Bhukki Kujjan Tihaar Motor Road
Work Completed
|
Project: |
UDRP-RB |
UID: |
3126 |
Sanction Cost: |
176.64 lakh |
Length:
|
5.000 KM. |
District: |
Uttarkashi |
Block: |
Bhatwari |
Constituency: |
Gangotri |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Uttarkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 33
Package Name: 
UDRP/PWD/01/31/RD/033
Tender Date: 14-08-2014
Current Status: Agreement signed
Achieved on Date: 04-06-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/01/31/RD/033
Contractor Name: Arya Construction
|
Start Date: 11-06-2015
Intended Completion Date: 31-07-2017
Original End Date: 10-09-2016 |
Total Bond Cost: 30095179.78 (300.95 lakh)
Variation Cost: 12251575.02 (122.52 lakh) Hence Total Bond Cost is 42346754.8 (423.47 lakh)
|
Sub Project Cost: 163.89 lakh
Variation Cost of Sub Project: 2008151.89 (20.08 lakh)
Total Sub Project Cost:
183.97 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 1820808 for 121 days
LD Analysis for Milestone2: calculated LD is Rs 5567760 for 370 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 0.30 KM | 10.54 | 01-05-2016 | 31-12-2016 | 0.30 KM | 0.30 KM | 7.16 | 10.54 | 2. | R/Wall, B/ Wall Type Protection works | 1147.00 m | 58.90 | 01-07-2015 | 30-05-2017 | 1147.00 m | 1147.00 m | 40.03 | 58.90 | 3. | GSB/RBI/G-1 | 2.20 KM | 7.80 | 01-09-2015 | 15-02-2017 | 2.20 KM | 2.20 KM | 5.3 | 7.80 | 4. | G-2 | 2.20 KM | 9.87 | 01-10-2015 | 28-02-2017 | 2.20 KM | 2.20 KM | 6.71 | 9.87 | 5. | G-3 | 2.20 KM | 10.21 | 01-12-2016 | 15-03-2017 | 2.20 KM | 2.20 KM | 6.94 | 10.21 | 6. | PC/CC i/c Prime Coat, Tack Coat | 2.20 KM | 27.41 | 22-04-2017 | 15-05-2017 | 2.20 KM | 2.20 KM | 18.63 | 27.41 | 7. | Cause Way | 2.00 No | 3.28 | 01-10-2015 | 31-01-2016 | 2.00 No | 2.00 No | 2.23 | 3.28 | 8. | Culverts/Scupper | 5.00 No | 10.15 | 01-10-2015 | 31-03-2016 | 5.00 No | 5.00 No | 6.9 | 10.15 | 9. | longitudinal Drain | 4700.00 m | 8.74 | 01-12-2015 | 31-07-2017 | 4700.00 m | 4700.00 m | 5.94 | 8.74 | 10. | Crash Barrier | 0.00 m | 0.00 | 15-06-2017 | 30-06-2017 | 0.00 m | 0.00 m | 0 | 0.00 | 11. | Parapet | 0.00 No | 0.00 | 01-03-2017 | 31-03-2017 | 0.00 No | 0.00 No | 0 | 0.00 | 12. | Road Furniture | 25.00 No | 0.24 | 01-12-2015 | 30-06-2017 | 25.00 No | 25.00 No | 0.16 | 0.24 |
Total Amount: |
147.14 |
|
100 |
147.14 |
|
Remarks:
No Remarks
Work Program Made On:
11-08-2015 } ?>
Updation of work program on:
13-08-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 26-September-2015 | 5.00 lakh | 2. | 30-September-2015 | 3.67 lakh | 3. | 19-December-2015 | 0.03 lakh | 4. | 19-February-2016 | 6.81 lakh | 5. | 11-March-2016 | 9.98 lakh | 6. | 30-March-2016 | 2.74 lakh | 7. | 27-October-2016 | 5.43 lakh | 8. | 09-December-2016 | 10.93 lakh | 9. | 11-January-2017 | 15.50 lakh | 10. | 29-March-2017 | 11.73 lakh | 11. | 18-May-2017 | 42.33 lakh | 12. | 30-June-2017 | 0.07 lakh | 13. | 31-July-2017 | 10.08 lakh | 14. | 12-October-2017 | 4.60 lakh | 15. | 27-November-2017 | 8.66 lakh | 16. | 23-December-2017 | 0.58 lakh | 17. | 17-February-2018 | 28.53 lakh | 18. | 21-April-2018 | 12.44 lakh | 19. | 31-May-2018 | 7.05 lakh | 20. | 15-July-2019 | 4.59 lakh |
Total |
190.75 lakh |
% Payment | 103.69 % |
|
Advance Amount: 70.90 lakh
Recovered Amount: 70.90 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 281 No. of Test Done : 361 No. of Test Passed : 338 No. of Test Failed : 23 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 85.96 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 76 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 30-10-2017 | Ch2/39 | Slip cleaning | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
2. | 17-10-2017 | Ch2/40 | Site visit with EE sir | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
3. | 16-10-2017 | Ch0/26 | Site inspaction by EE sir regarding site hand over progress | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
4. | 15-10-2017 | Ch0/36 | Slip cleaning | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
5. | 30-08-2017 | Ch 2/7 | Slip from PMGSY new cutting | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
6. | 21-04-2017 | Ch 2/3 | Bitumen supply for PC | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
7. | 08-02-2017 | Excavation in foundations for B/wall km 4/12 | Excavation in foundations for B /wall work in progress | Sadhan Negi | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
8. | 15-01-2017 | 2/7 | KC drain 50mtr rejected due to poor quality | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
9. | 11-01-2017 | Ch 2/6 -2/7 | K.C drain rejected poor workmanship | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
10. | 31-12-2016 | R.R.Dry wall km 1/22 | Dry wall work in progress | Sadhan Negi | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
11. | 26-12-2016 | Ch 2/7 | KC drain rejected due to alignment and without compaction | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
12. | 21-12-2016 | Ch 1/22 | HP stone filling backside of R/W | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
13. | 21-12-2016 | Ch 1/7 | G1 relaying after removal | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
14. | 12-12-2016 | WBM G. 2 km 2/3 | WBM G 2 | Sadhan Negi | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
15. | 04-12-2016 | WBM G. 1 KM 1/225 | WBM G 1 work in progress | Sadhan Negi | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
16. | 14-10-2016 | Aiv testing km 1/22 | Avi test | Sadhan Negi | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
17. | 14-10-2016 | Se sir site visit | WBM G.1 Rejected | Sadhan Negi | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
18. | 13-10-2016 | 1/8 | G1 layer rejected 1/4 to 1/18 due to oversize, excessive blinding and working without RFI | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
19. | 29-09-2016 | 0+975 | G2 material collected | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
20. | 25-09-2016 | WBM. G.2 Rejected km 2/850 | WBM.Rejected | Sadhan Negi | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
|
|