPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
20.29-09-20164/18G3 laying in progress material not found well graded instructed to rectifyPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic