Chadethi-Raitha Motor Road
Work Completed
|
Project: |
UDRP-RB |
UID: |
3130 |
Sanction Cost: |
351.89 lakh |
Length:
|
2.030 KM. |
District: |
Uttarkashi |
Block: |
Bhatwari |
Constituency: |
Gangotri |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Uttarkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 82
Package Name: 
UDRP/PWD/01/31/RD/071
Tender Date: 11-09-2015
Current Status: Agreement signed
Achieved on Date: 20-02-2016 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/01/31/RD/071
Contractor Name: Parth Construction
|
Start Date: 27-02-2016
Intended Completion Date: 28-02-2018
Original End Date: 26-12-2016 |
Total Bond Cost: 35940985.37 (359.41 lakh)
Variation Cost: 29465244.98 (294.65 lakh) Hence Total Bond Cost is 65406230.35 (654.06 lakh)
|
Sub Project Cost: 157.51 lakh
Variation Cost of Sub Project: 18793833.22 (187.94 lakh)
Total Sub Project Cost:
345.45 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 2282190 for 127 days
LD Analysis for Milestone2: calculated LD is Rs 3899490 for 217 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 2.10 KM | 9.71 | 27-02-2016 | 15-06-2017 | 2.10 KM | 2.10 KM | 3.68 | 9.71 | 2. | R/Wall, B/ Wall Type Protection works | 588.00 m | 152.10 | 27-02-2016 | 31-12-2017 | 588.00 m | 588.00 m | 57.6 | 152.10 | 3. | G-2 | 1.00 KM | 14.76 | 10-08-2017 | 20-11-2017 | 1.00 KM | 1.00 KM | 5.59 | 14.76 | 4. | G-3 | 1.00 KM | 7.27 | 01-09-2017 | 30-11-2017 | 1.00 KM | 1.00 KM | 2.75 | 7.27 | 5. | PC/CC i/c Prime Coat, Tack Coat | 2.10 KM | 25.88 | 15-11-2017 | 28-02-2018 | 2.10 KM | 2.10 KM | 9.8 | 25.88 | 6. | Culverts/Scupper | 2.00 No | 5.51 | 15-11-2017 | 10-12-2017 | 2.00 No | 2.00 No | 2.09 | 5.51 | 7. | longitudinal Drain | 1700.00 m | 42.66 | 15-09-2017 | 28-02-2018 | 1700.00 m | 1700.00 m | 16.16 | 42.66 | 8. | Crash Barrier | 0.00 m | 0.00 | 01-01-2017 | 30-05-2017 | 0.00 m | 0.00 m | 0 | 0.00 | 9. | Parapet | 200.00 No | 5.19 | 01-01-2018 | 28-02-2018 | 200.00 No | 200.00 No | 1.97 | 5.19 | 10. | Road Furniture | 26.00 No | 0.96 | 01-11-2016 | 15-01-2018 | 26.00 No | 26.00 No | 0.36 | 0.96 |
Total Amount: |
264.04 |
|
100 |
264.04 |
|
Remarks:
No Remarks
Work Program Made On:
18-05-2016 } ?>
Updation of work program on:
28-03-2018
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 22-July-2016 | 11.18 lakh | 2. | 14-September-2016 | 5.13 lakh | 3. | 14-October-2016 | 11.62 lakh | 4. | 16-December-2016 | 21.28 lakh | 5. | 02-March-2017 | 30.99 lakh | 6. | 17-June-2017 | 23.17 lakh | 7. | 31-July-2017 | 17.91 lakh | 8. | 29-August-2017 | 13.81 lakh | 9. | 13-October-2017 | 20.64 lakh | 10. | 20-November-2017 | 7.69 lakh | 11. | 27-November-2017 | 41.05 lakh | 12. | 23-December-2017 | 1.13 lakh | 13. | 17-February-2018 | 5.56 lakh | 14. | 26-March-2018 | 31.02 lakh | 15. | 31-May-2018 | 49.50 lakh | 16. | 29-September-2018 | 54.75 lakh |
Total |
346.43 lakh |
% Payment | 100.28 % |
|
Advance Amount: 12.06 lakh
Recovered Amount: 12.06 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 315 No. of Test Done : 588 No. of Test Passed : 561 No. of Test Failed : 27 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 91.97 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 99 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 05-12-2017 | Ch 0.600 | Using zycotherm for PC work | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
2. | 25-11-2017 | Ch 1.875 | PC thickness checking | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
3. | 24-11-2017 | Ch0+800 | WBM G2 layer water curing on progress | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
4. | 24-11-2017 | Ch1+675 | R/wall work on progress | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
5. | 24-11-2017 | Ch1+870 | Premix carpet layer thickness checking | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
6. | 24-11-2017 | Km2 | Premix carpet laying work on progress | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
7. | 05-11-2017 | Ch 1.400 | Plum concrete work in progress | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
8. | 02-11-2017 | C0+450 | Site cleaning work on progress | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
9. | 02-11-2017 | Ch0+310 | Water sprinkle at wbm g2 layer | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
10. | 02-11-2017 | Ch0+250 | Wbm g2 layer thickness checking | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
11. | 02-11-2017 | Ch0+200 | Wbm g2 rolling work on progress | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
12. | 02-11-2017 | Ch0/100 | Site inspaction by SE sir | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
13. | 02-11-2017 | Ch0+290 | Wbm g2 layer thickness checking | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
14. | 02-11-2017 | Ch0+300 | Wbm g2 layer water sprinkle | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
15. | 02-11-2017 | Ch0+325 | Site cleaning work on progress | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
16. | 02-11-2017 | Ch1+400 | Site inspaction by SE sir | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
17. | 02-11-2017 | Ch1+300 | Local problem discussion | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
18. | 02-11-2017 | Ch1+050 | Site visit | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
19. | 02-11-2017 | Ch0+280 | Wbm work on progress | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
20. | 29-10-2017 | 0/38 | Wbm g2 collection | Bhupendra Singh Rathore | RE | DSC4 R&B WB Uttarkashi | See Pic |
|
|