Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

From Gangotri NH to ITBP Motor road Work Completed
Project: UDRP-RB UID: 3148 Sanction Cost: 15.55  lakh Length: 0.820 KM.
District: Uttarkashi Block: Dunda Constituency: Gangotri Circle: Rudraprayag WB Circle
DEA: DEA Uttarkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision Type: VR
Procurement:
Package No.: 2        Package Name:  UDRP/PWD/01/30/RD/002        Tender Date: 20-11-2014        Current Status: Agreement signed        Achieved on Date: 03-06-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/01/30/RD/002      Contractor Name: Vinod Kumar Chauhan
Start Date:  10-06-2015      Intended Completion Date:  09-09-2016     
Total Bond Cost: 18394419.74 (183.94 lakh)        Variation Cost: 1403503.13 (14.04 lakh)    Hence Total Bond Cost is   19797922.87 (197.98 lakh) 
Sub Project Cost: 10.00  lakh        Variation Cost of Sub Project: 603943.40  (6.04 lakh)       Total Sub Project Cost:   16.04 lakh
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.longitudinal Drain500.00 m15.3801-10-201531-10-2016500.00 m500.00 m95.3415.38
2.Road Furniture2.00 No0.2710-06-201509-09-20162.00 No2.00 No1.660.27
3.Env. Man & Moni Plan1.00 Job0.4810-06-201509-09-20161.00 Job1.00 Job30.48
Total Amount: 16.13 100   16.13
Remarks: No Remarks       Work Program Made On: 02-09-2015        Updation of work program on: 16-10-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.09-November-20155.57  lakh
2.19-February-20162.37  lakh
3.22-June-20166.58  lakh
Total 14.52  lakh
% Payment90.52 %
Advance Amount:  10.20  lakh        Recovered Amount:  10.20  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 321   No. of Test Done : 321    No. of Test Passed : 319   No. of Test Failed : 2   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 90.00
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 25
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.10-07-2016Km1Drain work completedNeeraj PathakQCDSC1 R&B WB Uttarkashi See Pic
2.19-05-20160+725Drain work in progressPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
3.18-05-2016Km1Drain work on progressNeeraj PathakQCDSC1 R&B WB Uttarkashi See Pic
4.17-05-2016DRAIN WORK m-20 km 0/650DRAIN WORK M -20Sadhan NegiSite SupervisorDSC1 R&B WB Uttarkashi See Pic
5.17-05-2016DRAIN WORK M -20DRAIN WORKSadhan NegiSite SupervisorDSC1 R&B WB Uttarkashi See Pic
6.17-05-2016DRAIN WORKDRAIN WORKSadhan NegiSite SupervisorDSC1 R&B WB Uttarkashi See Pic
7.16-05-2016DRAIN WORKDRAIN WORKSadhan NegiSite SupervisorDSC1 R&B WB Uttarkashi See Pic
8.16-05-2016700 metreU Type Drain in ProgressChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
9.14-05-2016DRAIN WORK M-20DRAIN WORK M-20Sadhan NegiSite SupervisorDSC1 R&B WB Uttarkashi See Pic
10.14-05-2016DRAIN WORKDRAIN WORKSadhan NegiSite SupervisorDSC1 R&B WB Uttarkashi See Pic
11.08-05-2016DRAIN WORKDRAIN WORKSadhan NegiSite SupervisorDSC1 R&B WB Uttarkashi See Pic
12.07-05-2016DRAIN WORKDRAIN WORKSadhan NegiSite SupervisorDSC1 R&B WB Uttarkashi See Pic
13.06-05-2016DRAIN WORK km o /25DRAIN WORKSadhan NegiSite SupervisorDSC1 R&B WB Uttarkashi See Pic
14.05-05-2016M-10 FOR DRAIN WORKDRAIN WORKSadhan NegiSite SupervisorDSC1 R&B WB Uttarkashi See Pic
15.01-05-2016Excavation in foundationExcavation in foundation for DrainSadhan NegiSite SupervisorDSC1 R&B WB Uttarkashi See Pic
16.28-04-2016NH to ITBP roadExcavation of kc drainChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
17.24-04-2016Near ITBP GateExcavation for drainChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
18.11-11-2015200 meterPakki naliChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
19.11-11-20150/32Pakki naliChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
20.03-11-2015Drina WORK in progressK.C drinSadhan NegiSite SupervisorDSC1 R&B WB Uttarkashi See Pic