Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Gadh-Dewal molthat motor road Work Completed
Project: UDRP-RB UID: 3135 Sanction Cost: 339.22  lakh Length: 3.850 KM.
District: Uttarkashi Block: Naugaon Constituency: Purola Circle: Rudraprayag WB Circle
DEA: DEA Uttarkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 86        Package Name:  UDRP/PWD/01/34/RD/075        Tender Date: 29-12-2014        Current Status: Agreement signed        Achieved on Date: 04-06-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/01/34/RD/075      Contractor Name: People Concern Towards Social Realities
Start Date:  11-06-2015      Intended Completion Date:  31-01-2017      Original End Date:  10-09-2016
Total Bond Cost: 30060931.63 (300.61 lakh)        Variation Cost: 1206824.25 (12.07 lakh)    Hence Total Bond Cost is   31267755.88 (312.68 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 420840 for 28 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence3.85 KM12.9911-06-201528-02-20163.85 KM3.85 KM4.5212.99
2.R/Wall, B/ Wall Type Protection works2075.00 m118.9611-06-201531-12-20152075.00 m2075.00 m41.4118.96
3.GSB/RBI/G-10.00 KM0.0001-08-201531-10-20150.00 KM0.00 KM00.00
4.G-23.85 KM38.6601-08-201515-06-20163.85 KM3.85 KM13.4638.66
5.G-33.85 KM27.2901-02-201615-09-20163.85 KM3.85 KM9.527.29
6.PC/CC i/c Prime Coat, Tack Coat3.85 KM45.7801-04-201610-11-20163.85 KM3.85 KM15.9345.78
7.Culverts/Scupper 16.00 No36.5601-09-201531-03-201616.00 No16.00 No12.7236.56
8.longitudinal Drain3800.00 m6.4601-11-201530-09-20163800.00 m3800.00 m2.256.46
9.Crash Barrier0.00 m0.0026-11-201615-12-20160.00 m0.00 m00.00
10.Parapet0.00 No0.0001-12-201631-12-20160.00 No0.00 No00.00
11.Road Furniture13.00 No0.6201-03-201630-11-201613.00 No13.00 No0.220.62
Total Amount: 287.32 100   287.32
Remarks: No Remarks       Work Program Made On: 11-08-2015        Updation of work program on: 20-05-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.17-September-201517.00  lakh
2.30-September-201535.63  lakh
3.21-January-201635.89  lakh
4.06-February-20160.06  lakh
5.26-February-201611.58  lakh
6.30-March-201638.78  lakh
7.26-May-201616.19  lakh
8.07-September-201623.63  lakh
9.10-October-201620.73  lakh
10.31-December-201654.06  lakh
11.11-January-201714.20  lakh
12.10-April-201715.24  lakh
13.18-May-20179.69  lakh
14.17-June-201713.62  lakh
15.08-December-201713.28  lakh
16.13-March-2018-8.09  lakh
Total 311.49  lakh
% Payment 99.63 %
Advance Amount:  121.93  lakh        Recovered Amount:  121.97  lakh        Balance to be Recovered  -0.04  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 227   No. of Test Done : 251    No. of Test Passed : 235   No. of Test Failed : 16   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 87.93
Number of Notice(s) issued: 116

Mobile Pic Upload

Number of Pics Available on Web Repository: 218
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.05-05-2017Ch 1+500Track route for VillageVijayraj SinghJEUDRP R&B Uttarkashi See Pic
2.05-05-2017Ch- 0+300Painted Parapet.Vijayraj SinghJEUDRP R&B Uttarkashi See Pic
3.01-01-20173+300Discussion regarding site issues with villagers at Garh dewalPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
4.01-12-20161+600PC thickness found OKPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
5.01-12-20161+625Seal coat rolling in progressPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
6.27-10-2016Km 3+550PC work in progressBaru SinghSite SupervisorDSC1 R&B WB Uttarkahsi See Pic
7.27-10-2016Km 3+600PC workBaru SinghSite SupervisorDSC1 R&B WB Uttarkahsi See Pic
8.27-10-2016Km 3+580PC work in progressBaru SinghSite SupervisorDSC1 R&B WB Uttarkahsi See Pic
9.25-10-20163+800Premix CarpetBaru SinghSite SupervisorDSC1 R&B WB Uttarkahsi See Pic
10.25-10-2016Km 3+750Site Visit SE sir EE sir and RE sirBaru SinghSite SupervisorDSC1 R&B WB Uttarkahsi See Pic
11.25-10-2016Km 3+100Mix roll and Bitumen at Garh Dewal motor roadBaru SinghSite SupervisorDSC1 R&B WB Uttarkahsi See Pic
12.19-10-20163/4machinery &material for PC work arranged at sitePraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
13.18-10-20162+800Sieve analysis for wbm g-3Baru SinghSite SupervisorDSC1 R&B WB Uttarkahsi See Pic
14.18-10-2016Km 2+810Sieve analysis for WBM G-3Baru SinghSite SupervisorDSC1 R&B WB Uttarkahsi See Pic
15.06-10-2016Km 3+450Checking of Width for WBM G-3Baru SinghSite SupervisorDSC1 R&B WB Uttarkahsi See Pic
16.28-09-2016Km 3+630Sieve analysis for WBM G-3Baru SinghSite SupervisorDSC1 R&B WB Uttarkahsi See Pic
17.25-09-20160+100AIV TEST result found satisfactoryPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
18.25-09-2016site lab at ch 0+100AIV test of 20mm aggregatePraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
19.25-09-20163+770sieve analyses for G 2 aggrigate found okPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
20.25-09-20161+120G3layer material collection in progressPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic