Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Dunda Kurha Motor road Phase1 Work Completed
Project: UDRP-RB UID: 3146 Sanction Cost: 53.91  lakh Length: 2.000 KM.
District: Uttarkashi Block: Dunda Constituency: Gangotri Circle: Rudraprayag WB Circle
DEA: DEA Uttarkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision Type: VR
Procurement:
Package No.: 2        Package Name:  UDRP/PWD/01/30/RD/002        Tender Date: 20-11-2014        Current Status: Agreement signed        Achieved on Date: 03-06-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/01/30/RD/002      Contractor Name: Vinod Kumar Chauhan
Start Date:  10-06-2015      Intended Completion Date:  09-09-2016     
Total Bond Cost: 18394419.74 (183.94 lakh)        Variation Cost: 1403503.13 (14.04 lakh)    Hence Total Bond Cost is   19797922.87 (197.98 lakh) 
Sub Project Cost: 50.00  lakh        Variation Cost of Sub Project: 41799.32  (0.42 lakh)       Total Sub Project Cost:   50.42 lakh
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence1.50 KM0.0216-09-201515-10-20151.50 KM1.50 KM0.030.02
2.R/Wall, B/ Wall Type Protection works314.00 m28.4615-07-201530-09-2015314.00 m314.00 m53.7528.46
3.G-31.50 KM2.6601-09-201530-09-20151.50 KM1.50 KM5.032.66
4.PC/CC i/c Prime Coat, Tack Coat1.50 KM14.4101-10-201530-10-20151.50 KM1.50 KM27.2114.41
5.longitudinal Drain750.00 m6.6501-08-201515-08-2015750.00 m750.00 m12.566.65
6.Road Furniture2.00 No0.2710-06-201509-07-20152.00 No2.00 No0.50.27
7.Env. Man & Moni Plan1.00 Job0.4810-06-201509-09-20161.00 Job1.00 Job0.910.48
Total Amount: 52.95 100   52.95
Remarks: No Remarks       Work Program Made On: 05-08-2015        Updation of work program on: 16-10-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.21-August-20158.76  lakh
2.26-September-201510.00  lakh
3.30-September-20153.60  lakh
4.13-October-201512.90  lakh
5.09-November-201515.95  lakh
6.22-June-20161.78  lakh
Total 52.99  lakh
% Payment105.1 %
Advance Amount:  10.20  lakh        Recovered Amount:  10.20  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 321   No. of Test Done : 321    No. of Test Passed : 319   No. of Test Failed : 2   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 87.12
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 117
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.30-12-20160.525Road surface PC damaged due to blockage of the Pucca drain.Ashish AnthwalEnvironment SpecialistPIU UDRP R&B Dehradun See Pic
2.28-07-2016Ch3/29Wbm g1 thinkness checkingNeeraj PathakQCDSC1 R&B WB Uttarkashi See Pic
3.28-07-2016Ch3/28Wbm g2 laying on progressNeeraj PathakQCDSC1 R&B WB Uttarkashi See Pic
4.28-07-2016Km2 to 3WBM g2 material preparation at siteNeeraj PathakQCDSC1 R&B WB Uttarkashi See Pic
5.10-07-2016Km 2Site visit with TL sirNeeraj PathakQCDSC1 R&B WB Uttarkashi See Pic
6.14-06-20160/20Cooli wallChandra Lal BhartiJEUDRP R&B Uttarkashi See Pic
7.10-05-20160/18cleaning of KC drain and Patri dressing in progressPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
8.08-05-2016DRAIN WORKDRAIN WORKSadhan NegiSite SupervisorDSC1 R&B WB Uttarkashi See Pic
9.09-12-2015Ch0/37Site visitNeeraj PathakQCDSC1 R&B WB Uttarkashi See Pic
10.02-11-2015Cho/36 to 0/38Creash barrier work in progressNeeraj PathakQCDSC1 R&B WB Uttarkashi See Pic
11.31-10-20150/22P C laying work in progressPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
12.31-10-20150/25seal coat laying in progressPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
13.29-10-2015P.C WORK in progressP.C WORKSadhan NegiSite SupervisorDSC1 R&B WB Uttarkashi See Pic
14.29-10-2015P.C WORK in progress km 0/25P.C WORK in progressSadhan NegiSite SupervisorDSC1 R&B WB Uttarkashi See Pic
15.27-10-20150+550PC rolling workVipin Chandra BenjwalAEUDRP R&B Uttarkashi See Pic
16.27-10-20151/10p c work in progressPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
17.27-10-2015Ch0/18Pc laying on progressNeeraj PathakQCDSC1 R&B WB Uttarkashi See Pic
18.26-10-2015P.C.work in progressP.C.work in progressSadhan NegiSite SupervisorDSC1 R&B WB Uttarkashi See Pic
19.26-10-2015P.C.work in progress km 0/11P.C.work in progressSadhan NegiSite SupervisorDSC1 R&B WB Uttarkashi See Pic
20.26-10-2015P.C.work km 0/12P.C.workSadhan NegiSite SupervisorDSC1 R&B WB Uttarkashi See Pic