Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Bhukki Kujjan Tihaar Motor Road Work Completed
Project: UDRP-RB UID: 3126 Sanction Cost: 176.64  lakh Length: 5.000 KM.
District: Uttarkashi Block: Bhatwari Constituency: Gangotri Circle: Rudraprayag WB Circle
DEA: DEA Uttarkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision Type: VR
Procurement:
Package No.: 33        Package Name:  UDRP/PWD/01/31/RD/033        Tender Date: 14-08-2014        Current Status: Agreement signed        Achieved on Date: 04-06-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/01/31/RD/033      Contractor Name: Arya Construction
Start Date:  11-06-2015      Intended Completion Date:  31-07-2017      Original End Date:  10-09-2016
Total Bond Cost: 30095179.78 (300.95 lakh)        Variation Cost: 12251575.02 (122.52 lakh)    Hence Total Bond Cost is   42346754.8 (423.47 lakh) 
Sub Project Cost: 163.89  lakh        Variation Cost of Sub Project: 2008151.89  (20.08 lakh)       Total Sub Project Cost:   183.97 lakh
LD Analysis for Milestone1: calculated LD is Rs 1820808 for 121 days        LD Analysis for Milestone2: calculated LD is Rs 5567760 for 370 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence0.30 KM10.5401-05-201631-12-20160.30 KM0.30 KM7.1610.54
2.R/Wall, B/ Wall Type Protection works1147.00 m58.9001-07-201530-05-20171147.00 m1147.00 m40.0358.90
3.GSB/RBI/G-12.20 KM7.8001-09-201515-02-20172.20 KM2.20 KM5.37.80
4.G-22.20 KM9.8701-10-201528-02-20172.20 KM2.20 KM6.719.87
5.G-32.20 KM10.2101-12-201615-03-20172.20 KM2.20 KM6.9410.21
6.PC/CC i/c Prime Coat, Tack Coat2.20 KM27.4122-04-201715-05-20172.20 KM2.20 KM18.6327.41
7.Cause Way2.00 No3.2801-10-201531-01-20162.00 No2.00 No2.233.28
8.Culverts/Scupper 5.00 No10.1501-10-201531-03-20165.00 No5.00 No6.910.15
9.longitudinal Drain4700.00 m8.7401-12-201531-07-20174700.00 m4700.00 m5.948.74
10.Crash Barrier0.00 m0.0015-06-201730-06-20170.00 m0.00 m00.00
11.Parapet0.00 No0.0001-03-201731-03-20170.00 No0.00 No00.00
12.Road Furniture25.00 No0.2401-12-201530-06-201725.00 No25.00 No0.160.24
Total Amount: 147.14 100   147.14
Remarks: No Remarks       Work Program Made On: 11-08-2015        Updation of work program on: 13-08-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.26-September-20155.00  lakh
2.30-September-20153.67  lakh
3.19-December-20150.03  lakh
4.19-February-20166.81  lakh
5.11-March-20169.98  lakh
6.30-March-20162.74  lakh
7.27-October-20165.43  lakh
8.09-December-201610.93  lakh
9.11-January-201715.50  lakh
10.29-March-201711.73  lakh
11.18-May-201742.33  lakh
12.30-June-20170.07  lakh
13.31-July-201710.08  lakh
14.12-October-20174.60  lakh
15.27-November-20178.66  lakh
16.23-December-20170.58  lakh
17.17-February-201828.53  lakh
18.21-April-201812.44  lakh
19.31-May-20187.05  lakh
20.15-July-20194.59  lakh
Total 190.75  lakh
% Payment103.69 %
Advance Amount:  70.90  lakh        Recovered Amount:  70.90  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 281   No. of Test Done : 361    No. of Test Passed : 338   No. of Test Failed : 23   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 85.96
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 76
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.30-10-2017Ch2/39Slip cleaningNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
2.17-10-2017Ch2/40Site visit with EE sirNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
3.16-10-2017Ch0/26Site inspaction by EE sir regarding site hand over progressNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
4.15-10-2017Ch0/36Slip cleaningNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
5.30-08-2017Ch 2/7Slip from PMGSY new cuttingNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
6.21-04-2017Ch 2/3Bitumen supply for PCNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
7.08-02-2017Excavation in foundations for B/wall km 4/12Excavation in foundations for B /wall work in progressSadhan NegiSite SupervisorDSC1 R&B WB Uttarkashi See Pic
8.15-01-20172/7KC drain 50mtr rejected due to poor qualityPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
9.11-01-2017Ch 2/6 -2/7K.C drain rejected poor workmanshipNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
10.31-12-2016R.R.Dry wall km 1/22Dry wall work in progressSadhan NegiSite SupervisorDSC1 R&B WB Uttarkashi See Pic
11.26-12-2016Ch 2/7KC drain rejected due to alignment and without compactionNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
12.21-12-2016Ch 1/22HP stone filling backside of R/WNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
13.21-12-2016Ch 1/7G1 relaying after removalNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
14.12-12-2016WBM G. 2 km 2/3WBM G 2Sadhan NegiSite SupervisorDSC1 R&B WB Uttarkashi See Pic
15.04-12-2016WBM G. 1 KM 1/225WBM G 1 work in progressSadhan NegiSite SupervisorDSC1 R&B WB Uttarkashi See Pic
16.14-10-2016Aiv testing km 1/22Avi testSadhan NegiSite SupervisorDSC1 R&B WB Uttarkashi See Pic
17.14-10-2016Se sir site visitWBM G.1 RejectedSadhan NegiSite SupervisorDSC1 R&B WB Uttarkashi See Pic
18.13-10-20161/8G1 layer rejected 1/4 to 1/18 due to oversize, excessive blinding and working without RFIPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
19.29-09-20160+975G2 material collectedPraveen GuptaREDSC1 R&B WB Uttarkashi See Pic
20.25-09-2016WBM. G.2 Rejected km 2/850WBM.RejectedSadhan NegiSite SupervisorDSC1 R&B WB Uttarkashi See Pic