Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Chadethi-Raitha Motor Road Work Completed
Project: UDRP-RB UID: 3130 Sanction Cost: 351.89  lakh Length: 2.030 KM.
District: Uttarkashi Block: Bhatwari Constituency: Gangotri Circle: Rudraprayag WB Circle
DEA: DEA Uttarkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 82        Package Name:  UDRP/PWD/01/31/RD/071        Tender Date: 11-09-2015        Current Status: Agreement signed        Achieved on Date: 20-02-2016

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/01/31/RD/071      Contractor Name: Parth Construction
Start Date:  27-02-2016      Intended Completion Date:  28-02-2018      Original End Date:  26-12-2016
Total Bond Cost: 35940985.37 (359.41 lakh)        Variation Cost: 29465244.98 (294.65 lakh)    Hence Total Bond Cost is   65406230.35 (654.06 lakh) 
Sub Project Cost: 157.51  lakh        Variation Cost of Sub Project: 18793833.22  (187.94 lakh)       Total Sub Project Cost:   345.45 lakh
LD Analysis for Milestone1: calculated LD is Rs 2282190 for 127 days        LD Analysis for Milestone2: calculated LD is Rs 3899490 for 217 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence2.10 KM9.7127-02-201615-06-20172.10 KM2.10 KM3.689.71
2.R/Wall, B/ Wall Type Protection works588.00 m152.1027-02-201631-12-2017588.00 m588.00 m57.6152.10
3.G-21.00 KM14.7610-08-201720-11-20171.00 KM1.00 KM5.5914.76
4.G-31.00 KM7.2701-09-201730-11-20171.00 KM1.00 KM2.757.27
5.PC/CC i/c Prime Coat, Tack Coat2.10 KM25.8815-11-201728-02-20182.10 KM2.10 KM9.825.88
6.Culverts/Scupper 2.00 No5.5115-11-201710-12-20172.00 No2.00 No2.095.51
7.longitudinal Drain1700.00 m42.6615-09-201728-02-20181700.00 m1700.00 m16.1642.66
8.Crash Barrier0.00 m0.0001-01-201730-05-20170.00 m0.00 m00.00
9.Parapet200.00 No5.1901-01-201828-02-2018200.00 No200.00 No1.975.19
10.Road Furniture26.00 No0.9601-11-201615-01-201826.00 No26.00 No0.360.96
Total Amount: 264.04 100   264.04
Remarks: No Remarks       Work Program Made On: 18-05-2016        Updation of work program on: 28-03-2018       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.22-July-201611.18  lakh
2.14-September-20165.13  lakh
3.14-October-201611.62  lakh
4.16-December-201621.28  lakh
5.02-March-201730.99  lakh
6.17-June-201723.17  lakh
7.31-July-201717.91  lakh
8.29-August-201713.81  lakh
9.13-October-201720.64  lakh
10.20-November-20177.69  lakh
11.27-November-201741.05  lakh
12.23-December-20171.13  lakh
13.17-February-20185.56  lakh
14.26-March-201831.02  lakh
15.31-May-201849.50  lakh
16.29-September-201854.75  lakh
Total 346.43  lakh
% Payment100.28 %
Advance Amount:  12.06  lakh        Recovered Amount:  12.06  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 315   No. of Test Done : 588    No. of Test Passed : 561   No. of Test Failed : 27   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 91.97
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 99
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.05-12-2017Ch 0.600Using zycotherm for PC workNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
2.25-11-2017Ch 1.875PC thickness checkingNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
3.24-11-2017Ch0+800WBM G2 layer water curing on progressNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
4.24-11-2017Ch1+675R/wall work on progressNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
5.24-11-2017Ch1+870Premix carpet layer thickness checkingNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
6.24-11-2017Km2Premix carpet laying work on progressNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
7.05-11-2017Ch 1.400Plum concrete work in progressNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
8.02-11-2017C0+450Site cleaning work on progressNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
9.02-11-2017Ch0+310Water sprinkle at wbm g2 layerNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
10.02-11-2017Ch0+250Wbm g2 layer thickness checkingNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
11.02-11-2017Ch0+200Wbm g2 rolling work on progressNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
12.02-11-2017Ch0/100Site inspaction by SE sirNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
13.02-11-2017Ch0+290Wbm g2 layer thickness checkingNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
14.02-11-2017Ch0+300Wbm g2 layer water sprinkleNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
15.02-11-2017Ch0+325Site cleaning work on progressNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
16.02-11-2017Ch1+400Site inspaction by SE sirNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
17.02-11-2017Ch1+300Local problem discussionNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
18.02-11-2017Ch1+050Site visitNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
19.02-11-2017Ch0+280Wbm work on progressNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
20.29-10-20170/38Wbm g2 collectionBhupendra Singh RathoreREDSC4 R&B WB Uttarkashi See Pic