Ranari to Danda Majaf MR
Work Completed
|
Project: |
UDRP-RB |
UID: |
3133 |
Sanction Cost: |
376.32 lakh |
Length:
|
4.600 KM. |
District: |
Uttarkashi |
Block: |
Dunda |
Constituency: |
Gangotri |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Uttarkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 32
Package Name: 
UDRP/PWD/01/30/RD/032
Tender Date: 21-10-2014
Current Status: Agreement signed
Achieved on Date: 03-06-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/01/30/RD/032
Contractor Name: Dilawar Singh Contractor
|
Start Date: 10-06-2015
Intended Completion Date: 17-11-2016
Original End Date: 09-09-2016 |
Total Bond Cost: 38718032.06 (387.18 lakh)
Variation Cost: 3263774.37 (32.64 lakh) Hence Total Bond Cost is 41981806.43 (419.82 lakh)
|
Sub Project Cost: 340.73 lakh
Variation Cost of Sub Project: 3335458.30 (33.35 lakh)
Total Sub Project Cost:
374.08 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 522693 for 27 days
LD Analysis for Milestone2: calculated LD is Rs 1684233 for 87 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 4.00 KM | 13.15 | 01-09-2015 | 30-09-2016 | 4.00 KM | 4.00 KM | 4.06 | 13.15 | 2. | R/Wall, B/ Wall Type Protection works | 2119.00 m | 88.02 | 22-06-2015 | 30-11-2015 | 2119.00 m | 2119.00 m | 27.19 | 88.02 | 3. | GSB/RBI/G-1 | 4.60 KM | 35.55 | 22-06-2015 | 30-06-2016 | 4.60 KM | 4.60 KM | 10.98 | 35.55 | 4. | G-2 | 4.60 KM | 25.93 | 01-08-2015 | 10-08-2016 | 4.60 KM | 4.60 KM | 8.01 | 25.93 | 5. | G-3 | 4.60 KM | 33.88 | 01-09-2015 | 30-09-2016 | 4.60 KM | 4.60 KM | 10.46 | 33.88 | 6. | PC/CC i/c Prime Coat, Tack Coat | 4.60 KM | 63.11 | 15-04-2016 | 15-11-2016 | 4.60 KM | 4.60 KM | 19.49 | 63.11 | 7. | Cause Way | 1.00 No | 17.03 | 01-09-2015 | 30-06-2016 | 1.00 No | 1.00 No | 5.26 | 17.03 | 8. | Culverts/Scupper | 15.00 No | 26.96 | 15-07-2015 | 31-03-2016 | 15.00 No | 15.00 No | 8.33 | 26.96 | 9. | longitudinal Drain | 4500.00 m | 19.69 | 20-07-2015 | 26-11-2016 | 4500.00 m | 4500.00 m | 6.08 | 19.69 | 10. | Crash Barrier | 0.00 m | 0.00 | 01-03-2016 | 26-11-2016 | 0.00 m | 0.00 m | 0 | 0.00 | 11. | Road Furniture | 12.00 No | 0.46 | 01-03-2016 | 26-11-2016 | 12.00 No | 12.00 No | 0.14 | 0.46 |
Total Amount: |
323.78 |
|
100 |
323.78 |
|
Remarks:
No Remarks
Work Program Made On:
11-08-2015 } ?>
Updation of work program on:
16-03-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 26-September-2015 | 34.69 lakh | 2. | 28-October-2015 | 23.62 lakh | 3. | 18-February-2016 | 13.04 lakh | 4. | 29-March-2016 | 28.36 lakh | 5. | 22-June-2016 | 47.04 lakh | 6. | 15-August-2016 | 33.77 lakh | 7. | 24-September-2016 | 26.38 lakh | 8. | 03-October-2016 | 26.00 lakh | 9. | 26-October-2016 | 62.50 lakh | 10. | 31-January-2017 | 14.62 lakh | 11. | 24-March-2017 | 11.19 lakh | 12. | 30-June-2017 | 24.11 lakh | 13. | 13-October-2017 | 20.41 lakh | 14. | 23-December-2017 | 3.35 lakh | 15. | 16-May-2018 | 4.20 lakh |
Total |
373.28 lakh |
% Payment | 99.79 % |
|
Advance Amount: 60.61 lakh
Recovered Amount: 60.61 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 328 No. of Test Done : 380 No. of Test Passed : 361 No. of Test Failed : 19 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 80.80 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 347 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 09-11-2017 | Km2 | Site inspaction by SE Sir | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
2. | 05-11-2017 | Ch. 2/17 | Repairs of PC surface | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
3. | 05-11-2017 | Ch2/28 | Repairs work in progress | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
4. | 02-11-2017 | Ch0/2 | Dispute discussion local representatives with EE, Ae, and contractor, at danda majaf Mr | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
5. | 02-11-2017 | Km2 | Patch work on progress | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
6. | 02-11-2017 | Ch0/3 | Site visit regarding local dispute | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
7. | 02-11-2017 | Ch0/1 | Patch work completed at danda majaf Mr. | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
8. | 31-10-2017 | 2/18 | Patch work on progress | Bhupendra Singh Rathore | RE | DSC4 R&B WB Uttarkashi | See Pic |
9. | 31-10-2017 | 2/17 | Patch work on progress | Bhupendra Singh Rathore | RE | DSC4 R&B WB Uttarkashi | See Pic |
10. | 31-10-2017 | 4/20 | Patch Work | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
11. | 30-10-2017 | Ch2/17 | Pc layer depth checking | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
12. | 30-10-2017 | 3/2 | Parapet painting work on progress | Bhupendra Singh Rathore | RE | DSC4 R&B WB Uttarkashi | See Pic |
13. | 30-10-2017 | 2/28 | Whitewashing on road safety parapet | Bhupendra Singh Rathore | RE | DSC4 R&B WB Uttarkashi | See Pic |
14. | 30-10-2017 | 2/16 | Patch work on progress | Bhupendra Singh Rathore | RE | DSC4 R&B WB Uttarkashi | See Pic |
15. | 30-10-2017 | Ch3/2 | Culvert panting work complete | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
16. | 30-10-2017 | Ch2/28 | Parapet white washing work complete in mantion ch | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
17. | 30-10-2017 | Ch2/33 | Patch work on progress | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
18. | 26-10-2017 | 4/3 | Patch work on progress | Bhupendra Singh Rathore | RE | DSC4 R&B WB Uttarkashi | See Pic |
19. | 25-10-2017 | 4/3 | Patch work on progress | Bhupendra Singh Rathore | RE | DSC4 R&B WB Uttarkashi | See Pic |
20. | 06-01-2017 | 2/7 | Dry wall | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
|
|