Dunda Kurha Motor road Phase1
Work Completed
|
Project: |
UDRP-RB |
UID: |
3146 |
Sanction Cost: |
53.91 lakh |
Length:
|
2.000 KM. |
District: |
Uttarkashi |
Block: |
Dunda |
Constituency: |
Gangotri |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Uttarkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 2
Package Name: 
UDRP/PWD/01/30/RD/002
Tender Date: 20-11-2014
Current Status: Agreement signed
Achieved on Date: 03-06-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/01/30/RD/002
Contractor Name: Vinod Kumar Chauhan
|
Start Date: 10-06-2015
Intended Completion Date: 09-09-2016
|
Total Bond Cost: 18394419.74 (183.94 lakh)
Variation Cost: 1403503.13 (14.04 lakh) Hence Total Bond Cost is 19797922.87 (197.98 lakh)
|
Sub Project Cost: 50.00 lakh
Variation Cost of Sub Project: 41799.32 (0.42 lakh)
Total Sub Project Cost:
50.42 lakh
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 1.50 KM | 0.02 | 16-09-2015 | 15-10-2015 | 1.50 KM | 1.50 KM | 0.03 | 0.02 | 2. | R/Wall, B/ Wall Type Protection works | 314.00 m | 28.46 | 15-07-2015 | 30-09-2015 | 314.00 m | 314.00 m | 53.75 | 28.46 | 3. | G-3 | 1.50 KM | 2.66 | 01-09-2015 | 30-09-2015 | 1.50 KM | 1.50 KM | 5.03 | 2.66 | 4. | PC/CC i/c Prime Coat, Tack Coat | 1.50 KM | 14.41 | 01-10-2015 | 30-10-2015 | 1.50 KM | 1.50 KM | 27.21 | 14.41 | 5. | longitudinal Drain | 750.00 m | 6.65 | 01-08-2015 | 15-08-2015 | 750.00 m | 750.00 m | 12.56 | 6.65 | 6. | Road Furniture | 2.00 No | 0.27 | 10-06-2015 | 09-07-2015 | 2.00 No | 2.00 No | 0.5 | 0.27 | 7. | Env. Man & Moni Plan | 1.00 Job | 0.48 | 10-06-2015 | 09-09-2016 | 1.00 Job | 1.00 Job | 0.91 | 0.48 |
Total Amount: |
52.95 |
|
100 |
52.95 |
|
Remarks:
No Remarks
Work Program Made On:
05-08-2015 } ?>
Updation of work program on:
16-10-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 21-August-2015 | 8.76 lakh | 2. | 26-September-2015 | 10.00 lakh | 3. | 30-September-2015 | 3.60 lakh | 4. | 13-October-2015 | 12.90 lakh | 5. | 09-November-2015 | 15.95 lakh | 6. | 22-June-2016 | 1.78 lakh |
Total |
52.99 lakh |
% Payment | 105.1 % |
|
Advance Amount: 10.20 lakh
Recovered Amount: 10.20 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 321 No. of Test Done : 321 No. of Test Passed : 319 No. of Test Failed : 2 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 87.12 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 117 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 30-12-2016 | 0.525 | Road surface PC damaged due to blockage of the Pucca drain. | Ashish Anthwal | Environment Specialist | PIU UDRP R&B Dehradun | See Pic |
2. | 28-07-2016 | Ch3/29 | Wbm g1 thinkness checking | Neeraj Pathak | QC | DSC1 R&B WB Uttarkashi | See Pic |
3. | 28-07-2016 | Ch3/28 | Wbm g2 laying on progress | Neeraj Pathak | QC | DSC1 R&B WB Uttarkashi | See Pic |
4. | 28-07-2016 | Km2 to 3 | WBM g2 material preparation at site | Neeraj Pathak | QC | DSC1 R&B WB Uttarkashi | See Pic |
5. | 10-07-2016 | Km 2 | Site visit with TL sir | Neeraj Pathak | QC | DSC1 R&B WB Uttarkashi | See Pic |
6. | 14-06-2016 | 0/20 | Cooli wall | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
7. | 10-05-2016 | 0/18 | cleaning of KC drain and Patri dressing in progress | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
8. | 08-05-2016 | DRAIN WORK | DRAIN WORK | Sadhan Negi | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
9. | 09-12-2015 | Ch0/37 | Site visit | Neeraj Pathak | QC | DSC1 R&B WB Uttarkashi | See Pic |
10. | 02-11-2015 | Cho/36 to 0/38 | Creash barrier work in progress | Neeraj Pathak | QC | DSC1 R&B WB Uttarkashi | See Pic |
11. | 31-10-2015 | 0/22 | P C laying work in progress | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
12. | 31-10-2015 | 0/25 | seal coat laying in progress | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
13. | 29-10-2015 | P.C WORK in progress | P.C WORK | Sadhan Negi | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
14. | 29-10-2015 | P.C WORK in progress km 0/25 | P.C WORK in progress | Sadhan Negi | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
15. | 27-10-2015 | 0+550 | PC rolling work | Vipin Chandra Benjwal | AE | UDRP R&B Uttarkashi | See Pic |
16. | 27-10-2015 | 1/10 | p c work in progress | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
17. | 27-10-2015 | Ch0/18 | Pc laying on progress | Neeraj Pathak | QC | DSC1 R&B WB Uttarkashi | See Pic |
18. | 26-10-2015 | P.C.work in progress | P.C.work in progress | Sadhan Negi | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
19. | 26-10-2015 | P.C.work in progress km 0/11 | P.C.work in progress | Sadhan Negi | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
20. | 26-10-2015 | P.C.work km 0/12 | P.C.work | Sadhan Negi | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
|
|