Dhanari Motor road to Pujargaon Motor road
Work Completed
|
Project: |
UDRP-RB |
UID: |
3137 |
Sanction Cost: |
182.65 lakh |
Length:
|
3.100 KM. |
District: |
Uttarkashi |
Block: |
Dunda |
Constituency: |
Gangotri |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Uttarkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 61
Package Name: 
UDRP/PWD/01/30/RD/032(a)
Tender Date: 13-02-2015
Current Status: Agreement signed
Achieved on Date: 07-07-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/01/30/RD/032(a)
Contractor Name: Bharat Construction
|
Start Date: 14-07-2015
Intended Completion Date: 28-02-2018
Original End Date: 13-10-2016 |
Total Bond Cost: 36258671.4 (362.59 lakh)
Variation Cost: -2116471.67 (-21.16 lakh) Hence Total Bond Cost is 34142199.73 (341.42 lakh)
|
Sub Project Cost: 156.95 lakh
Variation Cost of Sub Project: -108303.73 (-1.08 lakh)
Total Sub Project Cost:
155.87 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 1685997 for 93 days
LD Analysis for Milestone2: calculated LD is Rs 5583732 for 308 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 3.10 KM | 1.57 | 25-11-2017 | 15-12-2017 | 3.10 KM | 3.10 KM | 0.83 | 1.57 | 2. | R/Wall, B/ Wall Type Protection works | 838.00 m | 87.66 | 14-07-2015 | 15-12-2017 | 838.00 m | 838.00 m | 46.48 | 87.66 | 3. | GSB/RBI/G-1 | 1.00 KM | 8.02 | 01-02-2018 | 05-02-2018 | 0.50 KM | 0.50 KM | 4.25 | 8.02 | 4. | G-2 | 1.00 KM | 6.19 | 06-02-2018 | 10-02-2018 | 0.50 KM | 0.50 KM | 3.28 | 6.19 | 5. | G-3 | 1.60 KM | 10.40 | 11-02-2018 | 17-02-2018 | 1.00 KM | 1.00 KM | 5.52 | 10.40 | 6. | PC/CC i/c Prime Coat, Tack Coat | 3.10 KM | 51.92 | 25-11-2017 | 28-02-2018 | 3.10 KM | 3.10 KM | 27.53 | 51.92 | 7. | Culverts/Scupper | 5.00 No | 9.17 | 01-08-2015 | 20-05-2017 | 5.00 No | 5.00 No | 4.86 | 9.17 | 8. | longitudinal Drain | 3000.00 m | 7.53 | 15-05-2017 | 10-09-2017 | 3000.00 m | 3000.00 m | 3.99 | 7.53 | 9. | Parapet | 120.00 No | 4.03 | 15-05-2017 | 28-02-2018 | 130.00 No | 130.00 No | 2.14 | 4.03 | 10. | Road Furniture | 44.00 No | 2.09 | 15-02-2018 | 28-02-2018 | 88.00 No | 88.00 No | 1.11 | 2.09 |
Total Amount: |
188.58 |
|
100 |
188.58 |
|
Remarks:
No Remarks
Work Program Made On:
11-08-2015 } ?>
Updation of work program on:
28-03-2018
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 14-March-2016 | 16.65 lakh | 2. | 30-March-2016 | 5.11 lakh | 3. | 28-March-2017 | 11.76 lakh | 4. | 19-May-2017 | 16.00 lakh | 5. | 26-December-2017 | 15.00 lakh | 6. | 27-February-2018 | 51.26 lakh | 7. | 31-March-2018 | 38.09 lakh | 8. | 31-May-2018 | 27.22 lakh |
Total |
181.09 lakh |
% Payment | 116.18 % |
|
Advance Amount: 94.36 lakh
Recovered Amount: 94.36 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 220 No. of Test Done : 296 No. of Test Passed : 284 No. of Test Failed : 12 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 87.75 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 51 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 24-03-2018 | Ch 2/2 | P. C work in progress | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
2. | 25-12-2017 | 1/4 | PC work in progress | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
3. | 17-12-2017 | 3/4 | Dhanari Pujargaon motor road PC work Start now | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
4. | 14-03-2017 | 1/11-12 | Plum and wirecrate work | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
5. | 27-02-2017 | 1/12 | Protection work in B/wall in progress | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
6. | 27-02-2017 | 1/12 | Protection work in R/wall in progress | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
7. | 24-02-2017 | 1/20 | Plum and wire crate | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
8. | 15-01-2017 | 1/12 | Protection work in progress but no labour found on site | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
9. | 02-01-2017 | 1/12 | Plum work in progress | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
10. | 02-01-2017 | 1/12 | Plum casting work in progress | Vikas Vyas | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
11. | 29-12-2016 | 1/11 | Plum work in progress | Vikas Vyas | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
12. | 29-12-2016 | 1/12 | Plum work in progress | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
13. | 21-12-2016 | Ch 1/12 | Material collection for damaged R.W reconstruction | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
14. | 13-12-2016 | 1/12 | Material for protection work collected no labour found | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
15. | 07-12-2016 | 2/11 -12 | Excavation for plum and wire crate | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
16. | 14-11-2016 | 0/14 | no work in progress at site | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
17. | 21-09-2016 | 1/16 | curve correction required | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
18. | 13-09-2016 | 1+209 | Site visit with TL and re sir | Neeraj Pathak | QC | DSC1 R&B WB Uttarkashi | See Pic |
19. | 10-09-2016 | 1+250 | Slope provided wrongly on breast wall.Instructed for the rectification | Sam Allen Matthews | TL | DSC1 R&B WB | See Pic |
20. | 10-09-2016 | 1+250 | Inspecting the damaged retaining wall (instructed to replace the wall as it will come under insurance coverage) | Sam Allen Matthews | TL | DSC1 R&B WB | See Pic |
|
|